Krull v Els and Another (1064/2012) [2012] ZAECGHC 44 (15 May 2012)
- Citation
- [2012] ZAECGHC 44
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Eastern Cape High Court, Grahamstown
- Panel
- J.E Smith
- Case number
- 1064/2012
More details
- Court
- Eastern Cape High Court, Grahamstown
- Panel
- J.E Smith
- Case number
- 1064/2012
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the applicant had conceded he did not have the necessary statutory permission from the Department of Roads and Transport to construct gates on a public road. The Certificate of Adequate Enclosure issued by the Department of Economic Development and Environmental Affairs and Tourism did not confer authority to obstruct a public road. As such, the gates were erected unlawfully. The court further held that no interim order had in fact been issued by Sandi J, and therefore the contempt application could not succeed. The rule nisi was discharged and both applications were dismissed with costs.
Court disposition
Both the contempt of court application and the main application for confirmation of the rule nisi are dismissed with costs.
Orders
- The contempt of court application is dismissed with costs, including the costs of two counsel.
- The rule nisi granted by Sandi J on 12 April 2012 is discharged with costs, including the costs of two counsel.
02
Material facts
Parties
Elvin Victor Krull
Applicant Counsel: Advocate ColletJohan Wynand Els
Respondent Counsel: Advocate Ford, SCDepartment of Economic Development and Environmental Affairs and Tourism
Respondent03
Procedural history
Posture
Urgent Application / Application for Confirmation of Rule Nisi and Contempt of Court
04
Questions and positions
Legal issues
- 01
Whether the applicant obtained the necessary statutory permission to construct gates on a public road.
- 02
Whether the Department of Economic Development and Environmental Affairs and Tourism had authority to approve the gates.
- 03
Whether the respondent was in contempt of court for alleged breach of the order.
Party arguments
- Applicant
- The applicant argued that he had received approval from the Department of Economic Development, Environmental Affairs and Tourism for the gates and fencing via a Certificate of Adequate Enclosure. He contended that this approval entitled him to construct the gates and restrict access as set out in the rule nisi. He later conceded that he required permission from the Department of Roads and Transport and sought postponement pending his application for such permission.
- Respondent
- The respondent argued that the Department of Economic Development and Environmental Affairs and Tourism lacked statutory authority to approve gates on public roads. He maintained that only the Department of Roads and Transport could grant such permission under the Roads Ordinance or the Eastern Cape Roads Act. The respondent asserted that the gates were unlawful and sought their removal, as well as compliance with fencing requirements.
05
Court’s reasoning
Legal principles
- 01
Roads Ordinance, 19 of 1976; Eastern Cape Roads Act, 3 of 2003
Permission from the Department of Roads and Transport is required for any obstruction on a public road; approval from other departments does not suffice.
- 02
Rule 42 of the Uniform Rules of Court
A contempt of court application cannot succeed where no operative interim order was granted.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the applicant had conceded he did not have the necessary statutory permission from the Department of Roads and Transport to construct gates on a public road. The Certificate of Adequate Enclosure issued by the Department of Economic Development and Environmental Affairs and Tourism did not confer authority to obstruct a public road. As such, the gates were erected unlawfully. The court further held that no interim order had in fact been issued by Sandi J, and therefore the contempt application could not succeed. The rule nisi was discharged and both applications were dismissed with costs.
Obiter and limits
- The court observed that the parties' failure to reach an amicable arrangement led to unnecessary and costly litigation.
- The judge noted that a mutually beneficial agreement was still possible if both parties were willing to compromise, but the hostility between them made this unlikely.
Court disposition
Both the contempt of court application and the main application for confirmation of the rule nisi are dismissed with costs.
- The contempt of court application is dismissed with costs, including the costs of two counsel.
- The rule nisi granted by Sandi J on 12 April 2012 is discharged with costs, including the costs of two counsel.
Source and reliance status
Eastern Cape High Court, Grahamstown
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Eastern Cape High Court, Grahamstown
Judgment
7
IN THE HIGH COURT OF SOUTH AFRICA
EASTERN CAPE DIVISION,
GRAHAMSTOWN
Case no: 1064/2012
Date Heard: 31/05/12
Date Delivered: 15/05/12
In the matter between:
ELVIN VICTOR KRULL …....................................................APPLICANT
Versus
JOHAN WYNAND ELS …............................................1st
RESPONDENT
DEPARTMENT
OF ECONOMIC DEVELOPMENT
AND ENVIRONMENTAL AFFAIRS AND TOURISM …............2ND
RESPONDENT
JUDGMENT
SMITH J:
[1] The Applicant (''Krull") seeks confirmation of a rule nisi which was granted by Sandi J on 12 April 2012 in the following terms:
1. That the First Respondent and/or any persons acting on his behalf or in furtherance of his objectives should not be interdicted and restrained from damaging and/or leaving open and/or restricting the Applicant's access and/or altering the gates and/or fencing of the Tyityaba reserve as approved by the Second Respondent in terms of the Certificate of Adequate Enclosure, number CR26/10/09, with immediate effect; and
2. That the First Respondent should not be ordered to utilise the approved Gate A at Gateway 2 with immediate effect.
Krull has also subsequently applied for an order declaring the First Respondent ("Els") to be in contempt of this order.
[2] Krull owns a game reserve in the Komgha district which shares a common boundary with the Glen Kei farm, in turn owned by a trust of which Els is a trustee.
[3] Krull's farm is traversed by a provincial public road (“the Tyityaba road"). The Tyityaba road is also the only means by which Els and members of his family can gain access to Glen Kei farm. Krull has fenced off the entrance from the national road to the reserve by way of a remote controlled gate. He had also subsequently constructed a guard house, where he posted a guard to control access to the reserve. The other gates have been erected on the boundary between Krull's farm and the Glen Kei farm. A portion of the Tyityaba Road continues onto Glen Kei farm. Krull also uses that portion of the road to gain access to one of his
other farms.
[4] It must be apparent from the above that it was undoubtedly in the best interests of both parties to conclude an amicable arrangement to regulate access to their respective farms. Unfortunately this was not to be. Instead the parties’ belligerent posturing has led to a proliferation of rancorous and costly litigation. In fact, I was initially of the view that even at this late stage, a mutually beneficial agreement was still eminently possible. However this would have required cool heads and willingness by both parties to compromise. The depth of the almost palpable hostility apparent from the papers however convinced me that this was an unlikely scenario. It therefore now falls to the court to resolve the disputes.
[5] I am of the view that despite the voluminous papers which had been filed in this, and the related applications, the case really turns on one issue only; and that is whether Krull had obtained the necessary permission from the relevant statutory authority before constructing the gates. Krull has averred that he had been granted permission by the Second Respondent, being the Department of Economic Development, Environmental Affairs and Tourism ("the Department of Economic Affairs"), when he was granted approval for the establishment of the game reserve and issued with a Certificate of Adequate Enclosure (“CAE”) in terms
of the Nature and Environmental Conservation Ordinance, 19 of 1974.
[5] Conversely, Els has contended that the Department of Economic Affairs does not have statutory power to approve the construction of gates on public roads. Krull therefore required the permission of the Department of Roads and Transport in terms of the provisions of the Roads Ordinance, 19 of 1976 (“the Ordinance”) or the Eastern Cape Roads Act, 3 of 2003, (“the Roads Act”). It was on the basis of this assertion that Els and other members of the trust subsequently brought an application (under case number 1332/2012), wherein they seek an order declaring the gates to be unlawful, as well as an order that they be removed. They also seek an order compelling Krull to erect fencing along the Tyityaba road in compliance with his CAE.
[6] In the meantime Krull has filed a counter-application in case no 1332/2012, wherein he seeks an order staying those proceedings pending an application which he intends to make to the Department of Roads and Transport for the necessary permission to construct gates at both ends of the Tyityaba Road. The counter-application was brought on the basis of a concession by Krull that he indeed requires permission from the Department of Roads and Transport to construct the gates. He stated in his founding affidavit in that matter that he had now been advised by the relevant authorities that the CAE does not sanction the construction of the gates, and that he still requires the permission of the Department of Roads and Transport.
[7] In my view this concession was correctly made. Both the Ordinance and the Roads Act provide unambiguously that the sanction of the Department of Roads and Transport is required for any type of obstruction on public roads.
[8] At the hearing of this matter Mrs Collet, who appeared for Krull, applied for both the main application and the contempt application to be postponed pending the finalisation of Krull's counter-application in case 1332/2012. I was however of the view that the postponement of these matters will serve no purpose other than to delay the inevitable. If indeed these gates were erected unlawfully (which Krull has now admitted is the case),
then I have no power to sanction the continued unlawful obstruction of a public road, even on an interim basis, pending the application
for the necessary permit. In the event it appears that while Sandi J was of the view that Krull was entitled to interim relief, he had inadvertently not granted the interim interdict. I have no doubt that he will in all probability rectify the order if he were approached by either party in terms of Rule 42 of the Uniform Rules of Court. This will result in the untenable situation where Krull will be the beneficiary of an interim interdict which had been issued on the basis of factual and legal averments which he has now admitted are incorrect. I therefore refused the application for postponement on this basis.
[9] Turning now to deal with the contempt of court application, I am of the view that it cannot succeed for the simple reason that Sandi J did in fact not grant interim relief. As I have stated before, while his ex tempore judgment clearly indicated that he was of the view that Krull had established all the requisites for interim relief, Sandi J inadvertently omitted to refer to paragraph 3 of the Notice of Motion (which relates to the interim interdict) when he had made the order. Neither of the parties has subsequently approached Sandi J for rectification of the order in terms of Rule 42. The result is therefore that no interim order had in fact issued and there can therefore be no question of Els having been in contempt of the order. The contempt application falls to be dismissed on this ground alone.
[10] I am similarly of the view that Krull cannot succeed with the main relief. Mrs Collet was constrained to concede that the application can only succeed if Krull was able to establish that the gates were lawful. Mr Ford SC, who appeared on behalf of Els, has in my view correctly submitted that it had now been established (and in fact conceded by Krull) that the gates and fences referred to in the rule granted by Sandi J on 12 April 2012, fall within the auspices of the Department of Roads and Transport. The Department of Economic Affairs did therefore not have any statutory power to grant permission for the construction of the gates on a public road. Krull was therefore obliged to seek the permission of the Department of Roads and Transport. He has failed to do so. The construction of the gates was therefore unlawful and the application must fail for this reason.
[11] In the result I make the following order:
The contempt of court application is dismissed with costs, such costs to include the costs of two counsel;
2. The rule nisi granted by Sandi J on 12 April 2012 is hereby discharged with costs, such costs to include the costs of two counsel.
_______
J.E SMITH
JUDGE OF THE HIGH COURT
Appearances
Counsel for the Applicant : Advocate Collet
Attorneys for the Applicant : Netteltons
GRAHAMSTOWN
(Ref: Mr Nettelton)
Counsel for the Respondents : Advocate Ford, SC
Attorneys for the Respondents : Wheeldon Rushmere & Cole
(Ref: Mr Laing)
Date Heard : 31 May 2012
Date Delivered : 15 June 2012
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.