LBMC Consulting (PTY) LTD v Minister of Public Works and Infrastructure and Another (28993/2020) [2023] ZAGPJHC 1334 (20 November 2023)

LBMC Consulting (PTY) LTD v Minister of Public Works and Infrastructure and Another (28993/2020) [2023] ZAGPJHC 1334 (20 November 2023)

The court found that the plaintiff was not entitled to issue a letter of suspension under the JBCC contract, as no payment was outstanding at the time and the contract did not provide for suspension and advance payment for future work. The plaintiff failed to submit invoices for the alleged losses and did not prove...

Source-derived case information.

Citation
[2023] ZAGPJHC 1334
Parties
Plaintiff: LBMC Consulting (PTY) LTD; Defendant: Minister of Public Works and Infrastructure; Defendant: Department of Public Works and Infrastructure
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
28993/2020
Procedural Posture
Civil Trial / Final Judgment
Outcome
Plaintiff's claim dismissed with costs.
Judges
S C Mia
Legal Topics
Construction Contracts, Breach of Contract, Quantum of Damages, Public Procurement, Bill of Quantities Dispute, Contractual Termination
Commercial and Corporate Civil Procedure Land and Property Construction Contracts Breach of Contract Quantum of Damages Public Procurement Bill of Quantities Dispute +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 4 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

LBMC Consulting (PTY) LTD

Plaintiff

Minister of Public Works and Infrastructure

Defendant

Department of Public Works and Infrastructure

Defendant

Procedural Posture

Civil Trial / Final Judgment

  1. 1 Whether the plaintiff was entitled to issue a letter of suspension under the JBCC contract.
  2. 2 Whether the defendants were entitled to cancel the JBCC Construction Agreement concluded in 2017.
  3. 3 Whether the plaintiff proved its claim for damages arising from breach of contract and delict.

Ratio Decidendi

The court found that the plaintiff was not entitled to issue a letter of suspension under the JBCC contract, as no payment was outstanding at the time and the contract did not provide for suspension and advance payment for future work. The plaintiff failed to submit invoices for the alleged losses and did not prove the amounts claimed. The evidence showed that the defendants granted extensions and paid for certified work, and the plaintiff did not exercise its contractual rights to address issues with the principal agent. The defendants were entitled to terminate the contract after the plaintiff abandoned the site and failed to remedy its breach. The plaintiff did not prove its damages,...

Court Disposition

Plaintiff's claim dismissed with costs.

Orders

  • The plaintiff’s claim is dismissed with costs.