Kwazulu Natal Federated Insurance Guarantee Brokers (Pty) Ltd v Johannesburg Development Agency (Pty) Ltd (AR9/08) [2007] ZAKZHC 58 (1 January 2007)

Kwazulu Natal Federated Insurance Guarantee Brokers (Pty) Ltd v Johannesburg Development Agency (Pty) Ltd (AR9/08) [2007] ZAKZHC 58 (1 January 2007)

The court held that the guarantee was intended to provide for payment to the applicant upon cancellation of the contract, subject to the delivery of the required written demand and notice of cancellation. Payment was not contingent on prior certification of loss by the principal agent. The guarantee served as an...

Source-derived case information.

Citation
[2007] ZAKZHC 58
Parties
Appellant: Federated Insurance Guarantee Brokers (Pty) Ltd; Respondent: Johannesburg Development Agency (Pty) Ltd
Court
High Courts - Kwazulu Natal
Jurisdiction
South Africa
Case Number
AR9/08
Procedural Posture
Civil Appeal / Appeal From High Court Judgment Granting Payment Under Construction Guarantee
Outcome
Appeal dismissed with costs, including costs of two counsel.
Judges
Hurt, Theron, Ntshangase
Legal Topics
Construction Guarantee, Contractual Interpretation, Liquid Document, Performance Security
Commercial and Corporate Civil Procedure Construction Guarantee Contractual Interpretation Liquid Document Performance Security

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Federated Insurance Guarantee Brokers (Pty) Ltd

Appellant

Johannesburg Development Agency (Pty) Ltd

Respondent

Procedural Posture

Civil Appeal / Appeal From High Court Judgment Granting Payment Under Construction Guarantee

  1. 1 Whether the guarantee required certification of loss before payment could be demanded.
  2. 2 Whether the applicant was entitled to call up the guarantee upon cancellation of the contract.
  3. 3 Whether the applicant's alleged breach precluded its right to cancel and claim under the guarantee.

Ratio Decidendi

The court held that the guarantee was intended to provide for payment to the applicant upon cancellation of the contract, subject to the delivery of the required written demand and notice of cancellation. Payment was not contingent on prior certification of loss by the principal agent. The guarantee served as an indemnity, and any surplus after final accounting would be refunded to the guarantor, preventing unjust enrichment. The applicant's compliance with the guarantee's procedural requirements rendered the respondent liable to pay. The respondent's argument that payment should await certification was rejected, as was the contention that the applicant's alleged breach precluded its...

Court Disposition

Appeal dismissed with costs, including costs of two counsel.

Orders

  • The appeal is dismissed.
  • The appellant is ordered to pay the respondent's costs, including the costs occasioned by the employment of two counsel.