Mitsubishi Hitachi Power Systems Africa (Pty) Ltd v Murray and Roberts Ltd and Another (1011/2019) [2020] ZASCA 110; 2021 (5) SA 532 (SCA) (29 September 2020)

Mitsubishi Hitachi Power Systems Africa (Pty) Ltd v Murray and Roberts Ltd and Another (1011/2019) [2020] ZASCA 110; 2021 (5) SA 532 (SCA) (29 September 2020)

The Supreme Court of Appeal held that Murray & Roberts is contractually entitled to disclosure of information relevant to its entitlement to contractual benefits under clause 11.3 of the subcontracts. The court rejected Mitsubishi's arguments that privity and the Variation Agreement excluded such entitlement,...

Source-derived case information.

Citation
[2020] ZASCA 110
Parties
Appellant: Mitsubishi Hitachi Power Systems Africa (Pty) Ltd; Respondent: Murray & Roberts Ltd; Respondent: Eskom Holdings SOC Limited
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
1011/2019
Procedural Posture
Civil Appeal / Appeal From Gauteng Division of the High Court, Johannesburg
Outcome
Appeal dismissed with costs; order of the High Court modified to limit disclosure to relevant portions of incentive arrangements and information necessary for the subcontractor's entitlement.
Judges
NAVSA, DLODLO, NICHOLLS, POYO-DLWATI, UNTERHALTER
Legal Topics
Contractual Disclosure, Good Faith in Contracts, Confidentiality Obligations, Remedies for Breach, Subcontractor Rights
Commercial and Corporate Civil Procedure Contractual Disclosure Good Faith in Contracts Confidentiality Obligations Remedies for Breach Subcontractor Rights

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Mitsubishi Hitachi Power Systems Africa (Pty) Ltd

Appellant

Murray & Roberts Ltd

Respondent

Eskom Holdings SOC Limited

Respondent

Procedural Posture

Civil Appeal / Appeal From Gauteng Division of the High Court, Johannesburg

  1. 1 Does the subcontractor (Murray & Roberts) have a contractual right to require disclosure of incentive arrangements from the contractor (Mitsubishi)?
  2. 2 Does Mitsubishi owe a duty of confidentiality to Eskom that precludes disclosure to Murray & Roberts?
  3. 3 What is the scope of the subcontractor's right to disclosure and the appropriate remedy?

Ratio Decidendi

The Supreme Court of Appeal held that Murray & Roberts is contractually entitled to disclosure of information relevant to its entitlement to contractual benefits under clause 11.3 of the subcontracts. The court rejected Mitsubishi's arguments that privity and the Variation Agreement excluded such entitlement, finding that the pass-on obligation remains. The court further found that confidentiality obligations under the Main Contract do not preclude disclosure to Murray & Roberts as a subcontractor, and that Eskom did not assert any right to prevent disclosure. The remedy was tailored to require Mitsubishi to disclose only those portions of the incentive arrangements and information...

Court Disposition

Appeal dismissed with costs; order of the High Court modified to limit disclosure to relevant portions of incentive arrangements and information necessary for the subcontractor's entitlement.

Orders

  • The appeal is dismissed with costs, including costs occasioned by the employment of two counsel.
  • The order of the High Court is substituted: The first respondent (Mitsubishi) is directed to disclose to the applicant (Murray & Roberts) those portions of the Incentive Arrangements concluded between the first and second respondents that are relevant to the applicant's entitlement to contractual benefits in terms...