Moodley v Eon Consulting (Pty) Ltd (JR968/16) [2017] ZALCJHB 446 (28 November 2017)
- Citation
- [2017] ZALCJHB 446
- Status
- Ruling
- Jurisdiction
- South Africa
- Court
- Labour Court Johannesburg
- Panel
- MC Mamosebo
- Case number
- JR968/16
More details
- Court
- Labour Court Johannesburg
- Panel
- MC Mamosebo
- Case number
- JR968/16
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the respondent failed to provide a reasonable and acceptable explanation for the substantial delay in filing its statement of response. The explanation offered was inadequate, did not cover the entire period of delay, and amounted to negligence and disregard for the court's rules. The court held that the applicant would be prejudiced if condonation were granted and that it would not be in the interests of justice to do so. Accordingly, the application for condonation was refused and costs were awarded against the respondent.
Court disposition
Condonation for the late filing of the statement of response is refused. Costs are awarded against the respondent.
Orders
- The late filing of the statement of response is not condoned.
- The respondent, Eon Consulting (Pty) Ltd, is ordered to pay the costs of this application.
02
Material facts
Parties
Vinothen Moodley
Applicant Counsel: Christopher GibsonEon Consulting (Pty) Ltd
Respondent Counsel: Riaz Itzkin03
Procedural history
Posture
Condonation Application / Ruling on Condonation for Late Filing of Statement of Response
04
Questions and positions
Legal issues
- 01
Whether the late filing of the statement of response by the respondent should be condoned.
- 02
Whether the delay in filing was reasonable and justified.
- 03
Whether the applicant would be prejudiced by condonation.
Party arguments
- Applicant
- The applicant argued that the respondent's statement of response was filed either 135 or 201 days out of time, and that the explanation provided for the delay was inadequate. The applicant contended that the delay was inordinate, prejudicial, and resulted from pure negligence and disregard for the court's rules. The applicant further submitted that the respondent failed to account for several periods of unexplained delay and that condonation should not be granted. Costs were sought against the respondent.
- Respondent
- The respondent argued that the delay was caused by internal upheaval, including retrenchments and resignations, which led to the fax-to-email system being unmonitored. The respondent claimed that the default judgment was only discovered in the junk mail folder months later. Counsel submitted that the respondent had good prospects of success and that the court should exercise its discretion to grant condonation, as the respondent would otherwise be precluded from defending the unfair dismissal claim on its pleaded case.
05
Court’s reasoning
Legal principles
- 01
Mankanyi v Anglo gold Ashanti Ltd [2011] BLLR 527 at para 8
Condonation may be granted if the interests of justice permit, considering factors such as the extent and cause of the delay, prejudice, reasonableness of the explanation, importance of the issues, and prospects of success.
- 02
Grootboom v National Prosecution Authority and Another 2014 (2) SA 68 (CC) at paras 50–51
Condonation is not granted merely for the asking; the interests of justice must be determined with reference to all relevant factors, and excessive unexplained delay may justify refusal regardless of prospects of success.
- 03
NUM v Council of Mineral Technology (1999) 2 BLLR 209 (LAC)
Without a reasonable and acceptable explanation for the delay, the prospects of success are immaterial.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the respondent failed to provide a reasonable and acceptable explanation for the substantial delay in filing its statement of response. The explanation offered was inadequate, did not cover the entire period of delay, and amounted to negligence and disregard for the court's rules. The court held that the applicant would be prejudiced if condonation were granted and that it would not be in the interests of justice to do so. Accordingly, the application for condonation was refused and costs were awarded against the respondent.
Obiter and limits
- The right to fair labour practices applies to both parties, but procedural compliance is essential.
- Condonation applications require full and reasonable explanations for all periods of delay.
Court disposition
Condonation for the late filing of the statement of response is refused. Costs are awarded against the respondent.
- The late filing of the statement of response is not condoned.
- The respondent, Eon Consulting (Pty) Ltd, is ordered to pay the costs of this application.
Source and reliance status
Labour Court Johannesburg
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Labour Court Johannesburg
Ruling
THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG
Not Reportable
Case no: JR 968/16
In the matter between:
VINOTHEN
MOODLEY
Applicant
and
EON CONSULTING (PTY)
LTD
Respondent
Heard: 17 November 2017
Delivered: 28 November 2017
JUDGMENT:
CONDONATION APPLICATION
MAMOSEBO AJ
[1] This is an application to condone the late filing of a Statement of Response by Eon Consulting (Pty) Ltd (Eon Consulting), the respondent
in the main action. For convenience, I will refer to the parties as they appear in the papers.
A brief factual background
[2] On 06 December 2016 the applicant, Mr Vinothen Moodley, served a default judgment on the respondent, Eon Consulting. The respondent claims that the said default judgment was retrieved from the junk mail folder by Ms Sithole, its employee, only in March 2017.
[3] The applicant filed its statement of claim on 22 November 2016. Eon Consulting, although aware of the statement of claim by 13 March
2017, only served its statement of response on 27 June 2017. The explanation proffered by Eon Consulting is that it was experiencing
an upheaval caused by large scale retrenchment processes and resignations of its employees, including senior personnel. No one was designated to monitor its fax to email through which all its legal documents were received. The problem of an unmonitored fax, according to Eon Consulting persisted for four months and is responsible for the statement of response being filed 135 days out of time. The applicant on the other hand contends that the statement is 201 days out of time. On either construction it must be determined whether such delay is inordinate and stands to prejudice the applicant.
[4] Mr Itzkin, counsel appearing for Eon Consulting, sought to convince me that the allegations in the applicant’s statement of claim are disingenuous and this Court lacks jurisdiction to hear the matter on procedural aspects because the applicant failed to approach this Court by way of an application in terms of section 189A (13) and (18) of the Labour Relations Act[1] (the LRA) and, instead, seeks relief based on section 191(5)(b)(ii) of the LRA. Counsel submitted that Eon Consulting has good prospects of success and that if condonation was not granted Eon Consulting will still be able to defend the matter as the Court will not be closing the door in its face. It will, however, be precluded from opposing the employee’s unfair dismissal claim on the basis of its pleaded case as alleged in its statement of response.
[5] Condonation may be granted at the discretion of the Court. In Mankanyi v Anglo gold Ashanti Ltd[2] the Constitutional Court stated:
“The test for the grant of condonation is whether the interests of justice permit. Factors relevant to this enquiry include, but are not limited to, the extent and cause of the delay, the prejudice to the opposing litigant, the reasonableness of the explanation, the importance of the issues to be decided and the prospects of success. The enquiry entails weighing each factor against others and determining where the interests of justice ultimately lie.”
[6] Condonation is not to be had merely for the asking. The Constitutional Court in Grootboom v National Prosecution Authority and Another[3] made the following instructive remarks:
“In this Court the test for determining whether condonation should be granted or refused is the interests of justice. If it is in the interests of justice that condonation be granted, it will be granted. It is not in the interests of justice to do so, it will not be granted. The interests of justice must be determined with reference to all relevant factors. However, some of the factors may justifiably be left out of consideration in certain circumstances. For example, where the delay is unacceptably excessive and there is no explanation for the delay, there may be no need to consider the prospects of success. If the period of delay is short and there is an unsatisfactory explanation but there are reasonable prospects of success, condonation should be granted. However, despite the presence of reasonable prospects of success, condonation may be refused where the delay is excessive, the explanation is non-existent and granting condonation would prejudice the other party. As a general proposition the various factors are not individually decisive but should all be taken into account to arrive at a conclusion as to what is in the interests of justice.”
[7] The applicant’s claim in the main action is based on an unfair dismissal following a restructuring and retrenchment process. The applicant served its statement of claim by fax on 24 November 2016. Of significance is that Eon Consulting does not allege that the statement of claim was faxed to the wrong fax, but that there was no one from its side to monitor that the fax is received. After the resignation of Ms Pamela Apps on 31 October 2016 whose duty it was to monitor faxes, no one was assigned to perform the function.
[8] It is required of Eon Consulting to show good cause for the delay and account in full therefor before condonation can be granted. Mr Gibson, counsel for the applicant, has demonstrated the four gaps where Eon Consulting has not furnished any explanation justifying
reasonable cause for the delay. These are between 22 November 2016 and 06 March 2017; 13 March 2017 to 25 May 2017; April 2017 to 24 May 2017; On 26 May 2017; 12 June 2017 to 27 June 2017.
[9] Eon Consulting has not shown good cause for referring the dispute late. A period of 6 months is substantial. Mr Itzkin argued that the right to fair labour practices[4] must also be afforded to Eon Consulting. I agree. I am, however, not satisfied with the explanation furnished by Eon Consulting for the delay. In my view, it was pure negligence and short-sightedness coupled with a flagrant disregard for the Rules of this Court. The explanation does not even attempt to cover the entire period for the inordinate delay. The Labour Appeal Court in NUM v Council of Mineral Technology[5] restated the following principle:
“Without a reasonable and acceptable explanation for the delay, the prospects of success are immaterial.”
[10] I am of the view that the applicant stands to be prejudiced if condonation is granted. It would also not be in the interests of justice to condone the late filing of the statement of response. Therefore, this condonation application stands to fail.
Costs
[11] Although Eon Consulting asked for costs in the notice of motion, it did not press for costs in oral argument. Mr Itzkin did not seek any costs order notwithstanding opposition. Mr Gibson argued for the dismissal of the application with costs. There is no reason why costs should not follow the results.
[12] In the premise, the following order is made:
Order
1. The late filing of the statement of response is not condoned.
2. The respondent, Eon Consulting (Pty) Ltd, is ordered to pay the costs of this application.
___
MC Mamosebo
Acting Judge of the Labour Court of South Africa
Appearances
For the applicant: Advocate Christopher Gibson
Instructed by:
Ismail & Dahya Attorneys
For the respondent: Advocate Riaz Itzkin
Instructed by:
Cowan- Harper Attorneys
[1] Act. 66 of 1995 as amended.
[2] [2011] BLLR 527 at para 8.
[3] 2014 (2) SA 68 (CC) at paras 50 – 51.
[4] Section 23 of the Constitution of the Republic of South Africa, 108 of 1996, as amended.
[5] (1999) 2 BLLR 209 (LAC).
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.