MLZ Constructive CC t/a Procem v Willow Riding Centre (A646/2014) [2014] ZAGPPHC 946 (2 December 2014)

MLZ Constructive CC t/a Procem v Willow Riding Centre (A646/2014) [2014] ZAGPPHC 946 (2 December 2014)

The court found that the appellant failed to prove that the CCTV system was fully operative on 1 April 2004, as required by the contract for payment to become due. The evidence, including the hand-over certificate and testimony from both parties, indicated that the system was not reliably functional and lacked remote access at the relevant time. The appellant's reliance on the certificate was misplaced, and its alternative argument regarding power supply was unsupported. The respondent's damages under counterclaim B were actual disbursements and properly awarded. Condonation for late filing was granted due to a satisfactory explanation, but the appeal itself was dismissed as the appellant...

Citation
[2014] ZAGPPHC 946
Parties
Appellant: MLZ Construction CC t/a Procem; Respondent: Willow Riding Centre
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Judgment Date
2 December 2014
Case Number
A646/2014
Procedural Posture
Civil Appeal / Appeal Against Magistrate's Court Judgment
Outcome
Appeal dismissed with costs.
Judges
AC Basson, DPJ Rossouw
Legal Topics
Breach of Contract, Damages, Condonation, Onus of Proof

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

MLZ Construction CC t/a Procem

Appellant

Willow Riding Centre

Respondent

Procedural Posture

Civil Appeal / Appeal Against Magistrate's Court Judgment

  1. 1 Whether the appellant discharged its onus to prove that the CCTV system was fully operative on 1 April 2004 and thus entitled to payment.
  2. 2 Whether the respondent was entitled to damages under counterclaim B for breach of contract.
  3. 3 Whether condonation for late filing of the notice of appeal and security should be granted.

Ratio Decidendi

The court found that the appellant failed to prove that the CCTV system was fully operative on 1 April 2004, as required by the contract for payment to become due. The evidence, including the hand-over certificate and testimony from both parties, indicated that the system was not reliably functional and lacked remote access at the relevant time. The appellant's reliance on the certificate was misplaced, and its alternative argument regarding power supply was unsupported. The respondent's damages under counterclaim B were actual disbursements and properly awarded. Condonation for late filing was granted due to a satisfactory explanation, but the appeal itself was dismissed as the appellant...

Court Disposition

Appeal dismissed with costs.

Orders

  • The appeal is dismissed with costs.