Download PDF

South Africa Judgment

Kwazulu-Natal High Court, Durban

Maximum Profit Recovery (Pty) Ltd v Umkhanyakude District Municipality and Another (D12061/2024) [2025] ZAKZDHC 32 (23 May 2025)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the Municipality's decision to appoint the second respondent via a quotation process was unlawful and constitutionally invalid. The value of the contract exceeded the statutory threshold for competitive bidding, and the Municipality's use of a quotation process constituted prohibited contract splitting. The Municipality failed to invite all panel members to quote, did not comply with its own policies, and did not provide evidence justifying its deviation from the competitive process. The procurement process lacked transparency, fairness, and accountability, violating section 217 of the Constitution and the Preferential Procurement Policy Framework Act. The Municipality's discretion to allocate work among panel members did not absolve it from compliance with statutory procurement requirements. The court set aside the appointment and any resulting agreements, ordered repayment of any amounts paid, interdicted further use of the quotation process for the tender, and directed the Municipality to allocate work based on statutory scoring.

Court disposition

Application granted; Municipality's decision and resulting agreements set aside; costs awarded to applicant.

Orders

  • The decision of the first respondent to appoint the second respondent to provide VAT review and recovery services in respect of Tender S[...] through the sourcing of quotations for a period of 12 months at a rate of 14.25% is declared to be constitutionally invalid and unlawful and is set aside.
  • Any agreement concluded between the respondents pursuant to the decision described above is set aside.
  • The second respondent is ordered to repay all amounts received from the first respondent pursuant to the invalid decision.
  • The first respondent is interdicted from utilising a quotation process to procure any goods and services that fall within the ambit of Tender S[...].
  • The first respondent is ordered to perform a point scoring of each of the members of the existing panel in respect of any goods and services that fall within the ambit of Tender S[...], and to allocate work on the basis that preference is given to the highest-scoring tenderer on the panel.
  • The first respondent is ordered to pay the applicant's costs, including costs consequent upon the employment of Senior Counsel, on Scale C in respect of this application and the matter under case number D9873/2024.

02

Material facts

Parties

Maximum Profit Recovery (Pty) Ltd

Applicant Counsel: APJ Els SC

Umkhanyakude District Municipality

Respondent Counsel: S Kuboni

PK Consulting Group CC

Respondent

Amounts and remedies

  • Contract Value Allocated by Municipality: ZAR 2,000,000
  • Percentage Rate Quoted by Second Respondent: ZAR 14.25

03

Procedural history

  1. Posture

    Review Application / Judgment Delivered After Opposed Review Application

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contended that the Municipality's appointment of the second respondent through a quotation process was expressly prohibited by its own Supply Chain Management Policy and the Municipal Supply Chain Management Regulations. The applicant argued that the Municipality was obliged to use a competitive tender process for services exceeding R200,000, and that the failure to invite all panel members to quote was procedurally unfair and irrational. The process was said to breach section 217 of the Constitution and Regulation 19(a), and amounted to unlawful contract splitting.
Respondent
The Municipality argued that its contractual arrangement with panel members allowed it discretion to award work on an 'as and when required' basis, guided by internal prescripts and Standard Operating Procedures. It claimed to have followed its procedures in selecting three panel members for quotations and awarding the contract to the second respondent, asserting that its actions were lawful and consistent with its policies.

05

Court’s reasoning

  1. 01

    Municipal Supply Chain Management Regulations, Regulation 19

    Goods or services above R200,000 may only be procured through a competitive bidding process; splitting contracts to avoid this requirement is prohibited.

  2. 02

    Preferential Procurement Policy Framework Act 5 of 2000; section 217 of the Constitution

    Public procurement must be fair, equitable, transparent, competitive, and cost-effective; contracts must be awarded to the highest scoring tenderer unless justified by law.

  3. 03

    Promotion of Administrative Justice Act 3 of 2000 (PAJA), sections 6(2)(b), 6(2)(c), 6(2)(f)(ii)

    Administrative action that is procedurally unfair, irrational, or inconsistent with statutory requirements is reviewable and may be set aside.

  4. 04

    Allpay Consolidated Investment Holdings (Pty) Ltd and Others v Chief Executive Officer, South African Social Security Agency and Others 2014 (1) SA 604 (CC)

    Municipalities must comply strictly with procurement laws and cannot rely on internal policies to circumvent statutory requirements.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the Municipality's decision to appoint the second respondent via a quotation process was unlawful and constitutionally invalid. The value of the contract exceeded the statutory threshold for competitive bidding, and the Municipality's use of a quotation process constituted prohibited contract splitting. The Municipality failed to invite all panel members to quote, did not comply with its own policies, and did not provide evidence justifying its deviation from the competitive process. The procurement process lacked transparency, fairness, and accountability, violating section 217 of the Constitution and the Preferential Procurement Policy Framework Act. The Municipality's discretion to allocate work among panel members did not absolve it from compliance with statutory procurement requirements. The court set aside the appointment and any resulting agreements, ordered repayment of any amounts paid, interdicted further use of the quotation process for the tender, and directed the Municipality to allocate work based on statutory scoring.

Obiter and limits

  • Municipal efficiency and service delivery may be enhanced by appointing panels, but this cannot justify non-compliance with procurement laws.
  • Internal policies and standard operating procedures cannot override statutory requirements for fairness, transparency, and competition.
  • A rotation process among panel members must still comply with statutory scoring and allocation requirements.
  • Organs of state cannot craft separate systems of awarding contracts that are contrary to law and open to abuse.
  • The two-stage bidding process under Regulation 25 was not applicable to the facts of this case.

Court disposition

Application granted; Municipality's decision and resulting agreements set aside; costs awarded to applicant.

  • The decision of the first respondent to appoint the second respondent to provide VAT review and recovery services in respect of Tender S[...] through the sourcing of quotations for a period of 12 months at a rate of 14.25% is declared to be constitutionally invalid and unlawful and is set aside.
  • Any agreement concluded between the respondents pursuant to the decision described above is set aside.
  • The second respondent is ordered to repay all amounts received from the first respondent pursuant to the invalid decision.
  • The first respondent is interdicted from utilising a quotation process to procure any goods and services that fall within the ambit of Tender S[...].
  • The first respondent is ordered to perform a point scoring of each of the members of the existing panel in respect of any goods and services that fall within the ambit of Tender S[...], and to allocate work on the basis that preference is given to the highest-scoring tenderer on the panel.
  • The first respondent is ordered to pay the applicant's costs, including costs consequent upon the employment of Senior Counsel, on Scale C in respect of this application and the matter under case number D9873/2024.

Source and reliance status

Kwazulu-Natal High Court, Durban

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Kwazulu-Natal High Court, Durban

Judgment

[2025] ZAKZDHC 32

SAFLII Note: Certain personal/private details of parties or witnesses have been redacted from this document in compliance with the law and SAFLII Policy

FLYNOTES:

ADMINISTRATIVE – Tender – Competitive bidding process – Mandated for services exceeding R200,000 in value – Splitting of contracts to avoid this requirement prohibited –

Municipality was obligated to follow competitive process – Deviation from quotation process – Limited to only three panel members – Constitutionally invalid and unlawful – Circumvented statutory scoring system – Violated procurement laws and municipality's own policies – Appointment declared invalid and set aside.

IN THE HIGH COURT OF

SOUTH AFRICA

KWAZULU-NATAL LOCAL DIVISION, DURBAN

CASE NO: D12061/2024

In the matter between:

MAXIMUM PROFIT RECOVERY (PTY) LTD

Applicant

and

UMKHANYAKUDE DISTRICT

MUNICIPALITY

First Respondent

PK CONSULTING GROUP CC

Second Respondent

ORDER

a) The decision of the first respondent to appoint the second respondent to provide VAT review and recovery services in respect of Tender S[...] through the sourcing of quotations for a period of 12 months

at a rate of 14.25% is declared to be constitutionally invalid and unlawful and is set aside;

b) Any agreement concluded between the respondents pursuant to the decision described in paragraph 1 of this Order is set aside;

c) Insofar as the first respondent has made any payment to the second respondent pursuant to the decision described in paragraph 1 of this Order, the second respondent is ordered to repay all such amounts to the first respondent;

d) The first respondent is interdicted from utilising a quotation process to procure any goods and services that fall within the ambit of Tender S[...];

e) The first respondent is ordered to perform a point scoring of each of the members of the existing panel in respect of any goods and services that fall within the ambit of Tender S[...], and to allocate

work on the basis that preference is given to the highest-soaring tenderer on the panel;

f) The first respondent is ordered to pay the applicants costs,

including the costs consequent upon the employment of Senior Counsel, on Scale C in respect of this application and the matter under case number D9873/2024.

JUDGMENT

SHAPIRO AJ

Overview

[1] In March 2024, the first respondent ("the Municipality")

published an invitation to tender, with the following description: “Bid Number: S[...] Panel of accounting support services for a period of 36 months”. The scope of work for which bidders were to tender included financial statements, preparation and audit support, financial support and business advisory, budget and reporting and "mSOCA" support, assets management, VAT review and recovery (which included reconciliation, review, and recovery of consolidated VAT) and actuarial services. Bidders were informed that the Municipality

intended to constitute a panel of service providers, but the bid document did not set out expressly how work would be allocated to successful appointees to the panel. All bidders were required to tender at an hourly rate for various levels of staff and were

required to indicate the rates per hour for each relevant rank for each of the three years of the proposed contract term.

[2] The applicant ("MPR") submitted a bid in respect of the VAT services discipline only. MPR and the second respondent were among 21 bidders who were appointed to the contemplated panel by the Municipality. That decision is not under review.

[3] MPR's review relates to what happened next: despite both it and the second respondent concluding Service Level Agreements with the Municipality, the Municipality then elected to issue an "Invitation for quotations for the value added tax (VAT) review for (the municipality) for a period of 12 months" under the same reference number as the original tender. That invitation was apparently transmitted by email to three members of the panel, including the second respondent. Only the second respondent replied to the Request and provided a quotation.

[4] Notwithstanding this, the Municipality sent a letter to the second respondent on 1 August 2024, informing the second respondent that it had "resolved to appoint (it) for the aforementioned project for the period of 12 months at the percentage of 14,25% starting from the 12 of August 2024”. The Municipality recorded that a written Service Level Agreement would have to be concluded between itself and the second respondent.

[5] It is the Municipality's decision to appoint the second respondent as its service provider for VAT services that is under review, together with consequential relief sought by the applicant. The second respondent did not take part in the review, which was opposed by the Municipality only.

[6] It remains unclear how the Municipality identified the three panellists from which to request quotations for the provision of VAT services as no documents in this regard were delivered as part of the Record of Decision. Similarly, it is not clear why the second respondent successfully quoted to provide the services "at the percentage of 14,25%" instead of at the hourly rates required by and contained in the original tender. The potential difference between the rate of remuneration tendered by the second respondent and the percentage-based rate that was later quoted was not disclosed in the Record either.

The applicant's grounds of review

[7] The applicant has argued that the appointment of the second respondent based on the quotation process adopted by the Municipality was expressly prohibited in its own Supply Chain Management Policy and the Municipal Supply Chain Management Regulations and further that the Municipality was obliged to come to utilise a competitive tender process[1]. The failure to invite all of the members of the panel to quote for the VAT services was procedurally unfair[2]. The quotation process was alleged to be in breach of the constitutional imperatives contained in section 217 of the Constitution[3], and the decision randomly to select three members of the panel to submit quotations was argued to be irrational[4]. Finally, the quotation process was alleged to be in direct conflict with Regulation 19(a) of the Municipal Supply Chain Management Regulations[5].

The municipality's defence of its decision

[8] The Municipality's submitted that the contractual arrangement between itself and the panel members for the award of work on an "as and when required" basis meant that it had a discretion to award work to different bidders guided by its internal prescripts and that it had followed its Standard Operating Procedures in exercising its discretion to allocate work to the second respondent.

The statutory procurement scheme

[9] The law as it applies to public procurement and how the court should deal with alleged irregularities in that process is settled[6].

[10] The alleged irregularity in the procurement process should be identified and if the court evaluates that the alleged irregularity amounts to a cognizable ground of review, the decision or award falls to be set aside.

[11] The Preferential Procurement Policy Framework Act[7] was enacted to give effect to the constitutional imperatives of fairness, equity, transparency, competition and cost effectiveness

contained in section 217 of the Constitution. The Municipality was obliged to determine a preferential procurement policy in terms of which the contract was awarded to the tenderer who scored the highest points in circumstances where (depending on the value of the contract) either 80 or 90 points out of a possible 100 points was awarded for price[8].

[12] Price is effectively paramount, and cost effectiveness is conditional upon competition. Competition, in turn, demands transparency and accountability - both for the sake of the organ of state concerned and the bidders competing to procure work from it.

[13] The integrity of the procurement process does not end with the awarding of a bid.

[14] Section 116 of the Municipal Finance Management Act[9] deals with contracts and contract management. Whilst it permits a contract procured through the SCM policy of a municipality to be amended by the contracting parties, this may only occur after the reasons for the proposed amendment have been tabled in the

municipality's council and the local community has not only been given reasonable notice of the intention to amend the contract but has also been invited to submit representations to the municipality.

[15] The Municipal Supply Chain Management Regulations[10] set out minimum requirements with which a municipality must comply when procuring goods and services. Regulation 19 requires that a SCM policy must specify that goods or services above a transaction value of (in this case) R200,000 inclusive of VAT may be procured by the municipality only through a competitive bidding process and that no requirement for goods or services above the estimated transaction value may deliberately be split into parts or items of lesser value merely for the sake procuring the goods or services, otherwise than through a competitive bidding process.

[16] It is beyond dispute that the contract value of the tender published by the Municipality exceeded R200,000.

The Municipality's internal policies

[17] Given the nature of the Municipality’s defence of its decision, it is necessary to consider its internal Supply Chain Management policies.

[18] The Municipality adopted a Supply Chain Management policy in terms of section 111 of the Municipal Finance Management Act.

[19] In terms of clause 14, goods and services could only be procured by way of formal written price quotations for procurement of a transaction value up to R200,000 including VAT and a competitive bidding process was required for procurement having a transaction value above that threshold and for the procurement of long-term contracts. The prohibition on splitting contemplated in Regulation 19 is repeated in clause 14(2).

[20] Clause 16 sets out the requirements in respect of a list of accredited prospective providers of goods and services and how prospective providers can apply for evaluation and listing. In terms of clause 18, quotations must then be obtained in writing from at least three different accredited providers and if it is not possible to obtain at least three quotations, reasons for this must be recorded and approved by the supply chain management manager or the chief financial officer of the municipality if the transaction value exceeds R 30,000. Clause 20 makes clear that goods and services above the threshold may only be procured through a competitive bidding process and splitting into parts "for the sake of procuring the

goods or services, otherwise than through a competitive bidding process" is not permitted.

[21] Clause 25 permits negotiations with preferred bidders arising out of the conclusion of a competitive tender process, providing that such negotiation neither permits the preferred bidder a second or unfair opportunity, nor is to the detriment of any other bidder nor leads to a higher price than the bid originally submitted.

[22] The Municipality has also adopted a Supply Chain Management Standard Operating Procedure.

[23] Clause 5. 1 of the policy is entitled "Sourcing of Quotations and clause 5.1.2 reads as follows:

‘5.1.2 From an appointed Panel

The nomination process has to follow a rotation method as per agreement.

Applicable preferential point system 80/20 or 90/10 should be stipulated and specific goals…where applicable.

(i) Verify if the panel is still valid;

(ii) The invitation for Quotations (RFQ) form will be drafted by an SCM Official, which must have a cover page with all the conditions of the quotation; specifications/TORs and a pricing schedule;

(iii) Invite quotations from the minimum number of service providers as per terms of the Panel;

(iv) Once quotation has been received, pricing must be checked against the unit price/rate as stipulated in the Panel…’.

[24] The Municipality argues that it complied with these provisions in awarding the 12-month VAT review contract to the second respondent and that its decisions to select three of the panellists and then to award the contract to the second respondent were lawful.

Could the municipality apply the quotations procedure?

[25] Both the statutory scheme and the Municipality's own SCM Policy and Standard Operating Procedure distinguish between the process to be followed for the procurement of goods and services under R200,000 and

those that exceed this amount.

[26] In the tender under review, the Municipality initiated a competitive bidding process. This was because the value of the services to be rendered over the contract term[11] exceeded the threshold. Logically, the quotation process could therefore not be used to procure the accounting and VAT services that the Municipality required. The Municipality was obliged to comply with the law and its own policies in evaluating the bids, scoring them and so on.

[27] The Municipality has failed to provide real answers to the following questions:

a) why did it decide to award a contract for 12-months instead of the 36-month period that it, itself, had sought in the tender?

b) if the VAT services were going to be discharged completely in the first year, why were those services included in the scope of work contained in the tender to be rendered over 36 months?

[28] The Municipality sought to justify its conduct by saying that the VAT services required for the 12-month period (and that justified a request for quotations) were different to that contemplated in the tender. However, this is not the case. The tender sought bids for services which included "VAT review and recovery: Reconciliation, review, and recovery of consolidated VAT". The Request for Quotations was expressed to be for "The Value Added Tax review" for the Municipality. While the required services may have been itemised in more detail in the Request for Quotation, they remained VAT review services.

[29] If new and previously uncontemplated services or needs arose in respect of VAT between March 2024[12] and July 2024[13], the Municipality was obliged to say so and explain what occurred. That it did not demonstrates that there was no difference in the services contemplated.

[30] There is no indication in the Record from the Municipality about why it was deemed necessary to seek a quotation for the provision of services for 12 months, when a few months before it had sought bids for the provision of services for 36 months, whilst requiring stipulated hourly rates for each year. Likewise, the Municipality did

not quantify the value of the services ostensibly to be rendered during the 12-month service period and gave no information about how the accepted rate of 14.25% of recoveries quoted by the second respondent was to be calculated to determine whether it fell under the threshold or not.

[31] On the evidence before me, contained in the Record disclosed by the Municipality, there is nothing that militates against the conclusion that the contract was "deliberately split into parts… for the sake of procuring the services, otherwise than through a competitive bidding process".

[32] In any event, the Municipality did not obtain three quotations from accredited suppliers – even if the second respondent was

somehow accredited by being appointed to the panel[14], the Municipality obtained only one quotation. Compounding matters, there was no evidence of the “minimum number of service

providers as per terms of the Panel”[15] and the price received from the second respondent (being a percentage-based recovery fee) could not be “checked against the … rate as stipulated in the Panel”.

[33] The Municipality ignored the provisions of its own Policy and procedure.

[34] It follows that the Municipality was not permitted to make use of the quotation process in respect of the provision of VAT services under the Tender and then to appoint the second respondent[16], and its decision to do so was unlawful.

Could the municipality allocate work to members of a panel at its own discretion?

[35] In principle, there is nothing objectionable about a municipality appointing a panel of service providers in respect of goods to be supplied or services to be rendered. Doing so may well increase efficiency and service delivery as a municipality will not be required to go out to tender each time it requires a specific service to be rendered, or if the successful bidder is unable to perform or the services exceed its capacity.

[36] There is also nothing objectionable about service providers being appointed on an "as and when required" basis and if the bidders tender for work on that basis, they can have no grounds to complain.

[37] However, a municipality cannot absolve itself of compliance with the statutory public procurement scheme for reasons either of efficiency or because it determines that its internal policies permitted to do so. If a practice is permitted where tenders are awarded not on the basis of cost effectiveness, competition or transparency, but instead on opaque, internal decisions, then a system designed for fairness and accountability collapses. Organs of state will be able to pay lip service to section 217 of the Constitution and the peremptory provisions of the procurement laws and nevertheless award a tender to a bidder whose bid otherwise would have failed.

[38] Neither municipal policies nor standard operating procedures can expressly or by implication condone non-compliance with the law. Cost effectiveness, transparency and competition cannot be sacrificed on

the altar of efficiency or convenience. These imperatives can coexist, but this must occur lawfully. Otherwise, the door to corruption is forced open.

[39] Therefore, and even if a panel of service providers is appointed by an organ of state, that entity must nevertheless comply strictly with the provisions of the public procurement laws when awarding bids or

allocating work. Even if bidders are appointed to a panel, the respective bids must still be assessed in terms of the PPPFA and

ranked accordingly. Depending on the value of the contract, either 80 or 90 points must continue to be allocated for price, and the remaining points must still be allocated in accordance with statutory transformation and empowerment imperatives.

[40] It may occur that an organ of state reserves the right not to award a tender to the cheapest bidder because of transformation and empowerment imperatives, but this decision too must satisfy the lawfulness and rationality test if it is to survive a challenge.

[41] In the ordinary course however, an organ of state remains obliged to award a tender to the bidder who achieves the highest score and, if that party cannot supply the goods or render the services required in the time required, the organ of state then must award the bid to the party with the next highest score, and so on. A rotation process cannot be used mechanically and while ignoring these prescripts.

[42] Regulation 25 of the Municipal Supply Chain Management Regulations does not assist the Municipality either[17]. Regulation 25 permits supply chain management policies to permit a two-stage bidding process in limited circumstances, which include large complex projects, projects where it may be undesirable to prepare complete detailed technical specifications or long-term projects with a duration period exceeding three years. If such a process is permitted, technical proposals on conceptual design or performance specifications are to be invited in the first stage, subject to technical as well as commercial clarifications and adjustments and in the second stage final technical proposals and priced bids are invited.

[43] There is nothing in either the tender or the Record that would indicate that a two-stage process was contemplated or required. To the contrary, priced bids were sourced in a standard form tender (at the first phase) and the contract period did not exceed three years. Requiring bidders to tender on price for the provision of identified services and thereafter seeking quotations from certain identified bidders to the exclusion of the rest, does not constitute the two-stage bidding process contemplated in Regulation 25.

[44] I accept that a contrary conclusion was reached by Djaje AJP in Maximum Profit Recovery (Pty) Ltd v Naledi Local Municipality[18]. I respectfully differ with the conclusions reached in that case and decline to follow them. The Municipality did not call for technical proposals in the first stage and pricing at the second stage of the process, even if the sourcing of accounting services identified in the tender fell within the ambit of Regulation 25 – which, to my mind, it did not. Pricing was required in the tender and bids were required to be firm for 90 days because SLA’s were to be (and were) concluded based on those prices.

[45] Further, and if the two-stage process was properly to be invoked, priced bids would still have to be evaluated in terms of the scheme set out in the PPPFA and other statutory instruments.

[46] Organs of state cannot craft a separate system of awarding contracts that runs contrary to the law, and which is open to abuse. Quotations cannot be sourced if the value of the service to be rendered exceeds the stipulated threshold, and the threshold is to be determined by reference to the total transaction value that informs which procedure (quotation or competitive bid) is invoked at the commencement of the process.

[47] In these circumstances, it is appropriate that orders be granted which prohibit the Municipality from using the quotation process to procure any goods and services falling within the tender and directing it to comply with the statutorily required scoring of the panel members and the concomitant allocation of work to the appropriate members of the panel.

Conclusion

[48] The applicant has therefore successfully established that the decisions taken by the Municipality were unlawful and constitutionally invalid and fall to be set aside.

[49] There is no reason why costs should not follow the result. I am not persuaded that a punitive costs order is merited especially as there was a previous judgement that endorsed the Municipality’s actions.

[50] I am satisfied also that the urgent application that was launched by the applicant under case number D9873/2024 and which interdicted the Municipality and the second respondent from implementing their agreement was necessary and that the applicant should be entitled to its costs in that respect as well.

Orders

[51] I make the following orders:

(a) The decision of the first respondent to appoint the second respondent to provide VAT review and recovery services in respect of Tender S[...] through the sourcing of quotations for a period of 12 months at a rate of 14.25% is declared to be constitutionally invalid and unlawful and is set aside;

(b) Any agreement concluded between the respondents pursuant to the decision described in paragraph 1 of this Order is set aside;

(c) Insofar as the first respondent has made any payment to the second respondent pursuant to the decision described in paragraph 1 of this Order, the second respondent is ordered to repay all such amounts to the first respondent;

(d) The first respondent is interdicted from utilising a quotation process to procure any goods and services that fall within the ambit of Tender S[...];

(e) The first respondent is ordered to perform a point scoring of each of the members of the existing panel in respect of any goods and services that fall within the ambit of Tender S[...], and to allocate work on the basis that preference is given to the highest-soaring tenderer on the panel;

(f) The first respondent is ordered to pay the applicants costs, including the costs consequent upon the employment of Senior Counsel, on Scale C in respect of this application and the matter under case

number D9873/2024.

SHAPIRO AJ

Appearances

Counsel for Applicants: Advocate APJ Els SC Instructed by: Albert Hibbert Attorneys 231 Lange Street Nieuw Muckleneuk Pretoria Tel: 012 346 4633 Email: aha3@hibbertlaw.co.za Counsel for First Respondents: Advocate S Kuboni Instructed by: Nompumelelo Hadebe Inc Suite 1202, 12th Floor Metlife Building 391 Anton Lembede Street Durban Tel: 031 304 3655 Email: litigation@nhadebeattorneys.co.za Date Judgment Reserved: 29 April 2025 Date Judgment Delivered: 23 May 2025

[1] Section 6(2)(b) of the Promotion of Administrative Justice Act 3 of 2000 (“PAJA”)

[2] Section 6(2)(c) of PAJA

[3] Section 6(2)(i) of PAJA

[4] Section 6(2)(f)(ii) of PAJA

[5] Sections 6(2)(a)(i) and 6(2)(e)(i) of PAJA

[6] Allpay Consolidated Investment Holdings (Pty) Ltd and Others v Chief Executive Officer, South African Social Security Agency and Others 2014 (1) SA 604 (CC) at paras [22], [27], [28] and [43]

[7] Act 5 of 2000

[8] Sections 2(1)(b) and 2(1)(f) of the PPPFA

[9] Local Government: Municipal Finance Management Act 56 of 2003

[10] Municipal Supply Chain Management Regulations, published under GenN 868 in GG 27636 of 30 May 2005

[11] According to the Municipality, a budget of R2 million had been allocated.

[12] The closing date for the tender was 11 March 2024.

[13] When the Municipality requested quotations from the three members of the panel, including the second respondent

[14] Which I do not accept, and in respect of which no evidence was tendered

[15] There was no evidence of any stipulation or decision about how many members of the 21-member panel constituted a minimum number of service providers.

[16] cf Sections 6(2)(b), (d) and (f)(i) of PAJA

[17] Regulation 25 has been reproduced in the Municipality’s SCM policy as clause 26

[18] (M214/2022) [2023] ZANWHC 167 (15 September 2023) at paras [18] to [23]

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Allpay Consolidated Investment Holdings (Pty) Ltd and Others v Chief Executive Officer, South African Social Security Agency and Others 2014 (1) SA 604 (CC)

Case cited

Maximum Profit Recovery (Pty) Ltd v Naledi Local Municipality (M214/2022) [2023] ZANWHC 167 (15 September 2023)

Case cited

Promotion of Administrative Justice Act 3 of 2000 (PAJA)

Legislation

Legislation referenced in the available case record.

Preferential Procurement Policy Framework Act 5 of 2000

Legislation

Legislation referenced in the available case record.

Local Government: Municipal Finance Management Act 56 of 2003

Legislation

Legislation referenced in the available case record.

Municipal Supply Chain Management Regulations, GenN 868 in GG 27636 of 30 May 2005

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.