Molema Projects and Developers CC v L F Bantjies Civil t/a Elcon Civil (853/2011) [2012] ZANCHC 33 (17 February 2012)
- Citation
- [2012] ZANCHC 33
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Northern Cape High Court, Kimberley
- Panel
- Olivier
- Case number
- 853/2011
More details
- Court
- Northern Cape High Court, Kimberley
- Panel
- Olivier
- Case number
- 853/2011
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the plaintiff's particulars of claim were vague, embarrassing, and contradictory. The written contract annexed to the particulars did not support the alleged entitlement to 84% of the remuneration received by the plaintiff, and the calculation of the overpayment was not reconcilable with the facts pleaded. The defects in the particulars of claim prejudiced the defendant, as it would be unable to plead meaningfully except by denying all allegations, which would itself be excipiable. The exception was therefore upheld. However, the court granted the plaintiff leave to amend its particulars of claim within 15 days, considering that the plaintiff had previously been afforded an opportunity to amend and should bear the costs of the exception.
Court disposition
Exception upheld with costs; plaintiff granted leave to amend particulars of claim within 15 days.
Orders
- The exception is upheld with costs.
- The plaintiff is granted leave to amend its particulars of claim within 15 days hereof.
02
Material facts
Parties
Molema Projects and Developers CC
Plaintiff Counsel: C KgotlagomangL F Bantjies Civil t/a Elcon Civil
Respondent Counsel: A H Burger SCAmounts and remedies
- Amount Alleged Overpaid: ZAR 234,176.37
- Amount Paid to Defendant: ZAR 481,919.66
- Amount Allegedly Payable to Defendant: ZAR 247,743.48
- Amount Allegedly Entitled for Specific Invoice: ZAR 53,206.3
03
Procedural history
Posture
Civil Procedure / Exception to Particulars of Claim
04
Questions and positions
Legal issues
- 01
Whether the plaintiff's particulars of claim are vague and embarrassing and thus excipiable.
- 02
Whether the written contract supports the alleged entitlement to 84% of the remuneration received by the plaintiff.
- 03
Whether the amount claimed as overpayment is properly pleaded and reconcilable with the facts.
- 04
Whether the plaintiff should be granted leave to amend its particulars of claim.
Party arguments
- Applicant
- The plaintiff argued that the exception should be dismissed as it was filed three days late and that the defendant had waived its right to file the exception. The plaintiff maintained that the particulars of claim sufficiently set out the basis for the alleged overpayment and the contractual entitlement to 84% of the remuneration received from the owner.
- Respondent
- The respondent contended that the exception was properly filed and that, in the absence of a notice of bar, it was entitled to proceed. The respondent argued that the particulars of claim were vague, embarrassing, and contradictory, particularly regarding the contractual entitlement and the calculation of the alleged overpayment. The respondent requested that the claim be dismissed or, alternatively, that the plaintiff be ordered to amend its particulars of claim.
05
Court’s reasoning
Legal principles
- 01
Erasmus: Superior Court Practice, Farlam et al, B1-158
An exception to particulars of claim is a pleading and, in the absence of a notice of bar, the defendant is entitled to proceed with the exception.
- 02
Landmark Mthatha (Pty) Ltd v King Sabata Dalindyebo Municipality and Others: In re African Bulk Earth Works (Pty) Ltd v Landmark Mthatha (Pty) Ltd and Others 2010 (3) SA 81 (ECM) paras [10] – [13]
A pleading is vague and embarrassing if it is contradictory or fails to disclose a clear cause of action, thereby prejudicing the defendant.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the plaintiff's particulars of claim were vague, embarrassing, and contradictory. The written contract annexed to the particulars did not support the alleged entitlement to 84% of the remuneration received by the plaintiff, and the calculation of the overpayment was not reconcilable with the facts pleaded. The defects in the particulars of claim prejudiced the defendant, as it would be unable to plead meaningfully except by denying all allegations, which would itself be excipiable. The exception was therefore upheld. However, the court granted the plaintiff leave to amend its particulars of claim within 15 days, considering that the plaintiff had previously been afforded an opportunity to amend and should bear the costs of the exception.
Obiter and limits
- The court noted that a delay of only three days in filing the exception did not justify an inference of waiver of the right to file.
- The court observed that the amount claimed as overpayment was not the precise difference between the amounts alleged to have been paid and those allegedly payable, further contributing to the vagueness of the pleading.
- The court remarked that the particulars of claim failed to clarify whether the work had been completed and finalised, which was material to the entitlement under the contract.
Court disposition
Exception upheld with costs; plaintiff granted leave to amend particulars of claim within 15 days.
- The exception is upheld with costs.
- The plaintiff is granted leave to amend its particulars of claim within 15 days hereof.
Source and reliance status
Northern Cape High Court, Kimberley
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Northern Cape High Court, Kimberley
Judgment
IN THE HIGH COURT OF
SOUTH AFRICA
(Northern Cape High Court, Kimberley)
Case Nr: 853/2011
Case Heard: 10/02/2012
Date delivered: 17/02/2012
In the matter between:
Molema Projects and Developers CC ….................................................PLAINTIFF
and
L F Bantjies Civil t/a Elcon Civil …....................................................RESPONDENT
Coram: Olivier J
JUDGMENT
Olivier J:
The defendant, L F Bantjies Civil CC (t/a Elcon Civil), has excepted to the particulars of claim of the plaintiff, Molema Projects and Developers CC, on the basis of it being vague and embarrassing.
The plaintiff’s attorney, Mr Kgotlagomang, argued in limine that the exception should be dismissed because it was filed three days late. There is no merit in this point. As pointed out by mr Burger SC, counsel for defendant, an exception to particulars of claim is a pleading and in the absence of a notice of bar the defendant is entitled to proceed with the exception1. There is even less merit in Mr Kgotlagomang’s reply that the defendant must be deemed to have waived its right to file an exception. A delay of only three days would not in these circumstances justify such an inference.
The cause of action is basically the conditio indebiti, it being alleged2 that the defendant overpaid the plaintiff in the amount of R234 176,373. It is also alleged that this was caused by a bona fide and reasonable mistake of fact and in circumstances where there had been no obligation to pay this amount to the defendant.
In paragraphs 3 to 9 of the particulars of claim the plaintiff clearly intended to plead facts to sustain the allegation that the payment had been sine causa. It was alleged that the parties had concluded a written contract in terms of which the defendant would subcontract for the plaintiff, at 84 % of the amounts paid to the plaintiff by De Beer Consolidated Mines (“the owner”)4.
The first complaint raised by the defendant, in paragraphs 1 and 1.1 of the exception, is basically that the purported written contract (annexure A to the particulars of claim) contains no provision to the effect that the defendant would be entitled to 84 % of the remuneration received by the plaintiff.
This is clearly so. In fact, the contents of the written contract are in effect difficult to reconcile with an allegation that the defendant’s remuneration would amount to 84 % of that received by the plaintiff. In clause 2.1.1 reference is made to fixed amounts to be paid to the defendant for “site-establishment”. There is no indication at all that the plaintiff would also be remunerated for site-establishment and that the amounts mentioned in clause 2.1.1 would constitute 84 % (or any other agreed percentage) thereof.
In clause 2.1.2 reference is made to the total amounts payable to the defendant in respect of the construction of “the works” involved in the two construction contracts. Again these amounts are on the face of them fixed and there is no indication of them constituting 84 % (or, once again, any other agreed percentage) of payments received by the plaintiff in it capacity as the contractor.
In paragraphs 6 to 9 of the particulars of claim it is basically alleged that the plaintiff rendered an account or invoice for an amount of R61 867,80 to the owner (after initially rendering one for an amount of R207 936,00 on the strength of an allegedly erroneous account or invoice rendered to the plaintiff by the defendant5), and that the defendant was then “in terms of agreement” only entitled to an amount of R53 206,30 (on the basis of the last account rendered by the plaintiff to the owner).
Although this was not raised by the defendant in its exception, it is clear that the amount of R53 206,30 would not amount to 84 % of the amount of R61 867,80 (the final amount of that particular account or invoice).
What was, however, raised in the exception is that it is impossible to reconcile the amount of R234 176,37, alleged in paragraph 10 to be the amount overpaid, with the allegations in paragraphs 6 to 9 of the particulars of claim.
Once again, this is quite correct. If an amount of R481 919,66 was paid to the defendant, as alleged in paragraph 10, while the defendant had only been entitled to an amount of R53 206,30, as alleged in paragraph 9, the difference and the amount of overpayment would have been R428 713,36, and not R234 176,376.
These defects make it impossible to discern how the amount claimed (R234 176,37) is made up, on what basis it is alleged that the plaintiff had been under no obligation to pay it and what error of fact had led to the alleged overpayment.
In my view there is a further defect in the particulars of claim. The amount of R481 919,66 allegedly paid to the defendant is far less than the total amounts payable to the defendant in terms of the written contract. It is not clear whether the work has been completed and finalised. If so, the defendant would, if no other payments had been made, be entitled to far more than the amount of R481 919,66. If not, the plaintiff’s case should probably have been that the defendant received remuneration in the form of progress payments. No such allegation was made and the only express mention in the contract of the issue of progress payments is to the effect that the plaintiff would receive payment from the owner as the work progressed.
Be that as it may, I am satisfied that the allegations in the particulars of claim are indeed vague and embarrassing, and in fact contradictory, on the grounds set out in the exception. The defendant is prejudiced. The only conceivable way in which it could approach these allegations in a plea, would be to simply deny all of them, which would render the plea excipiable?
It follows that I am of the view that the exception should be upheld. I am not, however, prepared to dismiss the claim, as requested on behalf of the defendant. In my view the plaintiff should be granted one more opportunity to amend its particulars of claim.
It is, however, a fact that the plaintiff was afforded this opportunity to amend, when confronted with the defendant’s notice in terms of Uniform Rule 23 (1). There can therefore be no doubt that the plaintiff should pay the costs of the exception.
In the premises I make the following order:
The exception is upheld with costs.
The plaintiff is granted leave to amend its particulars of claim within 15 days hereof.
______
C J OLIVIER
JUDGE
NORTHERN CAPE
DIVISION
For the Plaintiff: Mr C Kgotlagomang
Towel & Groenewaldt,
KIMBERLEY
For the Respondent: Adv A H Burger SC
Instructed by: Engelsman Magabane Inc, KIMBERLEY
1Erasmus: Superior Court Practice, Farlam et al, B1-158; Landmark Mthatha (Pty) Ltd v King Sabata Dalindyebo Municipality and Others: In re African Bulk Earth Works (Pty) Ltd v Landmark Mthatha (Pty) Ltd and Others 2010 (3) SA 81 (ECM) paras [10] – [13]
2in paragraph 10 of the particulars of claim
3allegedly the difference between the amount of R481 919,66 paid and the amount of R247 743,48 payable
4paragraphs 4 and 5 of the particulars of claim
5the repeated reference to an “amount” which had been rendered is clearly a typing error and was probably intended to refer to an account.
6The amount alleged in paragraph 10, and which is in any event not the precise difference between the R481 919,66 allegedly paid and the R247 743,48 allegedly payable
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.