Mokala Beleggings (Pty) Ltd and Another v Minister of Rural Development and Land Reform and Others (2012 (4) SA 22 (SCA); [2012] 3 All SA 130 (SCA)) [2012] ZASCA 209; [2012] ZASCA 21 (23 March 2012)
The Supreme Court of Appeal held that the State was in deliberate default regarding payment and transfer, having instructed its conveyancers to delay due to budgetary constraints. The contractual clause 5.2 did not fix a definite date for transfer, so mora ex re did not apply. However, the written letters of demand, properly dispatched and received, placed the State in mora ex persona. The breach and notice provisions in the agreements were satisfied, and the department's evasive response did not create a bona fide dispute. The appellants suffered financial loss due to the delay, and the State was liable for mora interest on the purchase price for the specified periods. The appeal...
- Citation
- [2012] ZASCA 21
- Parties
- Appellant: Mokala Beleggings (Pty) Ltd; Appellant: Willem Hendrik Steyn Snyman; Respondent: Minister of Rural Development and Land Reform; Respondent: Director-General of the Department of Land Affairs; Respondent: Chief Land Claims Commissioner; Respondent: Regional Land Claims Commissioner: Gauteng and North West Province; Respondent: Deputy Director: Finance, Department of Land Affairs; Respondent: Minister of Finance; Respondent: Registrar of Deeds; Respondent: Mahlangu Attorneys; Respondent: Barolong ba ga Mariba Community
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 23 March 2012
- Case Number
- 276/2011
- Procedural Posture
- Civil Appeal / Appeal From Land Claims Court
- Outcome
- Appeal upheld. The order of the Land Claims Court is set aside and replaced with an order for payment of interest and costs.
- Judges
- MPATI, NAVSA, SNYDERS, MAJIEDT, WALLIS
- Legal Topics
- Mora Interest, Contractual Delay, Specific Performance, Land Claims, Sale of Land, Restitution of Land Rights Act
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Mokala Beleggings (Pty) Ltd
Appellant
Willem Hendrik Steyn Snyman
Appellant
Minister of Rural Development and Land Reform
Respondent
Director-General of the Department of Land Affairs
Respondent
Chief Land Claims Commissioner
Respondent
Regional Land Claims Commissioner: Gauteng and North West Province
Respondent
Deputy Director: Finance, Department of Land Affairs
Respondent
Minister of Finance
Respondent
Registrar of Deeds
Respondent
Mahlangu Attorneys
Respondent
Barolong ba ga Mariba Community
Respondent
Procedural Posture
Civil Appeal / Appeal From Land Claims Court
Legal Issues
- 1 Whether the State is liable for mora interest due to deliberate delay in transfer and payment of purchase price.
- 2 Whether the contractual provisions or written demand placed the State in mora.
- 3 Whether the breach provisions and notices were properly effected to trigger liability for interest.
Ratio Decidendi
The Supreme Court of Appeal held that the State was in deliberate default regarding payment and transfer, having instructed its conveyancers to delay due to budgetary constraints. The contractual clause 5.2 did not fix a definite date for transfer, so mora ex re did not apply. However, the written letters of demand, properly dispatched and received, placed the State in mora ex persona. The breach and notice provisions in the agreements were satisfied, and the department's evasive response did not create a bona fide dispute. The appellants suffered financial loss due to the delay, and the State was liable for mora interest on the purchase price for the specified periods. The appeal...
Court Disposition
Appeal upheld. The order of the Land Claims Court is set aside and replaced with an order for payment of interest and costs.
Orders
- The first to fourth respondents are ordered jointly and severally to pay the costs of the appeal.
- The first to fourth respondents are ordered to pay interest to the first applicant at the rate of 15.5% per annum on R1,450,000 from 28 November 2009 until 30 June 2010 and on a further R1,450,000 from 8 December 2009 until 12 July 2010.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment