JSW Electrical (Pty) Ltd v SBB Joint Venture (24603/2001) [2008] ZAGPHC 359 (14 October 2008)
The court found that the parties had entered into a termination agreement on 21 January 1999, which fully and finally settled all rights and obligations arising from the subcontract. The agreement specified that completed work would be paid for at schedule rates, materials on site would be paid for as agreed, and substandard work would not be paid for. The evidence established that on 25 January 1999, the plaintiff and the defendant's quantity surveyor agreed on the materials and that payment for completed work would be based on the December certificate. The defendant's attempt to rely on the exceptio non adempleti contractus failed because the claim was based on the termination...
- Citation
- [2008] ZAGPHC 359
- Parties
- Plaintiff: JSW Electrical (Pty) Ltd; Defendant: SBB Joint Venture
- Court
- High Courts - Gauteng
- Jurisdiction
- South Africa
- Judgment Date
- 14 October 2008
- Case Number
- 24603/2001
- Procedural Posture
- Civil Trial / Final Judgment
- Outcome
- Judgment for the plaintiff; defendant ordered to pay the claimed amount, interest, and costs.
- Judges
- B. R. Du Plessis
- Legal Topics
- Subcontractor Liability, Termination Agreement, Retention Money, Quantification of Claim, Exceptio Non Adeimpleti Contractus
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
JSW Electrical (Pty) Ltd
Plaintiff
SBB Joint Venture
Defendant
Procedural Posture
Civil Trial / Final Judgment
Legal Issues
- 1 Whether the plaintiff is entitled to payment under the termination agreement for completed work, materials on site, and retention money.
- 2 Whether the defendant can rely on the exceptio non adempleti contractus to resist payment.
- 3 Whether the December certificate and subsequent agreement on 25 January 1999 constitute full and final settlement of the parties' rights.
Ratio Decidendi
The court found that the parties had entered into a termination agreement on 21 January 1999, which fully and finally settled all rights and obligations arising from the subcontract. The agreement specified that completed work would be paid for at schedule rates, materials on site would be paid for as agreed, and substandard work would not be paid for. The evidence established that on 25 January 1999, the plaintiff and the defendant's quantity surveyor agreed on the materials and that payment for completed work would be based on the December certificate. The defendant's attempt to rely on the exceptio non adempleti contractus failed because the claim was based on the termination...
Court Disposition
Judgment for the plaintiff; defendant ordered to pay the claimed amount, interest, and costs.
Orders
- The defendant must pay the plaintiff R432,784.77 plus interest at 15.5% per annum from 1 February 1999 to date of payment.
- The defendant is ordered to pay the plaintiff's costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment