Jaltech Africa Capital (Pty) Ltd and Others v Alleyroads Power (Pty) Ltd and Others (2025/091612) [2025] ZAGPJHC 660 (2 July 2025)

Jaltech Africa Capital (Pty) Ltd and Others v Alleyroads Power (Pty) Ltd and Others (2025/091612) [2025] ZAGPJHC 660 (2 July 2025)

The applicants established a clear contractual right to deactivate the electricity supply system for emergency repairs, maintenance, and interference with safe operation. The respondents interfered with the system, removed components without approval, and failed to pay outstanding amounts, resulting in ongoing...

Source-derived case information.

Citation
[2025] ZAGPJHC 660
Parties
Applicant: Jaltech Africa Capital (Pty) Ltd; Applicant: Jaltech SP 1 Partnership en Commandite; Applicant: Jaltech SP September 2023 Partnership en Commandite; Respondent: Alleyroads Power (Pty) Ltd; Respondent: Blockpower (Pty) Ltd; Respondent: Bridge City Housing Consortium (Pty) Ltd; Respondent: Sivula South Africa (Pty) Ltd
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
2025/091612
Procedural Posture
Urgent Application / Final Determination of Urgent Application for Interdict and Relief
Outcome
Application granted. Final interdict and relief ordered in favour of applicants.
Judges
Allen AJ
Legal Topics
Final Interdict, Specific Performance, Urgent Interdict, Contractual Dispute Resolution, Electricity Supply Agreement
Civil Procedure Commercial and Corporate Final Interdict Specific Performance Urgent Interdict Contractual Dispute Resolution Electricity Supply Agreement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Jaltech Africa Capital (Pty) Ltd

Applicant

Jaltech SP 1 Partnership en Commandite

Applicant

Jaltech SP September 2023 Partnership en Commandite

Applicant

Alleyroads Power (Pty) Ltd

Respondent

Blockpower (Pty) Ltd

Respondent

Bridge City Housing Consortium (Pty) Ltd

Respondent

Sivula South Africa (Pty) Ltd

Respondent

Procedural Posture

Urgent Application / Final Determination of Urgent Application for Interdict and Relief

  1. 1 Whether the applicants are entitled to deactivate the electricity supply system for emergency repairs and maintenance.
  2. 2 Whether respondents may be interdicted from interfering with or reactivating the system without applicants' consent.
  3. 3 Whether the applicants have a clear right and face irreparable harm absent relief.

Ratio Decidendi

The applicants established a clear contractual right to deactivate the electricity supply system for emergency repairs, maintenance, and interference with safe operation. The respondents interfered with the system, removed components without approval, and failed to pay outstanding amounts, resulting in ongoing financial loss and risk of irreparable harm to the system valued at over R20 million. The dispute resolution clause does not preclude urgent interim relief, and the respondents are obliged to continue payment pending dispute resolution. The requirements for a final interdict are satisfied, and the applicants are entitled to the relief sought, including deactivation of the system,...

Court Disposition

Application granted. Final interdict and relief ordered in favour of applicants.

Orders

  • The forms and service provided for in the rules are dispensed with and the matter is heard as one of urgency in accordance with Rule 6(12).
  • Applicants are authorized to turn off and deactivate the 380 KWP Solar PV and 1000 KWP Battery Electricity Generating Storage and Supply System known as Chiawelo Phase 2 at Wasani Heights Apartment Block, Chiawelo, Soweto.