Mccarthy Contractors (Pty) Ltd. v Aegis Insurance Company Ltd. (374/92) [1993] ZASCA 199 (1 December 1993)
- Citation
- [1993] ZASCA 199
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Supreme Court of Appeal
- Panel
- Corbett, Vivier, Nienaber, Nicholas, Howie
- Case number
- 374/92
More details
- Court
- Supreme Court of Appeal
- Panel
- Corbett, Vivier, Nienaber, Nicholas, Howie
- Case number
- 374/92
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court held that, on a proper construction of section B of the policy, the indemnity for rectification of defects was limited to costs incurred during the period the policy was in force. The wording of the policy, read in context, did not support an interpretation that would extend cover to costs incurred after the expiry of the insurance period, even if the negligent act occurred within the retroactive period. As the appellant incurred the costs of rectification after the policy had lapsed, no liability arose under the policy. Consequently, the indemnity did not fall within the meaning of section 156 of the Insolvency Act, and the appellant could not claim against the respondent insurer.
Court disposition
Appeal dismissed. The respondent is not liable to indemnify the appellant for costs incurred after the expiry of the insurance period.
Orders
- The appeal is dismissed.
- Appellant is ordered to pay the costs of the appeal.
02
Material facts
Parties
Mccarthy Contractors (Pty) Limited
AppellantAegis Insurance Company Limited
Respondent03
Procedural history
Posture
Civil Appeal / Appeal From Trial Court Decision on Separated Questions of Law
04
Questions and positions
Legal issues
- 01
Whether section B of the insurance policy covers indemnification for costs incurred by a third party in rectifying defects.
- 02
Whether the insurer is obliged to indemnify for costs incurred after the expiry of the insurance period.
- 03
Whether the indemnity under section B constitutes an indemnity within the meaning of section 156 of the Insolvency Act.
Party arguments
- Applicant
- The appellant contended that section B of the policy entitled Burrows, and by substitution the appellant, to indemnification for costs incurred in rectifying defects, regardless of whether those costs were incurred by Burrows or a third party. The appellant argued that the policy's retroactive date and the nature of the professional indemnity cover meant that liability could arise for negligent acts occurring within the specified period, even if the costs were incurred after the insurance period ended. The appellant further submitted that such indemnity fell within the scope of section 156 of the Insolvency Act, allowing the appellant to claim in Burrows's stead.
- Respondent
- The respondent maintained that section B of the policy only covered costs incurred by Burrows during the currency of the insurance period. The respondent argued that the indemnity did not extend to costs incurred after the policy had expired, regardless of when the negligent act occurred. Consequently, the respondent asserted that no liability arose under the policy for costs incurred by the appellant after the insurance period, and therefore, section 156 of the Insolvency Act did not apply.
05
Court’s reasoning
Legal principles
- 01
Santam Insurance Ltd v Taylor 1985 (1) SA 514 (A)
An insurance policy must be interpreted according to its clear wording, giving effect to the intention of the parties as expressed in the contract.
- 02
Insolvency Act 24 of 1936, s 156
Section 156 of the Insolvency Act allows a third party to claim in the stead of an insolvent where the insolvent would have had a right of indemnity.
06
Ratio, limits and disposition
Ratio decidendi
The court held that, on a proper construction of section B of the policy, the indemnity for rectification of defects was limited to costs incurred during the period the policy was in force. The wording of the policy, read in context, did not support an interpretation that would extend cover to costs incurred after the expiry of the insurance period, even if the negligent act occurred within the retroactive period. As the appellant incurred the costs of rectification after the policy had lapsed, no liability arose under the policy. Consequently, the indemnity did not fall within the meaning of section 156 of the Insolvency Act, and the appellant could not claim against the respondent insurer.
Obiter and limits
- The court noted that the retroactive date provision in the policy was intended to extend cover for negligent acts occurring before the insurance period, but only where the costs were incurred during the period of insurance.
- The court observed that the distinction between claims made and losses incurred policies is critical in determining the scope of indemnity under professional indemnity insurance contracts.
Court disposition
Appeal dismissed. The respondent is not liable to indemnify the appellant for costs incurred after the expiry of the insurance period.
- The appeal is dismissed.
- Appellant is ordered to pay the costs of the appeal.
Source and reliance status
Supreme Court of Appeal
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Supreme Court of Appeal
Judgment
Case No 374/92. E du Plooy
IN THE SUPREME COURT OF SOUTH AFRICA (APPELLATE DIVISION)
In the matter between:
MCCARTHY CONTRACTORS (PTY) LIMITED Appellant
andAEGIS INSURANCE COMPANY
LIMITED Respondent
Coram: CORBETT CJ, VIVIER, NIENABER JJA NICHOLAS et HOWIE AJJA.
Heard: Delivered:
8 November 1993. 1 December 1993.
2
JUDGMENT HOWIE AJA:Appellant, a company carrying on business as a building contractor, sued the respondent insurance company in the Witwatersrand Local Division for payment in terms of a professional indemnity insurance policy. After the pleadings were closed the parties requested the Court below, in terms of Rule 33(4), to decide three questions of law separately from the other issues. The trial Judge (Cloete J) assumed an answer favourable to appellant on one question but answered the other, decisive questions in favour of respondent. He consequently dismissed the claim but granted leave to appeal to this Court.
For the purposes of deciding the questions raised the following facts were either agreed or assumed.
In August 1987 appellant contracted to perform certain construction work on an hotel in Somerset West.
3This work ("the main contract") included the installationof an air-conditioning system. Later that monthappellant engaged R & M Burrows Air-Conditioning
(Proprietary) Limited ("Burrows") as a sub-contractor to
install the system. In November 1987 Burrows and
respondent entered into an insurance agreement pursuant
to which the policy in question was issued.
In accordance with authorisation granted by
respondent to a company referred to in the policy as "the
underwriters", respondent undertook to provide Burrows
with two forms of insurance cover. The material
provisions of the policy in that regard (omitting
presently irrelevant wording) read thus:
"SECTION A - PROFESSIONAL LIABILITY.
The Underwriters agree to indemnify the Insured .... for the sums which the Insured shall become legally liable to pay arising from any claim or claims first made against them during the Period of Insurance as a direct result of negligence in the performance of the Insured's Professional Activities as specified in the Schedule by or on behalf of the Insured in the course of the Insured's business.
4
SECTION B - DEFECT IN CONTRACT WORKS. The Underwriters agree to indemnify the Insured .... for costs incurred in rectifying defects in the Insured's contract works or in the design plans or specification of such works.
PROVIDING
(a) The Insured can prove to the reasonable satisfaction of the Underwriters that the defect was the direct result of negligence in the performance of the Insured's Professional Activities by or on behalf of the Insured in the course of the Insured's business. (b) Indemnity for the rectification of defects shall not extend to include the repair of damage to any other part of the contract works resulting from such defects."
In the schedule to the policy the insurance
period was stated to be from 13 November 1987 to 12November 1988 and the insured's professional activities
were defined as meaning air-conditioning work undertakenby Burrows in its professional capacity. In addition,provision was made for what was called "the retroactive
date" and this was 1 November 1985. The importance of
that date was that in terms of an exclusionary clause in
the policy the underwriters were not liable in respect of
the performance of any of the insured's professional
5activities prior to such date. Consequently, even if thesort of negligence referred to in the policy occurred prior to the insured period it could nonetheless lead to liability on the part of the underwriters if it occurred on or after the retroactive date.
As a result of negligence on its part which occurred between 1 November 1985 and 12 November 1988, Burrows failed to install the system in terms of the specifications of the main contract. Such negligence related to Burrows's defective design and installation of the system and constituted a breach of its professional duties in the conduct of its business activities.
Burrows did not renew the policy on expiry of the insurance period. It was later called on to rectify the defects but failed to do so.
On 21 February 1990 Burrows was provisionally liquidated and the provisional order was made final on 14 March 1990. Subsequently appellant itself incurred the cost of rectifying the defects and thereafter sued
6respondent for reimbursement. Appellant relied on theterms of section B of the policy and claimed in Burrows's stead by invoking the substitutionary right of action afforded by s 156 of the Insolvency Act, 24 of 1936.
On the facts outlined, the questions for decision by the Court a quo were these:
1. Whether, on a proper construction of section B of the policy, respondent undertook to indemnify Burrows for the costs which a third party incurred in rectifying defects referred to in that section.
2. If so, whether respondent was obliged to indemnify Burrows if such costs were incurred after termination of the insurance period.
3. Depending on the answers to 1 and 2, whether the indemnity in section B was an indemnity within the meaning of s 156 of the Insolvency Act.
The trial Judge, having assumed an answer
favourable to appellant on question 1, held, as regards
question 2, that the costs referred to in section B had
to be incurred during the period that the policy was in
force. Consequently, because appellant's costs were
incurred after that period had elapsed, respondent would7 not have been liable to Burrows under the policy. That,
in turn, meant, as regards question 3, that respondentwas not liable to appellant under s 156 of the InsolvencyAct.
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.