Johannesburg Development Agency (Pty) Ltd v Federated Insurance Guarantees Brokers (Pty) Ltd (6647/06) [2007] ZAKZHC 57 (30 April 2007)

Johannesburg Development Agency (Pty) Ltd v Federated Insurance Guarantees Brokers (Pty) Ltd (6647/06) [2007] ZAKZHC 57 (30 April 2007)

The court held that the construction guarantee issued by the respondent is a principal obligation, not accessory to the contractor's obligations. Upon cancellation of the contract due to the contractor's default and receipt by the respondent of the first written demand complying with Clause 5.0 of the guarantee, the...

Source-derived case information.

Citation
[2007] ZAKZHC 57
Parties
Applicant: Johannesburg Development Agency (Pty) Ltd; Respondent: Federated Insurance Guarantees Brokers (Pty) Ltd
Court
High Courts - Kwazulu Natal
Jurisdiction
South Africa
Case Number
6647/06
Procedural Posture
Civil Application / Final Judgment
Outcome
Application granted in favour of the applicant.
Judges
Niles-Dun&RJ
Legal Topics
Construction Guarantee, Principal Obligation, Liquid Document, Contract Cancellation, Security for Performance
Commercial and Corporate Civil Procedure Construction Guarantee Principal Obligation Liquid Document Contract Cancellation Security for Performance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Johannesburg Development Agency (Pty) Ltd

Applicant

Federated Insurance Guarantees Brokers (Pty) Ltd

Respondent

Procedural Posture

Civil Application / Final Judgment

  1. 1 Does receipt by the respondent of the first written demand under Clause 5.0 of the guarantee alone generate liability to pay the guaranteed sum to the applicant.
  2. 2 Is the guarantee a principal obligation or an accessory obligation dependent on the contractor's indebtedness.
  3. 3 Can the respondent rely on the applicant's alleged breach to avoid liability under Clause 36.6 of the contract.

Ratio Decidendi

The court held that the construction guarantee issued by the respondent is a principal obligation, not accessory to the contractor's obligations. Upon cancellation of the contract due to the contractor's default and receipt by the respondent of the first written demand complying with Clause 5.0 of the guarantee, the respondent's liability to pay the guaranteed sum is triggered. The guarantee does not require prior proof of the contractor's indebtedness or quantum, nor does it require the issue of a payment certificate or final account before payment is due under Clause 5.0. The respondent's defence that the applicant's alleged breach invalidated the cancellation under Clause 36.6 was...

Court Disposition

Application granted in favour of the applicant.

Orders

  • The respondent is ordered to pay the applicant the sum of R1,754,279.26.
  • The respondent is ordered to pay interest thereon at the rate of 15.5% per annum from 9 March 2006 to date of payment.