Minister of Public Works and Land Affairs and Another v Group Five Building Ltd. (653/94) [1996] ZASCA 63; 1996 (4) SA 280 (SCA); (30 May 1996)

Minister of Public Works and Land Affairs and Another v Group Five Building Ltd. (653/94) [1996] ZASCA 63; 1996 (4) SA 280 (SCA); (30 May 1996)

The Supreme Court of Appeal held that Claim D, being a claim for damages for breach of contract, became prescribed because the breaches and resulting losses occurred prior to July 1987, and the contractor either knew or could have known of the facts giving rise to the debt at that time. The court rejected the...

Source-derived case information.

Citation
[1996] ZASCA 63
Parties
Appellant: Minister of Public Works and Land Affairs; Appellant: Director General of the Department of Public Works and Land Affairs; Respondent: Group Five Building Limited
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
653/94
Procedural Posture
Civil Appeal / Appeal From the Transvaal Provincial Division on Prescription and Implied Terms in Contract
Outcome
Appeal upheld. Claim D is prescribed and dismissed. Costs awarded to appellants, including costs of two counsel.
Judges
Marais, Botha, E M Grosskopf, Vivier, Schutz
Legal Topics
Prescription Act, Implied Terms in Contract, Breach of Contract, Construction Contracts
Commercial and Corporate Civil Procedure Prescription Act Implied Terms in Contract Breach of Contract Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 5 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Minister of Public Works and Land Affairs

Appellant

Director General of the Department of Public Works and Land Affairs

Appellant

Group Five Building Limited

Respondent

Procedural Posture

Civil Appeal / Appeal From the Transvaal Provincial Division on Prescription and Implied Terms in Contract

  1. 1 Whether Claim D for damages for breach of contract was prescribed under the Prescription Act.
  2. 2 Whether the contract contained implied or tacit terms obliging the employer to provide drawings, instructions, and unrestricted site access timeously.
  3. 3 Whether the contractor's claim for damages arose only upon completion of the contract or at the time of breach.

Ratio Decidendi

The Supreme Court of Appeal held that Claim D, being a claim for damages for breach of contract, became prescribed because the breaches and resulting losses occurred prior to July 1987, and the contractor either knew or could have known of the facts giving rise to the debt at that time. The court rejected the argument that prescription only commenced upon completion of the contract or final certification, finding that the right to claim damages arose at the time of breach and was not dependent on the completion of the contract. The court further found that there was no reciprocal debt to suspend prescription under section 13(2) of the Prescription Act, nor was there any valid interruption...

Court Disposition

Appeal upheld. Claim D is prescribed and dismissed. Costs awarded to appellants, including costs of two counsel.

Orders

  • Plaintiff's Claim D is prescribed and is dismissed.
  • The costs of these proceedings, including the costs of two counsel, are to be paid by Plaintiff.