LTA Construction Ltd. v Minister of Public Works and Land Affairs (180/92) [1993] ZASCA 149; 1994 (1) SA 153 (AD); (29 September 1993)
The court held that clause 3(iii) of the contract does not entitle the appellant to additional remuneration for time-related costs resulting from delays caused by variation orders unless those items themselves are varied by specific order. Extensions of time under clause 17(iii) are not variations within the meaning of clause 3(iii) and do not justify additional payment for time-related items. Compensation for increased time-related costs is governed by clause 49 of Bill No 1, which had already been applied. The appellant's interpretation would result in double payment, which is not supported by the contract language or the parties' intentions. The application for condonation was refused...
- Citation
- [1993] ZASCA 149
- Parties
- Appellant: LTA Construction Limited; Respondent: Minister of Public Works and Land Affairs
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 29 September 1993
- Case Number
- 180/92
- Procedural Posture
- Civil Appeal / Appeal Against Dismissal of Claim and Application for Condonation
- Outcome
- Appeal dismissed; application for condonation refused.
- Judges
- Nestadt, Hoexter, Milne, Nicholas, Kriegler
- Legal Topics
- Construction Contracts, Variation Orders, Time Related Costs, Contractual Interpretation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
LTA Construction Limited
Appellant
Minister of Public Works and Land Affairs
Respondent
Procedural Posture
Civil Appeal / Appeal Against Dismissal of Claim and Application for Condonation
Legal Issues
- 1 Whether the appellant is entitled to additional remuneration for time-related costs resulting from delays caused by variation orders.
- 2 Whether clause 3(iii) of the contract allows for valuation of time-related items due to extensions of time.
- 3 Whether extensions of time under clause 17(iii) constitute a variation of Bill No 1 for the purposes of clause 3(iii).
Ratio Decidendi
The court held that clause 3(iii) of the contract does not entitle the appellant to additional remuneration for time-related costs resulting from delays caused by variation orders unless those items themselves are varied by specific order. Extensions of time under clause 17(iii) are not variations within the meaning of clause 3(iii) and do not justify additional payment for time-related items. Compensation for increased time-related costs is governed by clause 49 of Bill No 1, which had already been applied. The appellant's interpretation would result in double payment, which is not supported by the contract language or the parties' intentions. The application for condonation was refused...
Court Disposition
Appeal dismissed; application for condonation refused.
Orders
- The application for condonation is dismissed with costs.
- The appellant is to pay the respondent's costs of appeal.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment