Download PDF

South Africa Judgment

North West High Court, Mafikeng

Kwende Construction CC v Ditsobotla Local Municipality (604/2024) [2025] ZANWHC 119 (15 July 2025)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that Kwende Construction CC was lawfully appointed under emergency procurement provisions, completed the contracted work, and received both a certificate of completion and a written acknowledgment of debt from Ditsobotla Local Municipality. Ditsobotla's opposition was based on bare denials and unsubstantiated allegations of irregularity, without any credible evidence of unlawful conduct or procedural defects in the emergency procurement. The court held that the contract and acknowledgment of debt remain binding until set aside in proper review proceedings, which Ditsobotla had not instituted. The request for referral to oral evidence was rejected due to the absence of a genuine dispute of fact. Ditsobotla's conduct in launching defective urgent proceedings, refusing to pay an admitted debt, and opposing the counter-application on spurious grounds constituted an abuse of process, justifying a punitive costs order. The main application remains live but was not before the court for determination. The counter-application succeeded, and Ditsobotla was ordered to pay the outstanding amount, interest, and costs on the attorney and client scale.

Court disposition

Counter-application granted. Main application dismissed with costs. Ditsobotla Local Municipality ordered to pay the outstanding debt, interest, and costs on attorney and client scale.

Orders

  • The Applicant's application dated 9 February 2024 is dismissed with costs on the attorney and client scale.
  • The Applicant is ordered to make payment to the Respondent in the amount of R7,518,171.22, including interest thereon a tempore morae at the legally prescribed interest rate, calculated from 31 January 2024 to date of final payment, which payment is to be made within 14 days of this order.
  • The Applicant is ordered to pay the Respondent’s costs on attorney and client scale in respect of the Applicant’s counter-claim.

02

Material facts

Parties

Kwende Construction CC

Applicant Counsel: Advocate B Ziswe

Ditsobotla Local Municipality

Respondent Counsel: Advocate AP Ellis

Amounts and remedies

  • Outstanding Certified Debt: ZAR 7,518,171.22
  • Partial Payment Made: ZAR 1,000,000

03

Procedural history

  1. Posture

    Urgent Application / Counter Application Determination Following Removal of Main Application From Roll

04

Questions and positions

Legal issues

Party arguments

Applicant
Kwende Construction CC argued it was lawfully appointed under emergency circumstances to restore electricity, completed the work, and received a certificate of completion and an acknowledgment of debt from Ditsobotla. It contended that the procurement deviation was properly authorised under the MFMA and relevant regulations, and that Ditsobotla's refusal to pay was without merit, consisting only of bare denials unsupported by evidence. Kwende maintained that all statutory and contractual requirements were met, and that Ditsobotla's opposition was frivolous and amounted to an abuse of process.
Respondent
Ditsobotla Local Municipality argued that the procurement process was irregular and unlawful, and that the contract should be declared invalid. It requested referral to oral evidence to resolve factual disputes regarding the legality of the appointment and contract. Ditsobotla relied on constitutional principles of legality and procurement compliance, asserting that the acknowledgment of debt and certificate of completion could not override an unlawful appointment. It also challenged the sufficiency of the documentation supporting the claimed amount and denied liability for payment.

05

Court’s reasoning

  1. 01

    Kekana v Society of Advocates of South Africa [1998] ZASCA 54; 1998 (4) SA 649 (T)

    Removal of a matter from the roll does not dispose of the matter nor amount to abandonment; it remains pending until properly disposed of.

  2. 02

    Regulation 36(1)(a)(i) of the Municipal Supply Chain Management Regulations under MFMA

    Municipalities may lawfully deviate from ordinary procurement processes in emergencies if properly authorised and recorded.

  3. 03

    Valor IT v Premier, North West Province and Others [2021] ZACC 39; 2022 (4) SA 1 (CC)

    A contract concluded in breach of procurement prescripts is invalid and unenforceable, even if the other party acted in good faith.

  4. 04

    Merafong City Local Municipality v AngloGold Ashanti Ltd 2017 (2) SA 211 (CC)

    An administrative act remains effective until set aside by a court; organs of state cannot unilaterally repudiate their own decisions.

  5. 05

    Gijima Holdings (Pty) Ltd v State Information Technology Agency SOC Ltd 2018 (2) SA 23 (CC)

    PAJA does not apply to contractual disputes; only to reviewable administrative action.

  6. 06

    Plastic Converters Association of SA v NUMSA [2016] ZACC 3; 2016 (5) BCLR 578 (CC)

    Punitive costs are awarded where a party's conduct warrants judicial disapproval, such as acting frivolously, vexatiously, or in bad faith.

06

Ratio, limits and disposition

Ratio decidendi

The court found that Kwende Construction CC was lawfully appointed under emergency procurement provisions, completed the contracted work, and received both a certificate of completion and a written acknowledgment of debt from Ditsobotla Local Municipality. Ditsobotla's opposition was based on bare denials and unsubstantiated allegations of irregularity, without any credible evidence of unlawful conduct or procedural defects in the emergency procurement. The court held that the contract and acknowledgment of debt remain binding until set aside in proper review proceedings, which Ditsobotla had not instituted. The request for referral to oral evidence was rejected due to the absence of a genuine dispute of fact. Ditsobotla's conduct in launching defective urgent proceedings, refusing to pay an admitted debt, and opposing the counter-application on spurious grounds constituted an abuse of process, justifying a punitive costs order. The main application remains live but was not before the court for determination. The counter-application succeeded, and Ditsobotla was ordered to pay the outstanding amount, interest, and costs on the attorney and client scale.

Obiter and limits

  • The removal of a matter from the roll does not dispose of the matter; it remains pending until properly set down and determined.
  • Municipalities must comply with their statutory duty to pay undisputed debts within 30 days, as required by the MFMA.
  • Bare denials and speculative requests for oral evidence do not create a genuine dispute of fact warranting referral to oral evidence.
  • Punitive costs are appropriate where a party abuses the court's process and acts in bad faith, as Ditsobotla did in this matter.
  • PAJA is not applicable to contractual claims for payment based on acknowledgment of debt and certified performance.

Court disposition

Counter-application granted. Main application dismissed with costs. Ditsobotla Local Municipality ordered to pay the outstanding debt, interest, and costs on attorney and client scale.

  • The Applicant's application dated 9 February 2024 is dismissed with costs on the attorney and client scale.
  • The Applicant is ordered to make payment to the Respondent in the amount of R7,518,171.22, including interest thereon a tempore morae at the legally prescribed interest rate, calculated from 31 January 2024 to date of final payment, which payment is to be made within 14 days of this order.
  • The Applicant is ordered to pay the Respondent’s costs on attorney and client scale in respect of the Applicant’s counter-claim.

Source and reliance status

North West High Court, Mafikeng

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North West High Court, Mafikeng

Judgment

[2025] ZANWHC 119

IN

THE HIGH COURT OF SOUTH AFRICA

NORTH WEST DIVISION -

MAHIKENG

CASE NUMBER: 604/2024

Reportable: YES / NO

Circulate to Judges: YES / NO

Circulate to Magistrates: YES / NO

Circulate to Regional Magistrates: YES / NO

In the counter-application of:

KWENDE

CONSTRUCTION CC

APPLICANT (Respondent in the Main Application) and

DITSOBOTLA

LOCAL MUNICIPALITY

RESPONDENT (Applicant in the Main Application) In Re

DITSOBOTLA

LOCAL MUNICIPALITY

APPLICANT and

KWENDE

CONSTRUCTION CC

RESPONDENT

CORAM: OOSTHUIZEN-SENEKAL AJ

Date judgment reserved: 6 June 2025

The judgment was handed down electronically by circulation to the parties’ representatives via email. The date and time for hand-down is deemed to be 15 July 2025 at 10H00am.

ORDER

1. The Applicant's application dated 9 February 2024 is dismissed with costs on the attorney and client scale.

2. The Applicant is ordered to make payment to the Respondent in the amount of R7,518.171.22, including interest thereon a tempore morae at the legally prescribed interest rate, calculated from 31 January 2024 to date of final payment, which payment is to be made within 14 days of this order.

3. The Applicant is ordered to pay the Respondent’s costs on attorney and client scale in respect of the Applicant’s counter-claim.

JUDGMENT

OOSTHUIZEN-SENEKAL AJ:

Introduction

[1] This matter concerns two related applications between the parties:

1) An urgent main application by Ditsobotla Local Municipality (“Ditsobotla”), seeking to interdict Kwende Construction CC (“Kwende”) from removing or tampering with its electricity infrastructure;

2) A counter-application by Kwende, seeking payment of R7 518 171.22, plus interest, for emergency electrical repair services rendered to Ditsobotla following a total collapse of the municipal electricity

supply.

[2] For ease of reference, I refer to Ditsobotla as the applicant in the main application and respondent in the counter-application, and to Kwende as the respondent in the main application and applicant in the counter-application.

[3] On 9 February 2024, the main application came before the court on an urgent basis but was removed from the roll by agreement after Kwende undertook not to remove any equipment pending resolution of the dispute. Importantly, the main application was not withdrawn and therefore remains live on the roll. The main application awaits proper set-down by Ditsobotla for determination once it is ready to proceed.

[4] The principle that the removal of a matter from the roll does not amount to its dismissal, and remains pending until disposed of, was confirmed in Kekana v Society of Advocates of South Africa[1], where the court stated:

“The removal of a matter from the roll does not dispose of the matter, nor does it amount to an abandonment of the cause of action or defence. It merely postpones the hearing to a later date or occasion.”

[5] What is now before the court is the counter-application, which was not postponed nor removed, and it is to this application that this judgment primarily relates. The counter-application

is properly before me and ripe for determination as there is no procedural impediment to doing so.

Background Facts

[6] On 7 November 2023, Ditsobotla appointed Kwende to urgently restore electricity to six areas within its jurisdiction following a complete power failure. Kwende rendered emergency electrical services and completed the repairs. On 13 December 2023 Ditsobotla certified the completion of the work by issuing a Certificate of Compliance/Completion on 17 December 2023.

[7] The agreed contract price was R7 698 337,47, of which Ditsobotla made a part-payment of R1 000 000 on 22 December 2023. On the same date, Ditsobotla executed a written Acknowledgment of Debt and Repayment Agreement, explicitly acknowledging its indebtedness to Kwende in the remaining amount of R7 368 171,22, confirming that all internal processes and procurement prescripts were complied with.

[8] Despite these facts, Ditsobotla refused and failed to pay the outstanding amount. Instead, Ditsobotla launched a main application seeking to interdict Kwende from allegedly threatening to interfere with its electricity infrastructure. It is evident that Kwende’s undertaking to refrain from any self-help measures effectively reduced the urgency of the main application.

[9] Kwende denied any intention of self-help, expressly undertaking in writing on 7 February 2024 to seek any relief only through the courts. Ditsobotla nonetheless proceeded with the main application on 9 February 2024, after accepting Kwende’s undertaking.

Submissions by Kwende

[10] Kwende submits that it was lawfully appointed by Ditsobotla on 7 November 2023 to perform emergency electrical repairs after a total power failure in six areas of the municipality.

[11] The agreed remuneration was R7 698 337.47, which was later confirmed by a written Acknowledgment of Debt and Repayment Agreement dated 22 December 2023.

[12] Kwende completed the work on 13 December 2023, and Ditsobotla issued a Certificate of Completion and Compliance on 17 December 2023, confirming the successful performance of the work.

[13] Ditsobotla made a partial payment of R1 000 000 but thereafter refused to pay the outstanding amount despite the certificate of completion and acknowledgment of debt.

[14] Kwende contends that Ditsobotla’s opposition to the counter-application is without merit, consisting only of bare denials, and no evidence was advanced to refute the validity of the contract, the completion of work, or the lawful deviation from procurement rules under emergency circumstances.

[15] Kwende contended further that the emergency procurement was lawful, properly authorised under the Municipal Financial Management Act and Regulations.

Submissions by Ditsobotla

[16] Ditsobotla contended that the procurement process was irregular and unlawful, and that the matter should be referred to oral evidence to determine the factual disputes around the legality of the appointment and the validity of the contract.

[17] In this regard, Ditsobotla relied on the principle laid down in Valor IT v Premier, North West Province and Others[2], where the Constitutional Court held that contracts concluded in violation of procurement prescripts are invalid and cannot be

enforced, even where the other party acted in good faith.

[18] Ditsobotla argued that the acknowledgment of debt and certificate of compliance cannot override the principle of legality, if the underlying appointment was unlawful, the municipality cannot be compelled to pay.

[19] Ditsobotla also contended that the founding affidavit in the main application, although unsigned when filed, does not automatically invalidate the application. They relied on the principle that courts may condone such defects if the affidavit was later signed or if the deponent testifies and adopts it.

[20] Finally, Ditsobotla argued that the amount claimed by Kwende was not properly set out nor substantiated by detailed invoices and supporting documents.

Legal Framework

Emergency Procurement

[21] Section 217(1) of the Constitution requires that public procurement be fair, equitable, transparent, competitive and cost-effective. However, it permits deviations when authorised by law.

[22] The authority of a municipality to deviate from ordinary competitive procurement processes in emergency circumstances is expressly

provided for in Regulation 36(1)(a)(i) of the Municipal Supply Chain Management Regulations, issued under section 168 of the Local Government: Municipal Finance Management Act 56 of 2003 (MFMA).

[23] Regulation 36(1)(a)(i) reads:

“The accounting officer may dispense with the official procurement processes established by this policy and procure any required goods or services through any convenient process, which may include direct negotiations, but only—(a) in an emergency.”

[24] Furthermore, Regulation 36 deviations must also be properly recorded and reported to the municipal council and relevant authorities to ensure transparency and accountability. There was no evidence that such reporting did not occur.

[25] Section 55 of the Municipal Systems Act 32 of 2000 (“the MSA”) and section 65(2)(e) of the MFMA place a duty on the municipal manager to ensure that the municipality complies with its contractual and financial obligations, and that all monies due are paid within 30 days, unless validly disputed.

[26] In AllPay Consolidated Investment Holdings (Pty) Ltd v Chief Executive Officer, SASSA[3], the court recognised that while adherence to procurement rules is vital, deviations are justified when properly authorised and

recorded, as was done here.

[27] In Valor IT, however, the court cautioned that even good faith reliance on an invalid appointment cannot cure a contract concluded in breach of procurement laws. But unlike in Valor IT, where no evidence of lawful deviation was presented, here the acting municipal manager expressly authorised emergency procurement, the work was completed and certified, and Ditsobotla signed the acknowledgment of debt without raising illegality at the time.

Promotion of Administrative Justice Act 3 of 2000 (“PAJA”)

[28] Ditsobotla did not formally invoke the Promotion of Administrative Justice Act 3 of 2000 (“PAJA”) in its pleadings, nor was it properly pleaded or advanced that the acknowledgment of debt, the certificate of completion, or the

appointment of Kwende constituted reviewable administrative action under PAJA. The court therefore did not and could not consider PAJA applicable to the merits of this contractual dispute.

[29] This is because the counter-application concerns an ordinary enforcement of a contractual claim for payment of a certified debt, based on an acknowledgment of debt signed by the municipal manager, rather than a review of an administrative act. In Oudekraal Estates (Pty) Ltd v City of Cape Town[4], the Supreme Court of Appeal explained:

“Until the invalid administrative act is set aside by a court in proceedings for judicial review it exists in fact, and it has legal consequences that cannot simply be overlooked.”

[30] Thus, even if there were irregularities in the appointment or contract, which have not been established, the act remains effective and binding until and unless it is reviewed and set aside in proper proceedings under PAJA.

[31] The Constitutional Court later reaffirmed in Merafong City Local Municipality v AngloGold Ashanti Ltd[5] following:

“An administrative act remains legally effective until properly set aside by a court on review. An organ of state cannot unilaterally

repudiate or ignore its own decisions without a proper challenge.”

[32] Ditsobotla has not launched review proceedings under PAJA or sought to set aside its own acknowledgment of debt or the underlying procurement decision. Its opposition in the counter-application rests on vague assertions of irregularity rather than a formally instituted review, which is procedurally impermissible.

[33] In Kirland Investments (Pty) Ltd v Minister of Medical Aid and Others[6], Cameron J observed the following:

“The decision, until properly set aside, exists in fact and has legal consequences. Public authorities must respect and enforce it. They cannot simply ignore it because they consider it defective.”

[34] The debt claimed here flows from services performed, certified, and acknowledged in writing. Those instruments remain valid and binding until a competent court, in properly instituted review proceedings, declares them invalid. PAJA therefore has no application in the counter-application for payment of a contractual debt.

[35] Furthermore, the counter-application does not fall within the ambit of “administrative action” as defined in section 1 of PAJA, which excludes contractual disputes[7] In Gijima, the Court states:

“PAJA does not apply to the exercise of public power that does not constitute administrative action as defined. Here the claim

arose ex contractu and not ex lege.”

[36] In the present matter, I am of the view that Kwende’s claim rests squarely on the acknowledgment of debt, the completed and certified work, and the contractual undertakings made by Ditsobotla. It is not founded on any public-law duty. Accordingly, PAJA does not apply to the present dispute.

Evaluation

[37] On the evidence, the main application remains alive but is not before me for determination. Ditsobotla’s reliance on its unsigned founding affidavit in the main application does not assist it here. While procedural defects in affidavits can be cured if promptly addressed in terms of Rule 6(5)(b) and by appropriate application to the court, no such application was made here.

[38] Even if curable, the defective affidavit and lack of authority to launch proceedings, as discussed in Ganes and Another v Telecom Namibia Ltd[8], raise serious questions about the bona fides of the main application.

[39] The main application was removed from the roll by agreement after Kwende undertook not to remove its equipment, pending resolution of the dispute. In terms of Kekana, the main application remains live, but there is no evidence that Kwende has breached its undertaking or threatened unlawful conduct

since then.

[40] Turning to the counter-application, the evidence shows:

1) The emergency procurement was authorised under Regulation 36(1)(a)(i) by the acting municipal manager.

2) The work was completed and certified as compliant by the municipality on 17 December 2023.

3) Ditsobotla signed an acknowledgment of debt on 22 December 2023.

4) Ditsobotla paid R1 000 000,00 but refused to pay the outstanding R7 518 171.22.

[41] Ditsobotla now seeks to impugn its own contract and acknowledgment of debt by alleging illegality. But no concrete evidence has been presented to suggest that the emergency was fabricated or that the deviation was unauthorised. In Steenkamp v Provincial Tender Board, Eastern Cape[9], the Constitutional Court stressed the importance of respecting finality in certified public works unless fraud or gross irregularity

is shown.

[42] While Valor IT recognises the principle of legality, the facts here are distinguishable: Ditsobotla itself invoked emergency procurement, certified the work, and signed the acknowledgment of debt. It cannot now rely on its own dereliction to escape liability[10].

[43] The request for referral to oral evidence is without merit. As held in Room Hire Co (Pty) Ltd v Jeppe Street Mansions (Pty) Ltd[11], such referral is justified only when there is a genuine, material factual dispute incapable of resolution on the papers, which is absent here.

[44] Ditsobotla’s bare and unsubstantiated denials fall far short of creating a genuine dispute of fact. In Wightman t/a JW Construction v Headfour (Pty) Ltd[12], it was held:

“A real, genuine and bona fide dispute of fact can exist only where the court is satisfied that the party who purports to raise the dispute has seriously and unambiguously addressed the fact said to be disputed.”

[45] Similarly, the argument that the amount claimed was not set out in sufficient detail is contradicted by the appointment letter, the certificate of compliance, and the acknowledgment of debt specifying the amount. The certificate of completion is prima facie proof of proper performance and remains unchallenged by any credible evidence.

[46] The municipality’s refusal to pay despite its acknowledgment of debt, certificate of completion, and the statutory obligation under s 65(2)(e) of the MFMA, amounts to a blatant breach of its duties. The MFMA obliges municipalities to pay undisputed debts within 30 days, a duty clearly ignored here without lawful justification.

Conclusion

[47] In view of the evidence and the legal framework, I find that the main application remains alive, but there is no evidence to justify interdictory relief at this stage, given Kwende’s undertaking and the absence of any threat.

[48] Furthermore, that the counter-application is meritorious. The emergency procurement was lawful; the work was completed and certified; the debt was acknowledged; and no valid defence has been raised.

Costs

[49] The award of costs is discretionary and must be exercised judicially, taking into account the particular circumstances of the case.

The general rule in civil litigation is that the successful party is entitled to its costs. As stated in Zwane v Elias and Another[13], the principle is:

“The successful party is, as a general rule, entitled to be awarded his costs unless there are special circumstances which warrant a different order.”

[50] The rationale behind the general rule was explained in Kruger Bros & Wasserman v Ruskin[14]:

“The rule of our law is that all costs — unless expressly otherwise enacted — are in the discretion of the judge, but that discretion must be judicially exercised upon a consideration of the facts of each case, and, where the proceedings are properly and reasonably taken, the successful party should have his costs.”

[51] While costs ordinarily follow the result, there are circumstances where a court will depart from the ordinary rule and award costs on a punitive scale, such as attorney-and-client costs. This is a measure of the court’s displeasure at a litigant’s conduct and is designed both to penalise the offending party and to indemnify the successful party from being out of pocket.

[52] In Plastic Converters Association of SA v NUMSA[15], the Constitutional Court noted:

“Punitive costs are awarded when the conduct of a party warrants disapproval by the court, usually when it has acted frivolously, vexatiously, or in bad faith.”

[53] Similarly, in Public Protector v South African Reserve Bank[16], the court held that a punitive costs order is appropriate where a party’s conduct constitutes an abuse of the court’s

process, wastes judicial resources, and unfairly burdens the opponent.

[54] In this matter, Ditsobotla’s conduct warrants such censure:

1) It launched an urgent main application on defective and unsigned papers, without genuine urgency, and despite having accepted Kwende’s undertaking not to remove equipment.

2) It refused to pay an admitted and certified debt, despite issuing a Certificate of Completion and signing an Acknowledgment of Debt.

3) It opposed the counter-application on spurious grounds, raising bare denials unsupported by any substantive evidence.

4) It invoked serious allegations of unlawful procurement without producing evidence to substantiate them and raised a request for oral evidence that was speculative and contrived.

[55] This conduct amounts to an abuse of the court’s process, wasted judicial time and resources, and caused unnecessary expense and prejudice to Kwende.

[56] The court cannot allow its processes to be used as a tactical tool to evade lawful obligations or to harass a counter-party who has lawfully performed its duties.

[57] Ditsobotla’s conduct, launching defective and unnecessary urgent proceedings, refusing to pay an admitted and certified debt, opposing the counter-application on spurious grounds, raising unsubstantiated allegations of illegality, and making a speculative request for oral evidence, amounts to an abuse of the court’s process.

[58] Accordingly, the court is satisfied that this is an appropriate case to mark its disapproval by awarding costs in the counter-application on the punitive scale of attorney-and-client.

Order

[59] In the result, the following order is made:

1. The Applicant's application dated 9 February 2024 is dismissed with costs on the attorney and client scale.

2. The Applicant is ordered to make payment to the Respondent in the amount of R7,518.171.22, including interest thereon a tempore morae at the legally prescribed interest rate, calculated from 31 January 2024 to date of final payment, which payment is to be made within 14 days of this order.

3. The Applicant is ordered to pay the Respondent’s costs on attorney and client scale in respect of the Applicant’s counter-claim.

CSP OOSTHUIZEN-SENEKAL

ACTING JUDGE OF THE

HIGH COURT OF SOUTH AFRICA

NORTH WEST DIVISION,

MAHIKENG

APPEARANCES

For the Applicant: Advocate AP Ellis

Email: alex@gkchambers.co.za

Instructed by:

JASSAT MITCHELL INC

Cnr Andrew & Dr Yusuf Dadoo Ave

Flamwood

Klerksdorp, 2572

Email: litigation1@thelawhub.co.za

anton@thelawhub.co.za

c/o

BRUCE LOXTON INC

20 Cooke Street

Golfview

Mahikeng

Email: cachet@loxinc.co.za

mahikeng@loxinc.co.za

Ref: C Loxton/am/J331

For the Respondent: Advocate B Ziswe

Luyanda Nyangiwe

Email:

Instructed by:

MORANTHI

AND MATAKA ATTORNEYS

1st Floor, EP Building

Cnr Walter Sisulu & Nelson Mandela Drive

Potchefstroom

Email: moranthimatak@mweb.co.za

raphepeng@mweb.co.za

lucas@maleshaneinc.co.za

c/o

MALESHANE ATTORNEYS INCORPORATED

3590 Wildevy Street

Extension 34, Danville

Ref: R.E.M/MK/1178(8)

[1] [1998] ZASCA 54; 1998 (4) SA 649 (T) at 655F–G.

[2] [2021] ZACC 39; 2022 (4) SA 1 (CC) paragraphs [28]-[29] and [54].

[3] 2014 (1) SA 604 (CC) at paragraph 23.

[4] 2004 (6) SA 222 (SCA) at paragraph [29].

[5] 2017 (2) SA 211 (CC) at paragraph [41].

[6] 2014 (3) SA 481 (CC) at paragraphs [65]–[66].

[7] Gijima Holdings (Pty) Ltd v State Information Technology Agency SOC Ltd 2018 (2) SA 23 (CC) at paragraph [26].

[8] 2004 (3) SA 615 (SCA) at paragraph [19].

[9] 2007 (3) SA 121 (CC) at paragraph [29].

[10] Cool Ideas 1186 CC v Hubbard 2014 (4) SA 474 (CC) at paragraph [33].

[11] 1949 (3) SA 1155 (T) at 1165.

[12] [2008] ZASCA 6; 2008 (3) SA 371 (SCA) at paragraph [13].

[13] 1998 (2) SA 624 (W) at 632D.

[14] 1918 AD 63 at 69.

[15] [2016] ZACC 3; 2016 (5) BCLR 578 (CC), paragraph [46].

[16] 2019] ZACC 29; 2020 (5) SA 487 (CC) at paragraph [144].

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Kekana v Society of Advocates of South Africa [1998] ZASCA 54; 1998 (4) SA 649 (T)

Case cited

Valor IT v Premier, North West Province and Others [2021] ZACC 39; 2022 (4) SA 1 (CC)

Case cited

AllPay Consolidated Investment Holdings (Pty) Ltd v Chief Executive Officer, SASSA 2014 (1) SA 604 (CC)

Case cited

Oudekraal Estates (Pty) Ltd v City of Cape Town 2004 (6) SA 222 (SCA)

Case cited

Merafong City Local Municipality v AngloGold Ashanti Ltd 2017 (2) SA 211 (CC)

Case cited

Kirland Investments (Pty) Ltd v Minister of Medical Aid and Others 2014 (3) SA 481 (CC)

Case cited

Gijima Holdings (Pty) Ltd v State Information Technology Agency SOC Ltd 2018 (2) SA 23 (CC)

Case cited

Ganes and Another v Telecom Namibia Ltd 2004 (3) SA 615 (SCA)

Case cited

Steenkamp v Provincial Tender Board, Eastern Cape 2007 (3) SA 121 (CC)

Case cited

Cool Ideas 1186 CC v Hubbard 2014 (4) SA 474 (CC)

Case cited

Room Hire Co (Pty) Ltd v Jeppe Street Mansions (Pty) Ltd 1949 (3) SA 1155 (T)

Case cited

Wightman t/a JW Construction v Headfour (Pty) Ltd [2008] ZASCA 6; 2008 (3) SA 371 (SCA)

Case cited

Zwane v Elias and Another 1998 (2) SA 624 (W)

Case cited

Kruger Bros & Wasserman v Ruskin 1918 AD 63

Case cited

Plastic Converters Association of SA v NUMSA [2016] ZACC 3; 2016 (5) BCLR 578 (CC)

Case cited

Public Protector v South African Reserve Bank [2019] ZACC 29; 2020 (5) SA 487 (CC)

Case cited

Constitution of the Republic of South Africa, 1996

Legislation

Legislation referenced in the available case record.

Local Government: Municipal Finance Management Act 56 of 2003

Legislation

Legislation referenced in the available case record.

Municipal Supply Chain Management Regulations

Legislation

Legislation referenced in the available case record.

Municipal Systems Act 32 of 2000

Legislation

Legislation referenced in the available case record.

Promotion of Administrative Justice Act 3 of 2000

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.