Norland Construction (Pty) Ltd v Chris Hani District Municipality (1998/2016) [2016] ZAECGHC 110 (26 October 2016)
- Citation
- [2016] ZAECGHC 110
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Eastern Cape High Court, Grahamstown
- Panel
- N G Beshe
- Case number
- 1998/2016
More details
- Court
- Eastern Cape High Court, Grahamstown
- Panel
- N G Beshe
- Case number
- 1998/2016
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the defendant had disclosed facts which, if proved at trial, would constitute a bona fide defence to the plaintiff's claim. The defendant's allegations regarding the rejection of claim number 21 by its engineers, the alleged flaws and bias in the adjudicator's award, and the intention to institute a counter-claim to set aside the adjudication report were sufficient to satisfy the requirements for resisting summary judgment. The court held that the defendant should be granted leave to defend the action, as the issues raised warranted a full ventilation at trial rather than summary disposal.
Court disposition
Application for summary judgment dismissed; defendant granted leave to defend.
Orders
- The application for summary judgment is dismissed.
- The defendant is granted leave to defend the plaintiff's claim.
- The costs of this application are costs in the cause.
02
Material facts
Parties
Norland Construction (Pty) Ltd
Plaintiff Counsel: SH ColeChris Hani District Municipality
Defendant Counsel: A Beyleveld SCAmounts and remedies
- Claim Amount: ZAR 2,162,442.03
03
Procedural history
Posture
Summary Judgment Application / Application for Summary Judgment; Opposition; Decision on Leave to Defend
04
Questions and positions
Legal issues
- 01
Whether the defendant has established a bona fide defence to the plaintiff's claim for payment under a construction contract.
- 02
Whether the adjudicator's award in favour of the plaintiff is binding and enforceable.
- 03
Whether the defendant's intention to institute a counter-claim to set aside the adjudication report constitutes a valid defence to summary judgment.
Party arguments
- Applicant
- The plaintiff contends that it is entitled to payment of R2,162,442.03, interest, and costs, based on an adjudicator's award following a dispute over claim number 21 for electrical/mechanical works under a water purification contract. The plaintiff argues that the defendant has failed to implement the adjudicator's decision, which awarded the claim in full, and thus summary judgment should be granted.
- Respondent
- The defendant asserts a bona fide defence, arguing that its engineers rejected claim number 21 because the plaintiff was not entitled to claim twice for delays, especially after an extension had already been granted. The defendant further alleges that the adjudicator, Mr Gurry, was biased, acted irrationally and unreasonably, and that his award is fatally flawed. The defendant intends to institute a counter-claim to set aside the adjudication report as void and of no force and effect, and has served notice disputing its validity.
05
Court’s reasoning
Legal principles
- 01
Rule 32 (3) (b) of the Uniform Rules of Court
To successfully resist summary judgment, the defendant must establish by affidavit that he has a bona fide defence to the action or rely on a counter-claim. The defendant need not prove the truth of his allegations but must fully disclose the nature and grounds of his defence to satisfy the court that it is bona fide and good in law.
- 02
Maharaj v Barclays National Bank Ltd 1976 (1) SA 418 (A); Joob Joob Investments v Stocks Mavundla Zek JV 2009 (5) SA 1 (SCA)
A defendant resisting summary judgment must swear to a defence or fully disclose its nature and grounds, which will satisfy the court that the defence is bona fide and good in law.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the defendant had disclosed facts which, if proved at trial, would constitute a bona fide defence to the plaintiff's claim. The defendant's allegations regarding the rejection of claim number 21 by its engineers, the alleged flaws and bias in the adjudicator's award, and the intention to institute a counter-claim to set aside the adjudication report were sufficient to satisfy the requirements for resisting summary judgment. The court held that the defendant should be granted leave to defend the action, as the issues raised warranted a full ventilation at trial rather than summary disposal.
Obiter and limits
- The court noted that a defendant is not required to prove the truth of his allegations at the summary judgment stage, but must fully disclose the nature and grounds of his defence.
- The court observed that the existence of a counter-claim seeking to set aside an adjudication award may constitute a valid defence to summary judgment.
Court disposition
Application for summary judgment dismissed; defendant granted leave to defend.
- The application for summary judgment is dismissed.
- The defendant is granted leave to defend the plaintiff's claim.
- The costs of this application are costs in the cause.
Source and reliance status
Eastern Cape High Court, Grahamstown
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Eastern Cape High Court, Grahamstown
Judgment
IN THE HIGH
COURT OF SOUTH AFRICA
(EASTERN CAPE DIVISION, GRAHAMSTOWN)
CASE NO.: 1998/2016
In the matter between:
NORLAND CONSTRUCTION (PTY) LTD
Plaintiff
And
CHRIS
HANI DISTRICT MUNICIPALITY
Defendant
JUDGMENT
BESHE J:
[1] Plaintiff issued summons against the defendant on the 26 April 2016 for payment of the sum of R2 162 442.03, interest thereon and costs of suit.
[2] This was met by the entering of an intention to defend by the defendant.
[3] Plaintiff is now seeking summary judgment against the defendant which is in turn opposed by the defendant.
[4] The plaintiff is a company with limited capacity which is duly registered in accordance with the company laws of the Republic of South Africa as a civil engineering concern. The defendant is a local authority of Queenstown, duly established as a company C Municipality in terms of the provisions of Chapter 1 of the Local Government (Municipal Structure Act No. 117 of 1998).
[5] It is common cause that a contract relating to water purification was awarded to the plaintiff by the defendant in May of 2012. In June 2014 the plaintiff submitted the claim which is the subject of this litigation – claim number 21 in relation to electrical / mechanical works. The said claim reads thus:
“Therefore in accordance with clause 4.2, 4.9, 5.12, 6.3 and 10.1 of the General Conditions of the Contract. The contractor hereby requests an extension of time for completion of works to 15 July 2014 as reflected in its claim programme, together with preliminary and general costs amounting to R2 162 442.03.”
[6] It transpires that defendant was not amenable to paying this amount. This resulted in the dispute regarding the claim being referred to an adjudicator, one Mr Gurry. The adjudicator ruled that the plaintiff was to be awarded its claim in full as set out above.
[7] It is common cause that the defendant has not implemented the adjudicator’s award, hence this action against it.
[8] In its resistance of the summary judgment application, defendant contends that it has a bona fide defence to plaintiff’s claim. To substantiate this assertion, defendant contends that its engineers ruled against the plaintiff thereby rejecting claim number 21. This, it would appear, was on the basis that plaintiff was not entitled to claim twice for delays more especially that an extension had already been granted in respect of the completion date. Defendant further avers that Mr Gurry’s adjudication is fatally flawed and stands to be set aside on the basis that in making the award he was biased, acted irrationally and unreasonably and without any due regard to the true facts pertaining to the dispute. That there was no basis for Mr Gurry to approve / uphold the claim. This, so contends the defendant, is evidenced by an email which was erroneously or inadvertently provided together with other documents by plaintiff’s representatives to the defendant – subsequent to the adjudication. The email that is annexed to defendant’s papers as “MAM3” reads as follows:
Hi Warren
Cant advise Sam at this stage until dust has settled.
Can you please tell him that he must submit a certificate this month and include the following
Claim 21
Interest for late payment prime plus 3% which is 12% pa at moment.
50% of my fee – will have final Invoice to him by end of week
I believe that you have a claim for change in scope exceeding 15% and this claim will far exceed R1.0m
If Sam decides to go ahead the clam he should write something like the following to the client.
Further to our notice of a potential Claim and now that we know the total Contract value we confirm that we will submit a formal claim, in accordance with Clause 6.11 of GCC 2010, within 28 days from the date of this notice
Kind Regards
Neville Gurry
Bsc(Hons), MSc, PrEng, CEng, FSAICE, MICE, PrPCM
Specialist Construction Consultant
Multi-Disciplinary Mediator and Adjudicator
[9] According to the defendant, the “Warren” to whom the email is addressed is a senior member of the plaintiff whilst the “Sam” referred to in the email is a director in the plaintiff’s company – Mr Sam Hobson. The supporting affidavit in respect of the summary judgment application is deposed to by Mr Samuel Bonnin Hobson.
[10] Defendant further contends that it intends instituting a counter-claim seeking an order that the Gurry’s adjudication report be set aside as being void and of no force and effect. To this end, it is contended on behalf of the defendant that a notice has been served on the plaintiff and delivered by hand, in which they declare that defendant disputes the validity and / or correctness of Gurry’s decision. A letter to this effect is attached to defendant’s papers at “MAM6”.
[11] It is trite that in order to successfully resist an application for summary judgment, the defendant must establish by means of an affidavit that he has a bona fide defence to the action or rely on a counter-claim.[1] Whilst a defendant is not required to prove that his allegations are true, he must however swear to a defence or fully disclose the nature and grounds of his defence which will satisfy the court that he has a defence that is bona fide and good in law.[2]
[12] In my view, should the defendant succeed in proving the facts he alleges constitute a bona fide defence during the trial, such will constitute a defence to plaintiff’s claim. In my view, this is an appropriate case in which the defendant should be granted leave to defend the action.
[13] Accordingly the application for summary judgment is dismissed.
Defendant is granted leave to defend plaintiff’s claim.
The costs of this application are costs in the cause.
___
N
G BESHE
JUDGE
OF THE HIGH COURT
APPEARANCES
For the Plaintiff : Adv: SH Cole
Instructed by :
JOUBERT
GALPIN SEARLE
173 Cape Road
Mill Park
Docex 12
PORT
ELIZABETH
Ref.: M C Botha/ds/ NOR61/0002
Tel.: 041 – 396 9235
c/o
HUXTABLE
ATTORNEYS
22 Somerset Street
GRAHAMSTOWN
Ref.: Mr Huxtable
Tel.: 046 – 622 2692
For the Respondent : Adv: A Beyleveld SC
Instructed by :
McWILLIAMS & ELLIOTT INC.
152 Cape Road
Ref.: T Radloff/W73160
Tel.: 041 – 582 1250
WHITESIDES
ATTORNEYS
53 African Street
Ref.: Mr Nunn
Tel.: 046 – 622 7117
Date Heard : 7 June 2016
Date Reserved : 7 June 2016
Date Delivered : 26 October 2016
[1] Rule 32 (3) (b) of the Uniform Rules of Court.
[2] See Maharaj v Barclays National Bank Ltd 1976 (1) SA 418 A, Joob Joob Investments v Stocks Mavundla Zek JV2009 (5) SA 1 (SCA) at 12.
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.