Mercedes Benz South Africa v Buffalo City Municipality (EL1123/2011, ECD1956/2011) [2015] ZAECELLC 17 (11 December 2015)
The court found that the defendant breached the contract by allowing the supply of electricity to exceed the agreed voltage parameters for a sustained period, which directly caused damage to the plaintiff's equipment and consequential losses. The evidence established that the over-voltage endured for hours, far exceeding the ten-minute allowance in the contract, and that the damage was not caused by any event specifically listed in the protective measures clauses. The court accepted the expert evidence that the capacitor banks were not in operation and that the abnormal over-voltage was unprecedented. The obligation on the plaintiff to take 'adequate measures' did not extend to...
- Citation
- [2015] ZAECELLC 17
- Parties
- Plaintiff: Mercedes Benz South Africa; Defendant: Buffalo City Municipality
- Court
- Eastern Cape High Court, East London Local Court
- Jurisdiction
- South Africa
- Judgment Date
- 11 December 2015
- Case Number
- EL1123/2011
- Procedural Posture
- Civil Trial / Liability Separated and Determined; Damages to Be Proved in Due Course
- Outcome
- Defendant found liable for damages caused by over-supply of voltage; quantum of damages to be determined in due course.
- Judges
- Pickering
- Legal Topics
- Breach of Contract, Supply of Electricity, Causation, Remoteness of Damage, Contractual Interpretation, Protective Measures
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Mercedes Benz South Africa
Plaintiff
Buffalo City Municipality
Defendant
Procedural Posture
Civil Trial / Liability Separated and Determined; Damages to Be Proved in Due Course
Legal Issues
- 1 Whether the defendant breached the agreement by supplying electricity outside the stipulated voltage parameters for longer than ten minutes.
- 2 Whether the breach caused damage to the plaintiff's equipment and consequential losses.
- 3 Whether the plaintiff was required to take additional protective measures under the contract and if failure to do so affects liability.
Ratio Decidendi
The court found that the defendant breached the contract by allowing the supply of electricity to exceed the agreed voltage parameters for a sustained period, which directly caused damage to the plaintiff's equipment and consequential losses. The evidence established that the over-voltage endured for hours, far exceeding the ten-minute allowance in the contract, and that the damage was not caused by any event specifically listed in the protective measures clauses. The court accepted the expert evidence that the capacitor banks were not in operation and that the abnormal over-voltage was unprecedented. The obligation on the plaintiff to take 'adequate measures' did not extend to...
Court Disposition
Defendant found liable for damages caused by over-supply of voltage; quantum of damages to be determined in due course.
Orders
- It is declared that defendant is liable to plaintiff for such damages as plaintiff may in due course prove it has suffered in consequence of the over supply of voltage to it by defendant on 26 September 2009.
- Defendant is ordered to pay the costs of the action to date, such costs to include the qualifying expenses of Mr Ansell and the cost of two counsel.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment