Milling Techniks (Pty) Ltd v MEC for the Department of Transport KwaZulu-Natal and Another (6319/2022) [2023] ZAKZPHC 136 (10 November 2023)

Milling Techniks (Pty) Ltd v MEC for the Department of Transport KwaZulu-Natal and Another (6319/2022) [2023] ZAKZPHC 136 (10 November 2023)

The court found that the applicant's dissatisfaction claim was submitted within the time period prescribed by the contract, as the cause of dissatisfaction only arose upon receipt of the certified payment certificate on 25 August 2021, and the claim was submitted 27 days later. The first respondent's argument that...

Source-derived case information.

Citation
[2023] ZAKZPHC 136
Parties
Applicant: Milling Techniks (Pty) Ltd; Respondent: MEC for the Department of Transport KwaZulu-Natal; Respondent: Tony Smith N.O.
Court
Kwazulu-Natal High Court, Pietermaritzburg
Jurisdiction
South Africa
Case Number
6319/2022
Procedural Posture
Urgent Application / Final Order on Application
Outcome
Application granted. The appointment of the adjudicator is declared valid and binding. The first respondent is ordered to sign and deliver the adjudicator’s contract, failing which the sheriff is authorised to do so. Costs awarded against the first respondent.
Judges
E Bezuidenhout
Legal Topics
Adjudication Under Gcc, Specific Performance, Time Barring of Claims, Contractual Dispute Resolution
Civil Procedure Commercial and Corporate Adjudication Under Gcc Specific Performance Time Barring of Claims Contractual Dispute Resolution

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Milling Techniks (Pty) Ltd

Applicant

MEC for the Department of Transport KwaZulu-Natal

Respondent

Tony Smith N.O.

Respondent

Procedural Posture

Urgent Application / Final Order on Application

  1. 1 Whether the applicant submitted its dissatisfaction claim within the time period prescribed by the contract.
  2. 2 Whether the adjudicator was validly appointed in terms of the contract and applicable rules.
  3. 3 Whether the first respondent is obliged to comply with the adjudication process under the contract.

Ratio Decidendi

The court found that the applicant's dissatisfaction claim was submitted within the time period prescribed by the contract, as the cause of dissatisfaction only arose upon receipt of the certified payment certificate on 25 August 2021, and the claim was submitted 27 days later. The first respondent's argument that the time period commenced earlier was rejected. The court held that the first respondent is contractually obliged to comply with the adjudication process and that the appointment of the adjudicator by SAICE was valid due to the first respondent's failure to respond to the applicant's request for nominations. The relief sought by the applicant was granted, and the first...

Court Disposition

Application granted. The appointment of the adjudicator is declared valid and binding. The first respondent is ordered to sign and deliver the adjudicator’s contract, failing which the sheriff is authorised to do so. Costs awarded against the first respondent.

Orders

  • The appointment of the second respondent as adjudicator is declared valid and binding.
  • The first respondent is directed to sign and deliver the adjudicator’s contract to the second respondent within five days of service of this order.