Murray & Roberts Limited v SASOL South Africa (Pty) Ltd (2019/20801) [2020] ZAGPJHC 268 (16 April 2020)
The court held that the adjudicator's decision on Dispute 16 is binding and enforceable unless and until revised by the tribunal, in accordance with the contract. The adjudicator did not exceed his powers by reviewing the Project Manager's inaction in light of new facts established by the arbitration award. The principles established in the arbitration award regarding PMC200 and the timesheets apply to all relevant assessments, and the Project Manager was obliged to reassess earlier decisions accordingly. Sasol's delivery of a notice of dissatisfaction does not relieve it from the obligation to comply with the adjudicator's decision. The adjudicator acted within the prescribed time...
- Citation
- [2020] ZAGPJHC 268
- Parties
- Applicant: Murray & Roberts Limited; Respondent: SASOL South Africa (Pty) Ltd
- Court
- South Gauteng High Court, Johannesburg
- Jurisdiction
- South Africa
- Judgment Date
- 16 April 2020
- Case Number
- 2019/20801
- Procedural Posture
- Urgent Application / Application to Enforce Adjudicator's Decision and Counter Application to Enforce Earlier Adjudicator Decisions
- Outcome
- Application granted; counter-application dismissed with costs.
- Judges
- S E Weiner
- Legal Topics
- Construction Contracts, Adjudication Enforcement, Arbitration Award, Contractual Obligation, Mutual Trust and Cooperation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Murray & Roberts Limited
Applicant
SASOL South Africa (Pty) Ltd
Respondent
Procedural Posture
Urgent Application / Application to Enforce Adjudicator's Decision and Counter Application to Enforce Earlier Adjudicator Decisions
Legal Issues
- 1 Whether the adjudicator's decision (Dispute 16) is binding and enforceable pending arbitration.
- 2 Whether the adjudicator exceeded his powers by revisiting earlier decisions in light of the arbitration award.
- 3 Whether Sasol is obliged to comply with the adjudicator's decision despite having delivered a notice of dissatisfaction.
Ratio Decidendi
The court held that the adjudicator's decision on Dispute 16 is binding and enforceable unless and until revised by the tribunal, in accordance with the contract. The adjudicator did not exceed his powers by reviewing the Project Manager's inaction in light of new facts established by the arbitration award. The principles established in the arbitration award regarding PMC200 and the timesheets apply to all relevant assessments, and the Project Manager was obliged to reassess earlier decisions accordingly. Sasol's delivery of a notice of dissatisfaction does not relieve it from the obligation to comply with the adjudicator's decision. The adjudicator acted within the prescribed time...
Court Disposition
Application granted; counter-application dismissed with costs.
Orders
- The respondent shall give immediate effect to the adjudicator's decision delivered on 12 May 2019.
- The respondent shall make immediate payment to the applicant of the specified amounts plus VAT as set out in the judgment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment