Norland Construction (Pty) Ltd v O R Tambo District Municipality (37/2015) [2017] ZAECGHC 87 (4 July 2017)
The court found that the delay of 55 days was entirely beyond the plaintiff's control, as the employment system for the local workforce was managed by the community-based Project Steering Committee and the Municipality, leaving the plaintiff powerless to resolve the unrest. The adverse physical conditions encountered during construction were not reasonably foreseeable by an experienced contractor, as neither the tender documents nor the drawings indicated any warning signs, and even the Engineer had not anticipated the problems. The plaintiff complied with the contractual claims procedure by timely notification and record-keeping, submitting claims as soon as practicable. The adjudicator...
- Citation
- [2017] ZAECGHC 87
- Parties
- Plaintiff: Norland Construction (Pty) Ltd; Defendant: O R Tambo District Municipality
- Court
- Eastern Cape High Court, Grahamstown
- Jurisdiction
- South Africa
- Judgment Date
- 4 July 2017
- Case Number
- 37/2015
- Procedural Posture
- Civil Trial / Judgment After Trial
- Outcome
- Plaintiff's claims for extensions of time and payment of additional costs are upheld.
- Judges
- C Plasket
- Legal Topics
- Construction Contracts, Extension of Time, Adverse Physical Conditions, Contractual Compliance, Time Barring, Claims Procedure
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Norland Construction (Pty) Ltd
Plaintiff
O R Tambo District Municipality
Defendant
Procedural Posture
Civil Trial / Judgment After Trial
Legal Issues
- 1 Whether the delay of 55 days due to labour unrest was entirely beyond the plaintiff's control.
- 2 Whether the adverse physical conditions encountered were reasonably foreseeable by an experienced contractor at the time of tendering.
- 3 Whether the plaintiff complied with the contractual procedure for lodging claims for extensions of time and additional costs.
Ratio Decidendi
The court found that the delay of 55 days was entirely beyond the plaintiff's control, as the employment system for the local workforce was managed by the community-based Project Steering Committee and the Municipality, leaving the plaintiff powerless to resolve the unrest. The adverse physical conditions encountered during construction were not reasonably foreseeable by an experienced contractor, as neither the tender documents nor the drawings indicated any warning signs, and even the Engineer had not anticipated the problems. The plaintiff complied with the contractual claims procedure by timely notification and record-keeping, submitting claims as soon as practicable. The adjudicator...
Court Disposition
Plaintiff's claims for extensions of time and payment of additional costs are upheld.
Orders
- It is declared that the plaintiff is entitled to extensions of time of 55 and 187 days in relation to claims 1 and 2.
- The defendant is directed to pay to the plaintiff the amount of R1 054 500.52 plus VAT in respect of claim 1, with interest at the prescribed rate from date of demand to date of payment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment