Download PDF

South Africa Order

Free State High Court, Bloemfontein

Karpah Construction CC v Potgieter and Others (530/2014) [2014] ZAFSHC 230 (12 December 2014)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court held that the plaintiff's particulars of claim do disclose a cause of action and are not vague or embarrassing on any reasonable interpretation. The written contract, although signed by only one party, was acted upon by both parties and thus constitutes a binding agreement. The non-variation clause cannot be enforced when the contract itself was not signed by both parties, and the calculation of additional preliminary payments is sufficiently clear. The excipients failed to indicate any prejudice resulting from the alleged vagueness. Accordingly, none of the grounds of exception have merit, and the exception is dismissed with costs.

Court disposition

Exception dismissed with costs.

Orders

  • The exception is dismissed with costs.

02

Material facts

Parties

Karpah Construction CC

Plaintiff Counsel: Adv S. Grobler

Phillipus Potgieter

Defendant Counsel: Adv C.D. Pienaar

Phillipus Potgieter N.O.

Defendant Counsel: Adv C.D. Pienaar

Annatha Potgieter N.O.

Defendant Counsel: Adv C.D. Pienaar

John Henry Ford N.O.

Defendant Counsel: Adv C.D. Pienaar

Amounts and remedies

  • Total Value of Works Done: ZAR 6,016,621.76
  • Additional Preliminaries Per Month: ZAR 130,044.58
  • Additional Preliminaries Total: ZAR 390,133.74

03

Procedural history

  1. Posture

    Civil Procedure / Exception to Particulars of Claim

04

Questions and positions

Legal issues

Party arguments

Applicant
The defendants, represented by Adv C.D. Pienaar, argued that the plaintiff's claim is based on a written contract that was only signed by the contractor and not by the employer, thus failing to disclose a cause of action. They further contended that the non-variation clause in the contract requires all variations to be in writing and signed by both parties, precluding any claim for additional preliminary amounts. The defendants also argued that the particulars of claim are vague and embarrassing, particularly regarding further agreements and payment certificates, and that the contract terms do not support the inferences drawn by the plaintiff.
Respondent
The plaintiff, represented by Adv S. Grobler, responded that, except where legislation prescribes formalities, parties are free to determine the form of their contract, and a written document signed by only one party can still constitute a binding agreement if acted upon by both parties. The plaintiff argued that the non-variation clause cannot be enforced when the contract itself was not signed by both parties, and that the calculation of additional preliminary payments is clear and supported by the contract terms. The plaintiff further contended that the particulars of claim do not rely on a further agreement or novation, but simply allege that the total value of the works done is not in dispute, and that the excipients have not indicated any prejudice.

05

Court’s reasoning

  1. 01

    Mervis Brothers v Interior Acoustics and Another 1999 (3) SA 607 (W) at 610D-G

    A written contract may be binding even if signed by only one party, provided it is acted upon by both parties and no statutory formalities require otherwise.

  2. 02

    Pete’s Warehousing and Sales CC v Bowsink Investments CC 2000 (3) SA 833 (E) par [22], [26]

    Non-variation clauses require clear acceptance and incorporation, typically by signature; if the contract is unsigned, such clauses may not be enforceable.

  3. 03

    Dettmann v Goldfain and Another 1975 (3) SA 385 (A) at 400A; Klokow v Sullivan 2006 (1) SA 259 (SCA) par [24]

    Exceptions should not be upheld where the issues are fact-bound and require evidence to resolve.

  4. 04

    Francis v Sharp and Others 2004 (3) SA 230 (C) at 240E-G

    An exception based on vagueness and embarrassment must show prejudice to succeed.

06

Ratio, limits and disposition

Ratio decidendi

The court held that the plaintiff's particulars of claim do disclose a cause of action and are not vague or embarrassing on any reasonable interpretation. The written contract, although signed by only one party, was acted upon by both parties and thus constitutes a binding agreement. The non-variation clause cannot be enforced when the contract itself was not signed by both parties, and the calculation of additional preliminary payments is sufficiently clear. The excipients failed to indicate any prejudice resulting from the alleged vagueness. Accordingly, none of the grounds of exception have merit, and the exception is dismissed with costs.

Obiter and limits

  • Courts are reluctant to decide fact-bound issues on exception, as the main purpose of an exception is to avoid unnecessary evidence.
  • The excipient must indicate prejudice for an exception based on vagueness and embarrassment to succeed.

Court disposition

Exception dismissed with costs.

  • The exception is dismissed with costs.

Source and reliance status

Free State High Court, Bloemfontein

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Free State High Court, Bloemfontein

Order

[2014] ZAFSHC 230

IN THE HIGH COURT OF SOUTH AFRICA

FREE STATE DIVISION, BLOEMFONTEIN

Case No: 530/2014

In the matter between:-

KARPAH

CONSTRUCTION CC ....................................................Plaintiff/Respondent

and

PHILLIPUS

POTGIETER …........................................................1st Defendant/Excipients

PHILLIPUS POTGIETER N.O. ….............................................2nd Defendant/Excipients

ANNATHA POTGIETER N.O. ….................................................3rd Defendant/Excipients

JOHN HENRY FORD N.O. ….......................................................4th Defendant/Excipients

CORAM: KRUGER, J

HEARD ON: 12 DECEMBER 2014

DELIVERED ON: 12 DECEMBER 2014

[1] The defendants except to the plaintiff’s particulars of claim on the basis of not disclosing a cause of action, alternatively being vague and embarrassing. The grounds of exception can be discussed under the following headings:

(1) Contract not signed

[2] The first ground of exception is that the plaintiff relies on a written contract, yet the contract has only been signed by the contractor and not by the employer. Mr Pienaar, for the excipient, submits with reference to Christie’s Law of Contract in South Africa 6th edition at 112 that a written contract only comes into existence when the written document has been signed by both parties. Therefore

Mr Pienaar says plaintiff’s claim based on the “written contract” does not disclose a cause of action.

[3] The answer to Mr Pienaar’s submission is that, except in cases where legislation prescribes formalities, such as for instance that the contract for the sale of land must be in writing, the parties are fee to decide on the form of their contract. A

written contract signed by the parties is one such form. Another form could be that the signatures must be witnessed. Another

form could be that the terms be in writing, but need not be signed by the parties, or by both parties. The latter is the type of contract the parties agreed to here. They acted in terms of this agreement. The plaintiff alleges in the particulars of claim that the defendants have paid close to R6 million. A written document, although signed by only one party, constitutes a written agreement nonetheless, as it was received by one of the contracting parties without demur by the other and acted upon by both parties (Mervis Brothers v Interior Acoustics and Another 1999 (3) SA 607 (W) at 610D-G).

(2) Non-variation clause; Plaintiff not entitled to preliminary and 10% payments

[4] The second ground of exception is that in view of the non-variation clause in the written agreement on which the plaintiff relies, all variations have to be in writing and signed by both parties, therefore there could be no variations of the written contract, and the plaintiff is not entitled to claim for “additional preliminary amounts” as it has done.

[5] The answer to this ground of exception is that in the initial contract the parties did not require signature. As Mr Grobler for the plaintiff points out, this ground of exception is mutually exclusive to the first ground of exception. The exception seems to be excipiable. It could hardly have been their contemplation that although the original contract was not signed by both parties, variations had to be signed. The non-variation clause is inserted into contracts to protect them from variations. Where the parties do not clearly indicate their acceptance and incorporation of the non-variation clause into their agreement by appending their signatures to the contract, the non-variation clause in the strict terms of clause 1.5 of the standard contract prepared by the Joint Building Contract Committee cannot be deemed to be part of the agreement between the parties. At the very least, at this (exception) stage the test is whether, as a reasonable interpretation, clause 1.5 can be regarded as not forming

part of the agreement (Pete’s Warehousing and Sales CC v Bowsink Investments CC 2000 (3) SA 833 (E) par [22], [26]).

[6] Mr Pienaar says that the agreement, read with annexure “B” thereto makes provision for additional preliminaries of R390 133,74, not for additional preliminaries of R130 044,58 per month. Mr Grobler says the calculation is hardly unclear – 3 x R130 044,58 = R390 133,74. These were the costs for the extended period. The costs are allowed in terms of the contract if the period gets longer (Clause 14.8). It cannot be said that these allegations as to additional payment in the particulars of claim are so unclear that on any reasonable interpretation, they cannot sustain a cause of action (Pete’s Warehousing (supra) par [14]).

(3) The variation orders

[7] This complaint falls away once one accepts, as one has to at this stage, that on one of the reasonable interpretations of the agreement between the parties, the written document was not the sole memorial of their contractual relationship. As Mr Grobler points out, the “Contract Sum” (Clause 1.1) is subject to adjustment.

(4) Further agreements

[8] The excipient complains that the further agreement alleged by the plaintiff in paragraph 16 of the particulars of claim is not stated to have been oral or in writing, as required by the rules of court, and is therefore vague and embarrassing. Mr Grobler explains the allegations in the pleadings by pointing out that the particulars of claim do not here rely on a further agreement, but simply state that the defendants had failed to issue further payment certificates notwithstanding practical completion and had failed to make full payment of amounts that were due and owing. The plaintiff thus pleads, so says Mr Grober, an impasse. Plaintiff simply states that the parties had agreed that the total value of the works done was R6 016 621,76. The plaintiff does not plead a variation of the original agreement, nor does it plead a novation. It simply states that one of the essential elements entitling it to payment is not in dispute. Thus, so Mr Grobler points out, all that plaintiff is doing is simply alleging in the particulars of claim that there is no need to rely on further payment certificates, nor does plaintiff need to indicate the specific contract value. Mr Pienaar says that the terms of the contract as pleaded do not allow for the inferences Mr Grobler contends for. That is in my view a matter for the trial court.

[9] Courts are reluctant to decide issues on exception which are fact bound (Dettmann v Goldfain and Another 1975 (3) SA 385 (A) at 400A per Corbett JA; Klokow v Sullivan 2006 (1) SA 259 (SCA) par [24]). The main purpose of an exception is to avoid the leading of unnecessary evidence (Dharumpal Transport (Pty) Ltd v Dharumpal 1956 (1) SA 700 (A) at 706D-E). In order for an exception based on the allegation that it is vague and embarrassing to succeed, the excipient has to indicate prejudice Francis v Sharp and Others 2004 (3) SA 230 (C) at 240E-G. The excipient has not indicated how it is prejudiced.

CONCLUSION

[10] There is no merit in any of the grounds of exception. It cannot be said that the pleadings do not disclose a cause of action or are vague and embarrassing on every possible interpretation. Furthermore the excipient has failed to indicate prejudice.

ORDER

The exception is dismissed with costs.

___

A. KRUGER, J

On behalf of excipients/defendants: Adv C.D. Pienaar

Instructed by:

Rossouws Attorneys

BLOEMFONTEIN

On behalf of respondent/plaintiff: Adv S. Grobler

Peyper Attorneys

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Mervis Brothers v Interior Acoustics and Another 1999 (3) SA 607 (W)

Case cited

Pete’s Warehousing and Sales CC v Bowsink Investments CC 2000 (3) SA 833 (E)

Case cited

Dettmann v Goldfain and Another 1975 (3) SA 385 (A)

Case cited

Klokow v Sullivan 2006 (1) SA 259 (SCA)

Case cited

Francis v Sharp and Others 2004 (3) SA 230 (C)

Case cited

Dharumpal Transport (Pty) Ltd v Dharumpal 1956 (1) SA 700 (A)

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.