Joint Venture Between Aveng (Africa) Pty Ltd and Strabag International GmbH v South African National Roads Agency Soc Ltd and Another (8331/19) [2019] ZAGPPHC 97; [2019] 3 All SA 186 (GP) (22 March 2019)

Joint Venture Between Aveng (Africa) Pty Ltd and Strabag International GmbH v South African National Roads Agency Soc Ltd and Another (8331/19) [2019] ZAGPPHC 97; [2019] 3 All SA 186 (GP) (22 March 2019)

The court found that the applicant failed to establish a legal basis for restraining SANRAL from presenting the guarantees for payment. The applicant did not prove that the events constituted Force Majeure as defined in the contract, nor that the prescribed procedures for termination were properly followed. The...

Source-derived case information.

Citation
[2019] ZAGPPHC 97
Parties
Applicant: Joint Venture Between Aveng (Africa) Pty Ltd and Strabag International GmbH; Respondent: South African National Roads Agency SOC Ltd; Respondent: Lombard Insurance Company Limited
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
8331/19
Procedural Posture
Urgent Application / Final Determination of Urgent Application for Interdictory Relief
Outcome
Application dismissed with costs.
Judges
Makhuvele
Legal Topics
Construction Guarantees, Performance Security, Force Majeure, Interdictory Relief, Fidic Contracts
Commercial and Corporate Civil Procedure Construction Guarantees Performance Security Force Majeure Interdictory Relief Fidic Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Joint Venture Between Aveng (Africa) Pty Ltd and Strabag International GmbH

Applicant

South African National Roads Agency SOC Ltd

Respondent

Lombard Insurance Company Limited

Respondent

Procedural Posture

Urgent Application / Final Determination of Urgent Application for Interdictory Relief

  1. 1 Whether the applicant is entitled to interdict the first respondent from making a claim under the performance and retention guarantees pending dispute resolution proceedings.
  2. 2 Whether the underlying contractual dispute regarding Force Majeure can prevent the employer from calling up the guarantees under South African law.
  3. 3 Whether the applicant validly terminated the contract due to Force Majeure and followed the prescribed contractual procedures.

Ratio Decidendi

The court found that the applicant failed to establish a legal basis for restraining SANRAL from presenting the guarantees for payment. The applicant did not prove that the events constituted Force Majeure as defined in the contract, nor that the prescribed procedures for termination were properly followed. The correspondence and evidence did not support the existence of a continuous Force Majeure event affecting a substantial part of the works. The applicant's refusal to return to site was deemed unjustified, and SANRAL was entitled to regard this as repudiation of the contract. Under South African law, absent fraud, the autonomy of construction guarantees prevails, and the underlying...

Court Disposition

Application dismissed with costs.

Orders

  • The application is dismissed with costs.