Download PDF

South Africa Judgment

Supreme Court of Appeal

Maykent (Pty) Ltd v Trackstar Trading 20 (Pty) Ltd (1036/2013) [2015] ZASCA 14 (17 March 2015)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The Supreme Court of Appeal held that the contract between Maykent and Trackstar was not governed strictly by the JBCC 2000 Principal Building Agreement, as the parties did not complete the contract variables or follow its procedures. The requirement for a certificate of completion before a final payment certificate was not applicable. Trackstar was entitled to payment upon submission of its final account, and Maykent was aware of its liability from that date. The summons was not premature. The counterclaim for damages was dismissed due to lack of evidence. Interest was correctly awarded from the date of summons, as Maykent had knowledge of the debt from the outset.

Court disposition

Appeal dismissed with costs.

Orders

  • The appeal is dismissed with costs.
  • Interest at the prescribed rate of 15.5% is payable from the date of summons to the date of payment.

02

Material facts

Parties

Maykent (Pty) Ltd

Appellant Counsel: M P van der Merwe SC

Trackstar Trading 20 (Pty) Ltd

Respondent Counsel: N A D Maritz SC, A A Botha

Amounts and remedies

  • Final Payment Certificate Amount: ZAR 963,475
  • Counterclaim for Damages (dismissed): ZAR 2,122,206
  • Prescribed Interest Rate: ZAR 15.5

03

Procedural history

  1. Posture

    Civil Appeal / Appeal From High Court, Gauteng Division, Pretoria

04

Questions and positions

Legal issues

Party arguments

Applicant
Maykent argued that no payment was due to Trackstar because the principal agent, TRE, had not issued a certificate of completion or a final payment certificate at the time the summons was served. Maykent relied on the JBCC 2000 Principal Building Agreement, asserting that its terms required these certificates before any payment obligation arose. Maykent also counterclaimed for damages, alleging loss of income due to Trackstar's delayed completion and additional costs paid to TRE.
Respondent
Trackstar contended that the contract was concluded partly orally, partly by conduct, and partly on the basis of standard industry terms, but the parties did not strictly adhere to the JBCC contract. Trackstar argued that it was entitled to payment upon submission of its final account and that Maykent was aware of its liability from that date. Trackstar maintained that interest should run from the date of summons and that Maykent's counterclaim was unsupported by evidence.

05

Court’s reasoning

  1. 01

    JBCC 2000 Principal Building Agreement

    Where parties do not adhere to the strict terms of a standard form contract, the court may find that certain formalities, such as the issuance of certificates, are not required for payment to become due.

  2. 02

    Prescribed Rate of Interest Act 55 of 1975

    Interest on a debt is payable from the date the debtor is aware of the liability, even if formal documentation is issued later.

  3. 03

    General principles of South African contract law

    A counterclaim for damages must be supported by evidence establishing causation and quantum.

06

Ratio, limits and disposition

Ratio decidendi

The Supreme Court of Appeal held that the contract between Maykent and Trackstar was not governed strictly by the JBCC 2000 Principal Building Agreement, as the parties did not complete the contract variables or follow its procedures. The requirement for a certificate of completion before a final payment certificate was not applicable. Trackstar was entitled to payment upon submission of its final account, and Maykent was aware of its liability from that date. The summons was not premature. The counterclaim for damages was dismissed due to lack of evidence. Interest was correctly awarded from the date of summons, as Maykent had knowledge of the debt from the outset.

Obiter and limits

  • The court noted that parties in the construction industry often proceed on the basis of standard terms but may not adhere to all formalities, which can affect the enforceability of certain contractual provisions.
  • The issuance of a final payment certificate years after the claim arose does not absolve the debtor from liability for interest if the debt was known and demandable earlier.

Court disposition

Appeal dismissed with costs.

  • The appeal is dismissed with costs.
  • Interest at the prescribed rate of 15.5% is payable from the date of summons to the date of payment.

Source and reliance status

Supreme Court of Appeal

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Supreme Court of Appeal

Judgment

[2015] ZASCA 14

THE

SUPREME COURT OF APPEAL OF SOUTH AFRICA

JUDGMENT

Not reportable

Case No: 1036/2013

In the matter between:

Maykent (Pty ) Ltd............................................................................................................Appellant

and

Trackstar Trading 20 (Pty) Ltd....................................................................................Respondent

Neutral Citation: Maykent v Trackstar (1036/2013) [2015] ZASCA 14 (17 March 2015)

Coram: Lewis, Maya, Bosielo, Majiedt and Pillay JJA

Heard: 27 February 2015

Delivered: 17 March 2015

Summary: Construction contract concluded partly orally, partly by conduct and partly on basis of standard terms used in industry did not oblige the principal agent to issue a certificate of completion before issuing final payment certificate: employer’s failure to pay the contractor on this basis over a period of five years unjustified.

ORDER

On appeal from: High Court, Gauteng Division, Pretoria (Hiemstra AJ sitting as court of first instance)

The appeal is dismissed with costs.

Lewis JA (Maya, Bosielo, Majiedt and Pillay JJA concurring)

[1] The appellant, Maykent (Pty) Ltd (Maykent), is a franchisee in respect of Kentucky Fried Chicken fast food stores. It entered into a contract with the respondent, Trackstar Trading 20 (Pty) Ltd (Trackstar), a building contractor, in February 2006 for the

alteration and addition to premises for a new store in New Town, Johannesburg. In concluding the contract, Maykent was represented by Tertius Rabe Property Services CC (TRE), a close corporation, appointed as the principal agent, which was the second defendant in the trial court.

[2] The agreed completion date was 30 June 2006 and the site was handed over to Trackstar on 30 March 2006. The completion date was extended to 15 September 2006 because of variation orders causing delay. Trackstar effected the works, and interim payments to it were made. The total agreed amount due in terms of the contract was some R1 282 922. Its final invoice was for R985 423. Payment was not made despite demand and Trackstar instituted action for payment of the amount it alleged was owing in the Gauteng Division of the High Court. The summons was served on 5 September 2008.

[3] TRE was cited as the second defendant, and as against it, Trackstar claimed a final account supported by vouchers. Maykent raised several defences, including one that amounted to a plea that nothing was yet due to Trackstar as a certificate of final completion had not been issued by TRE, as was required by the contract on which it relied – the standard JBCC 2000 Principal Building Agreement used in the construction industry. There was thus no cause of action, it asserted. It also counterclaimed for damages in the amount of R2 122 206 for alleged loss of income arising from Trackstar’s failure to complete the work timeously, and additional amounts it had had to pay TRE for completing the work.

[4] On 14 August 2013, shortly before the trial started, TRE issued a final payment certificate for the sum of R963 475. The action against it was withdrawn. The high court (Hiemstra AJ) found that Trackstar was entitled to payment of the amount in the final certificate, and dismissed the counterclaim on the basis that no evidence had been led to show that any loss suffered was caused by Trackstar’s alleged breach of contract. The high court also ordered that Maykent pay interest at the prescribed rate of 15.5 per cent from the date of summons to date of payment. The appeal against these orders lies with its leave.

[5] The principal argument of Maykent in the high court was that TRE had not issued a certificate of completion or a final certificate of payment when summons was served: there was thus no cause of action, the summons being premature. It relied in this regard on the 2000 JBCC standard agreement which it claimed was the basis of the contract between it and Trackstar. Indeed, Trackstar had also alleged that this was the contract that they had concluded, and attached it to its particulars of claim. The contract consists of standard terms and a schedule headed ‘Contract Variables’. The schedule reflected the parties’ details as well as those of TRE. However, much of the schedule was not completed by the parties, and did not reflect dates of signature.

[6] The particular clause of the JBCC contract relied on by Maykent (34.5) provided that a final certificate of payment would be issued by the principal agent only after a certificate of final completion had been issued by it. No final certificate of final completion had ever been issued, and indeed, TRE had prepared snag lists for remedial works to be done. These had not been attended to, Maykent contended, before Trackstar left the site on 8 November 2006.

[7] The evidence of TRE’s representative, a Mr Stears, who had overseen the building work, and attended site meetings on behalf of TRE, was that he had not worked according to the standard terms of the JBCC contract and did not know that it formed the basis of the parties’ agreement. The high court found that all the parties had proceeded as if the terms of the JBCC contract were not applicable, and thus that the provision in the JBCC contract requiring a certificate of completion, and then a final certificate

of payment, was not required. The claim for a final payment certificate, and then payment, was akin to a claim for a statement

and debatement of account, followed by payment, and that the summons was in the circumstances not premature.

[8] Although the heads of argument filed for Maykent on appeal continued to rely on this argument, and contended that the JBCC contract terms were binding, and that the high court had erred in this regard, at the hearing counsel did not persist with either argument. It was also conceded that no evidence had been led to establish that Maykent had suffered damages as a result of Trackstar’s breach.

[9] However, counsel did argue that it was inappropriate that interest should run from the date of summons when the final payment

certificate had been issued by TRE only five years after the litigation commenced. The summons was served, as I have said, on 5

September 2008, and the final payment certificate was issued on 14 August 2013. However, as argued by Trackstar, TRE was Maykent’s

agent, and it had known from the date when Trackstar issued its final account – 17 January 2007 – that the sum claimed was payable. TRE and Maykent were represented by the same attorneys throughout the litigation. There was no doubt that Maykent was aware of its liability to pay the amount due at the date of service of the summons.

[10] Trackstar was entitled to a final payment certificate and should have been paid on the submission of its final account. There is no reason to deny it interest on that sum at the prescribed rate from the date of summons.

[11] Accordingly the appeal is dismissed with costs.

_______

C H Lewis

Judge of Appeal

APPEARANCES

For Appellant: M P van der Merwe SC

Instructed by: Saunders Venter Van der Watt c/o

Louis Benn Attorneys, Pretoria

Lovius Block, Bloemfontein

For Respondent: N A D Maritz SC, A A Botha

Instructed by: Van Heerden & Krugel, Pretoria

Kramer Weihmann & Joubert Inc Bloemfontein

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Prescribed Rate of Interest Act 55 of 1975

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.