Lonerock Construction v South African National Roads Agency (SOC Limited) [2023] ZAGPPHC 527; 89831/2018 (27 June 2023)
The court found that the contract did not entitle the defendant to object to or amend an Interim Payment Certificate once issued by the engineer. The plaintiff was entitled to payment as certified in IPC 36, as the contract only allowed for corrections in subsequent certificates, not withdrawal or cancellation of an existing certificate. The defendant's refusal to pay P&Gs and CPA was not contractually justified, and the differential treatment of SMMEs did not alter the plaintiff's rights under the main contract. The subsequent signing of a revised IPC 36 did not amount to waiver or acquiescence, as the plaintiff had consistently disputed the amendments and pursued its claim. Accordingly,...
- Citation
- [2023] ZAGPPHC 527
- Parties
- Plaintiff: Lonerock Construction; Defendant: South African National Roads Agency (SOC Limited)
- Court
- North Gauteng High Court, Pretoria
- Jurisdiction
- South Africa
- Judgment Date
- 27 June 2023
- Case Number
- 89831/2018
- Procedural Posture
- Civil Trial / Final Judgment
- Outcome
- Plaintiff's claim succeeds; defendant ordered to pay the balance certified in IPC 36.
- Judges
- Neukircher
- Legal Topics
- Construction Contracts, Interim Payment Certificates, Contractual Penalties, Waiver and Acquiescence
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Lonerock Construction
Plaintiff
South African National Roads Agency (SOC Limited)
Defendant
Procedural Posture
Civil Trial / Final Judgment
Legal Issues
- 1 Whether the plaintiff is entitled to payment of Preliminaries and Generals (P&Gs) and contract price adjustment (CPA) for the 11-month contract overrun period.
- 2 Whether the defendant was contractually entitled to refuse payment of P&Gs and CPA as certified in Interim Payment Certificate 36 (IPC 36).
- 3 Whether the defendant's differential treatment of the plaintiff and SMME subcontractors regarding penalties and P&Gs was contractually justified.
Ratio Decidendi
The court found that the contract did not entitle the defendant to object to or amend an Interim Payment Certificate once issued by the engineer. The plaintiff was entitled to payment as certified in IPC 36, as the contract only allowed for corrections in subsequent certificates, not withdrawal or cancellation of an existing certificate. The defendant's refusal to pay P&Gs and CPA was not contractually justified, and the differential treatment of SMMEs did not alter the plaintiff's rights under the main contract. The subsequent signing of a revised IPC 36 did not amount to waiver or acquiescence, as the plaintiff had consistently disputed the amendments and pursued its claim. Accordingly,...
Court Disposition
Plaintiff's claim succeeds; defendant ordered to pay the balance certified in IPC 36.
Orders
- The defendant is ordered to pay to the plaintiff the amount of R4 585 549.00.
- Interest is payable on the aforesaid sum a tempore morae from 10 September 2015 to date of payment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment