Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Malgas and Another v Minister of Justice and Correctional Services (73418/2016) [2024] ZAGPPHC 183 (23 February 2024)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that all plaintiffs failed to comply with the statutory requirement under section 3 of Act 40 of 2002 to deliver written notice to the defendant within six months of the debt becoming due. The notices were sent late and no application for condonation was made prior to the trial date. The court held that compliance with section 3 is imperative and that failure to comply, without condonation, deprives the court of jurisdiction to entertain the claims. The case law cited by the plaintiffs was found to be irrelevant to the present issues. Accordingly, the special plea was upheld and the plaintiffs' claims were dismissed.

Court disposition

Plaintiffs' claims dismissed for failure to comply with statutory notice requirements under section 3 of Act 40 of 2002.

Orders

  • The plaintiffs' claim is dismissed on account of their failure to comply with the requirement of notice in terms of section 3 of Act 40 of 2002.
  • Plaintiffs to pay costs of suit, including costs of two counsel.

02

Material facts

Parties

Peter Thembekile Malgas

Plaintiff Counsel: Adv L de Klerk SC

Alfred Disco Biyela

Plaintiff Counsel: Adv L de Klerk SC

Boswell John Mhlongo

Plaintiff Counsel: Adv L de Klerk SC

Minister of Justice and Correctional Services

Defendant Counsel: Adv G Shakoane SC

03

Procedural history

  1. Posture

    Civil Trial / Special Plea Regarding Compliance With Statutory Notice Requirements

04

Questions and positions

Legal issues

Party arguments

Applicant
The plaintiffs argued that they complied with section 3 of Act 40 of 2002, asserting that the first plaintiff delivered notice timeously and that there was substantive compliance for the second and third plaintiffs, despite the notice being three months late. They contended that the delay was due to incomplete information during initial interactions with their legal team. Plaintiffs further argued that the defendant is bound by its pleadings and should have raised all defences, including the special plea, at once rather than in a piecemeal fashion. They relied on case law to support the position that the defendant cannot amend its plea at this late stage and that the defendant received the notice in June 2016, allowing sufficient time to investigate the claims before action was instituted.
Respondent
The defendant argued that all plaintiffs failed to comply with the statutory requirement to deliver notice within six months of the debt becoming due, as required by section 3 of Act 40 of 2002. The notices were sent by registered post on 21 December 2015, which was after the expiry of the six-month period for each plaintiff. The defendant maintained that no application for condonation was made by the plaintiffs and that, as a result, the court lacks jurisdiction to entertain the claims. The defendant asserted that the special plea was properly raised and that the plaintiffs' claims must be dismissed for non-compliance with the Act.

05

Court’s reasoning

  1. 01

    Section 3(1)-(2) of Act 40 of 2002

    No legal proceedings for the recovery of a debt may be instituted against an organ of state unless written notice of intention to institute proceedings is given within six months from the date the debt became due.

  2. 02

    Section 3(4)(a) of Act 40 of 2002

    If an organ of state relies on a creditor's failure to serve notice, the creditor may apply to court for condonation of such failure.

  3. 03

    Crompton Street Motors CC v Bright Idea Projects 44 (Pty) Ltd 2022 (1) SA 317 (CC)

    A party is bound by its pleadings and should raise all defences at once, not in a piecemeal fashion.

  4. 04

    Minister of Safety and Security v De Witt 2009 (1) SA 457 (SCA)

    Failure to comply with statutory notice requirements may deprive the court of jurisdiction to entertain the claim.

06

Ratio, limits and disposition

Ratio decidendi

The court found that all plaintiffs failed to comply with the statutory requirement under section 3 of Act 40 of 2002 to deliver written notice to the defendant within six months of the debt becoming due. The notices were sent late and no application for condonation was made prior to the trial date. The court held that compliance with section 3 is imperative and that failure to comply, without condonation, deprives the court of jurisdiction to entertain the claims. The case law cited by the plaintiffs was found to be irrelevant to the present issues. Accordingly, the special plea was upheld and the plaintiffs' claims were dismissed.

Obiter and limits

  • The court noted that parties should ensure compliance with statutory requirements before setting a trial date to avoid unnecessary litigation.
  • The court observed that the defendant properly raised the special plea and that the piecemeal raising of defences was not prejudicial in the circumstances.

Court disposition

Plaintiffs' claims dismissed for failure to comply with statutory notice requirements under section 3 of Act 40 of 2002.

  • The plaintiffs' claim is dismissed on account of their failure to comply with the requirement of notice in terms of section 3 of Act 40 of 2002.
  • Plaintiffs to pay costs of suit, including costs of two counsel.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2024] ZAGPPHC 183

THE

REPUBLIC OF SOUTH AFRICA

IN THE HIGH COURT OF

SOUTH AFRICA

GAUTENG HIGH COURT DIVISION, PRETORIA

Case no: 73418/2016

REPORTABLE: NO

OF INTEREST TO OTHER JUDGES: NO

REVISED

DATE: 23/02/2024

In the matter between:

PETER

THEMBEKILE MALGAS

First Plaintiff

ALFRED

DISCO BIYELA

Second Plaintiff

BOSWELL

JOHN MHLONGO

Third Plaintiff

and

MINISTER

OF JUSTICE AND CORRECTIONAL SERVICES

Defendant

J U D G M E N T – Section 3 of Act 40 of 2002

MAKHOBA, J

[1] On 26 January 2024 the defendant filed its amended plea and practice note whereby the defendant raised a special plea on the failure by the plaintiffs to comply with section 3 of Act 40 2002[1].

[2] It is common cause that in its original plea, the defendant did not raise a special plea of failure to comply with section 3 of 40 of 2002.

[3] To the defendant’s pre-trial questions[2] the plaintiffs replied as follow:

“18. Do the Defendants admit that they have not applied for condonation for the late delivery of the letter of demand?

· No application for condonation was made.

· The Plaintiffs persist with their statements in the particulars of claim namely that the Plaintiffs complied with the Act.”

[4] In the founding affidavit on behalf of the plaintiff’s it is submitted that the notice in terms of section 3 was timeously delivered in respect of the first plaintiff. In respect of the second and third plaintiff there was substantive compliance although such notice was three months late[3].

[5] It is submitted further in the founding affidavit that the reason why the notice was late in respect of the second and third plaintiffs is that the exact history and nature of the matter was incomplete at the point of the first months of interaction between the legal team and the plaintiffs[4].

[6] Thus, the issue before court is whether the plaintiff have timeously complied with the requirement of prior notice to the defendant in terms of section 3(1), 2(3) of Act 40 of 2002

[7] Counsel for the defendant argues that the six months period within which the plaintiffs were required to have issued a notice in terms of section 3 of Act 40 of 2002 is as follows:

7.1 The first plaintiff was released on 25 June 2015 and the six months period (Notice in terms section 3) lapsed on 25 December 2015.

7.2 The second and third plaintiffs were released on 25 March 2015 and the six months period lapsed on 25 September 2015.

[8] Counsel for the defendant submitted that the plaintiffs only sent their notices by registered post to the defendant on 21 December 2015. This is common cause between the parties. Counsel for the defendant submitted further that such notices only received by the defendant on the date after 21 December 2015. As a result, the notices were issued late.

[9] The result thereof is that such notice was only received by the defendant on date after 21 December 2015.

[10] Finally counsel for the defendant contended that, the plaintiffs application for condonation in this court was refused and not heard, the plaintiffs are therefore not entitled to institute and prosecute their actions before this court.

[11] It is contended further that this court is without the necessary power or jurisdiction to entertain the plaintiffs actions or claims[5].

[12] On behalf of the plaintiffs counsel provided three reasons why the court should dismiss the special plea. The reasons are as follow:

12.1 “The Defendant is bound by his pleadings”

12.2 “The defendant had to raise all his defences at once; he cannot plead his defences in a piecemeal fashion”

12.3 “The plaintiffs complied with section 3 of Act 40 of 2002”

The defendant is bound by his pleadings.

[13] Counsel for the plaintiff referred the court to the decisions in Soth African Transport and Allied Workers Union and Another v Garvas[6] and MJK v IIK [7] and submitted that the defendant is bound by the way in which it pleaded its second special plea. This plea it is argued is based on an erroneous premise that the debt was due in 2012.

Defendant cannot plead in a piecemeal fashion.

[14] According to counsel for the plaintiffs, the defendant should have raised all the defences at the same time. In this regard counsel for the plaintiff relies on the decision in Crompton Street Motors CC v Bright Idea Projects 44(Pty) Ltd[8].

[15] It is further argued that the section 3 special plea should have been raised 2018 together with the special plea of non-joinder and misjoinder. The defendant should not be allowed to raise it now six year later.

Compliance with section 3 of Act 40 of 2002

[16] It is submitted on behalf of the plaintiffs that it appears from the answering affidavit that the defendant received the notice somewhere in June 2016.

[17] The plaintiffs instituted their action on 6 October 2016. Therefore the defendant could investigate the plaintiffs claim for the whole of July to September 2016.

[18] The plaintiffs submit that there was compliance with section 3 of Act 40 of 2002. The court must dismiss the special plea.

[19] In terms of section 3 of Act 40 of 2002 no legal proceedings for the recovery of a debt may be instituted against an organ of state unless the creditor has given the organ of state in question written notice of its intention to institute proceedings.

[20] The creditor’s written notice must be served on the organ of state within six months from the date on which the debt became due.

[21] Section 3 (4) (a) of Act 40 of 2002 reads as follows:

“(4) (a) if an organ of state relies on a creditor’s failure to serve a notice in terms of subsection (2)(a), the creditor may apply to a court having jurisdiction for condonation of such failure.”

[22] In this matter before me, the notice furnished by the plaintiffs to the defendant were sent by registered post on 21 December 2015. I am satisfied that all the plaintiffs’ notices in terms of section 3 of Act 40 of 2002 were sent to the defendant late, contrary to the provisions of section 3 of Act 40 of 2002.

[23] In my view it was imperative for the plaintiff to ask for condonation in terms of section 3 (4) (a) before a trial date was set. It is clear from the pleadings and the pre-trial that the defendant did raise with the plaintiffs the shortcomings in respect of the provision of section 3 of Act 40 of 2002. It is further my view that the plaintiffs should have made sure that they have complied with the provisions of section 3 of Act 40 of 2002 before the trial date was set.

[24] The case law referred to by counsel for the plaintiff does not have a bearing in the issues before me and can therefore not assist the plaintiffs.

[25] I make the following order:

25.1 The plaintiffs claim is dismissed on account of their failure to comply with the requirement of the notice in terms of section 3 of Act 40 of 2002

25.2 Costs of suit including cost of two counsel.

MAKHOBA

J

JUDGE

OF THE HIGH COURT

GAUTENG DIVISION, PRETORIA

HEARD AND RESERVED JUDGMENT: 21 February 2024

JUDGMENT HANDED DOWN ON: 23 February 2024

Appearances:

For the Plaintiffs: Adv L de Klerk SC with Adv D Thaldar (instructed by) Gildenhuys Malatji Incorporated

For the Defendant Adv G Shakoane SC with Adv D D Mosoma (instructed by) State Attorney Pretoria.

[1] CaseLines 000001 Sub-paragraph 2 at 000001 – 146, 000001-147 and 000001-148 paragraphs of 12,4, 13.4 and 14.4 of the Defendant’s

plea to plaintiffs amended particulars of claim.

[2] CaseLines 000001-17.

[3] CaseLines 33-2-10.

[4] CaseLines 33-2-13 ap Par 5.2

[5] CaseLines 0006-74 paragraph 21; Minister of Safety and Security v De Witt 2009 (1) SA 457 (SCA).

[6] 2013 (1) SA 83 (CC).

[7] 2023 (2) SA158(SCA).

[8] 2022 (1) SA 317 (CC).

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Minister of Safety and Security v De Witt 2009 (1) SA 457 (SCA)

Case cited

South African Transport and Allied Workers Union and Another v Garvas 2013 (1) SA 83 (CC)

Case cited

MJK v IIK 2023 (2) SA 158 (SCA)

Case cited

Crompton Street Motors CC v Bright Idea Projects 44 (Pty) Ltd 2022 (1) SA 317 (CC)

Case cited

Act 40 of 2002

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.