Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Mahlalerwa-Kgabo-Ergo v Cooperativa Muratori Cementisti Ravenna (Pty) Ltd t/a C.M.C di Ravenna (South Africa) (10058/2017) [2018] ZAGPPHC 102 (14 March 2018)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the written agreement between the parties was clear and unequivocal regarding the contract price and the items included therein. The contract expressly stated that all duties, fees, taxes, and further costs payable by the subcontractor, including overheads and profit, were deemed to be included in the prices and rates of the Schedule of Quantities. The applicant's attempt to introduce implied or tacit terms regarding payment for Health and Safety Procedures and Site Establishment costs was inconsistent with the express terms of the agreement. The claims for restitution and unjustified enrichment were not properly pleaded and, if allowed, would render the particulars of claim excipiable. Accordingly, the application for amendment was refused.

Court disposition

Application for amendment refused; costs awarded against the applicant.

Orders

  • The application for amendment is refused.
  • The applicant is to pay the costs of the application.

02

Material facts

Parties

Mahlalerwa-Kgabo-Ergo JV

Applicant Counsel: K Fitzroy

Cooperativa Muratori Cementisti Ravenna (Pty) Ltd t/a C.M.C di Ravenna (South Africa)

Respondent Counsel: T Mahon

Amounts and remedies

  • Contract Price (indicative Total Sum): ZAR 2,223,403

03

Procedural history

  1. Posture

    Amendment Application / Application for Amendment of Particulars of Claim

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contended that the written agreement, by referencing compliance requirements, contemplated that costs for Health and Safety Procedures and Site Establishment were to be borne by the respondent, even though the Bill of Quantities was silent on these items. The applicant argued that these costs were implied or tacit terms of the agreement and sought to amend its particulars of claim accordingly. The applicant further argued that the briefing of two counsel by the respondent was neither reasonable nor warranted.
Respondent
The respondent objected to the proposed amendment, arguing that the contract price was expressly determined by the Bill of Quantities and that no implied or tacit terms could be read into the agreement. The respondent relied on Hudson's Building and Engineering Contracts as authority. The respondent further argued that the claims for restitution and unjustified enrichment were bad in law and that the briefing of two counsel was reasonable given the nature and importance of the matter.

05

Court’s reasoning

  1. 01

    SA Mutual Aid Society v Cape Town Chamber of Commerce 1962 (1) SA 598 (A) at 615D

    A term is sought to be implied in an agreement because the parties failed to agree expressly thereon. Where the parties have expressly agreed upon a term and given expression to that agreement in the written contract in unambiguous terms, no reference can be had to surrounding circumstances to subvert the meaning derived from the language of the agreement only.

  2. 02

    Delmas Milling Co Ltd v Du Plessis 1955 (3) SA 447 (A) at 454

    Where a contract expressly provides for the contract price and what is included or excluded, there is no basis to impute implied or tacit terms regarding payment for additional items.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the written agreement between the parties was clear and unequivocal regarding the contract price and the items included therein. The contract expressly stated that all duties, fees, taxes, and further costs payable by the subcontractor, including overheads and profit, were deemed to be included in the prices and rates of the Schedule of Quantities. The applicant's attempt to introduce implied or tacit terms regarding payment for Health and Safety Procedures and Site Establishment costs was inconsistent with the express terms of the agreement. The claims for restitution and unjustified enrichment were not properly pleaded and, if allowed, would render the particulars of claim excipiable. Accordingly, the application for amendment was refused.

Obiter and limits

  • The court agreed with the applicant that the briefing of two counsel by the respondent was neither reasonable nor warranted given the nature of the matter.
  • The alternative claims for restitution and unjustified enrichment did not require detailed consideration as the express terms of the contract governed payment for all work done.

Court disposition

Application for amendment refused; costs awarded against the applicant.

  • The application for amendment is refused.
  • The applicant is to pay the costs of the application.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2018] ZAGPPHC 102

IN THE HIGH COURT OF SOUTH

AFRICA

(GAUTENG DIVISION. PRETORIA)

(1)

NOT REPORTABLE

(2)

NOT OF INTEREST TO OTHER

JUDGES

(3)

REVISED

Case No. 10058/2017

14/3/2018

In the matter between:

MAHLALERWA-KGABO-ERGO

JV

APPLICANT

And

COOPERATIVA

MURATORI

CEMENTISTI

RESPONDENT

RAVENNA (PTY) LTD T/A C.M.C di RAVENNA

(SOUTH AFRICA)

JUDGMENT

MILLAR AJ

1. The applicant is the plaintiff in an action where the respondent is the defendant. After the entry of an appearance to defend, the respondent served a notice in terms of Rule 23(1) calling on the applicant to remove various causes of complaint which it contended rendered the particulars of claim excipiable.

2. The applicant responded by giving notice of intention to amend its

particulars of claim to address the causes of complaint. The respondent objected to the proposed amendment.

3. Before me is an application to amend. The respondent persists in its

objection to the proposed amendment on the following grounds:

3.1 Firstly, that the applicant seeks by the amendment to introduce the allegation in paragraph 6.2 that there were implied alternatively tacit terms to the written agreement where the respondent contends that this would be in direct contradiction of the express terms of the agreement;

3.2 Secondly, that the applicant seeks by the amendment to introduce a claim for restitution in respect of payment of its claim for work done; and

3.3 Thirdly, that the alternative claim to paragraphs 6 to 9 of the amendment for unjustified enrichment is bad in law.

4. The applicant argued that by virtue of the references in the written agreement for the necessity to comply, that both the work undertaken for compliance with the Health and Safety Procedures as well as the Site Establishment costs were contemplated costs to be borne by the respondent notwithstanding that the Bill of Quantities ("BOQ")

did not specifically provide for, and was silent on these costs.

5. The respondent argued that absent a reference to the specific items in the BOQ, there was neither an agreement nor obligation on the respondent to pay for these items. They were to be regarded as part of the contract price. The respondent relied on inter alia Hudson's Building and Engineering Contracts,[1] a leading work on the type of agreement entered into between the parties, as authority for this view.

6. The proposed amendment to introduce the pleading of a tacit alternatively

implied term of the agreement in question goes to one of the essentialia of the agreement - the contract price.

7. The contract price is referred to in three parts of the written agreement, in the preamble to the "Subcontractor's Offer" it reads :

"Having examined the Conditions of Subcontract, the Subcontract Specification, the Subcontractor's Drawings, and the Subcontract Schedule of Quantities for the execution of the abovenamed Subcontract Works, we, the undersigned, offer to execute and complete such Works (my underlining) and remedy any defects therein in conformity with the Conditions of Subcontract, the Subcontract Specification, the Subcontract Drawings, the Subcontract Schedule of Quantities for the indicative total sum of R1,950,353,51 (one nine five zero three five three million hundred thousand hundred Rand/51) plus R273,049,49 (two seven three zero four nine hundred thousand hundred Rand/49) representing VAT (14%), for a total of R2,223,403,00 (million hundred thousand hundred Rand/00) or such other sum as may be ascertained in accordance with the said Conditior1s. The above amounts are indicative only being the Subcontract Agreement between MAHLALERWA-KGABO-ERGO JV and CMG re-measurable"

And clause 16.1 of the "Conditions of Contract" which reads:

"The Subcontract Price R1,950,353,51 (one nine five zero three five three million hundred thousand hundred Rand/51) plus R 273,049,49 (two seven three zero four nine hundred thousand hundred Rand/49) representing VAT (14%), for a total of R2,223,403,00 (million hundred thousand hundred Rand/00) or such other sum as may be ascertained in accordance with the said Conditions. The above

mentioned amounts are indicative only being the Subcontract Agreement between BATCH 2 JV and CMG re­ measurable in accordance to rates submitted by the Subcontractor, included into ANNEX E (my underlining)"

And clause 16.1 of the "General Conditions which reads:

"The Subcontract Price is the sum stated in the Schedule of Quantities (Annex E) as payable to the Subcontractor for the design (if any), performance, execution. completion and warranty of the Subcontract Works (my underlining) and the remedying of any defects therein in accordance with the provisions of the Subcontract and/or Main Contract.

All duties, fees, taxes and any further cost payable by the Subcontractor, including overheads and profit shall be deemed to be included in the Prices and Rates of the Schedule of Quantities (my bold and underlining).

The Subcontractor shall be deemed to have satisfied himself as to the correctness and sufficiency of the rates and prices stated in the Schedule of Quantities, all of which shall, except insofar and as it is otherwise provided in the Subcontract, cover all his obligations under the Subcontract (including those in respect of the supply of goods, Materials, Plants or services) and all matters and things necessary for the proper execution and completion of the Subcontract Works and the remedying of any defects therein. If any item in the Schedule of Quantities is not priced by the Subcontractor, it will be deemed to have been priced at nil (my underlining)

8. The principle to be applied when having regard to whether or not an

implied or tacit term is to be read into an agreement is stated in SA Mutual Aid Society v Cape Town Chamber of Commerce 1962 (1) SA 598 (A) at 6150 :

"A term is sought to be implied in an agreement for the very reason that the parties failed to agree expressly thereon. Where the parties have expressly agreed upon a term and given expression to that agreement in the written contract in unambiguous terms no reference can be had to surrounding

circumstances in order to subvert the meaning to be derived from a consideration of the language of the agreement only. See Delmas Milling Co Ltd v Du Plessis 1955 (3) SA 447 (A) at 454."

9. The agreement is clear and unequivocal in regard to what is included in the contract price and as to the manner of the determination of that price. On a plain reading of the above clauses, and in particular those parts that I have underlined, there is express agreement as to the contract price and what is to be included and what is to be excluded. There is no basis upon which to impute the implied or tacit term which the applicant contends-for.

10. Having found that the agreement provides expressly for payment for all the work that was done by the plaintiff, it is not necessary for me to deal in any detail with the alternative claims for restitution and

unjustified enrichment that the applicant sought to introduce. In any event these do not seem to me to have been properly pleaded and had they been allowed, would have rendered the particulars of claim in any event excipiable.

11. The respondent argued that given the nature and importance of the matter, it was a wise and reasonable precaution for it to have briefed two counsel in this matter and that costs, irrespective of the order,

should be awarded to the respondent on this basis. The applicant argued that given the nature of the matter, the briefing of two

counsel was neither reasonable nor warranted. I agree with the submission of the applicant in this regard.

12 In the circumstances I make the following order:

12.1 The application for amendment is refused.

12.2 The applicant is to pay the costs of the application.

A MILLAR

ACTING JUDGE OF THE HIGH COURT

GAUTENG DIVISION, PRETORIA

HEARD ON: 6

MARCH 2018

JUDGMENT DELIVERED ON: 14

MARCH 2018

COUNSEL FOR THE APPLICANT: ADV.

K FITZROY

INSTRUCTED BY: JORDAAN

& SMIT INCORPORATED

REFERENCE: MR

J JORDAAN

COUNSEL FOR THE FIRST RESPONDENT: ADV. T. MAHON

ADV. ASHWORTH

INSTRUCTED BY: TERRY

MAHON ATTORNEYS

REFERENCE: MR

T MAHON

[1] 19th Edition, EJ Rimmer and IN Duncan Wallace, Sweet & Maxwell Ltd, 1959 , see especially the references at pages 109 -110 and to the 11th Ed . By IN Duncan Wallace QC, Sweet & Maxwell Ltd, 1995 at pages 497 - 498.

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

SA Mutual Aid Society v Cape Town Chamber of Commerce 1962 (1) SA 598 (A) at 615D

Case cited

Delmas Milling Co Ltd v Du Plessis 1955 (3) SA 447 (A) at 454

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.