Orkin v Goldleaf Investment (Pty) Ltd (22321/2018) [2023] ZAGPJHC 356 (21 April 2023)
The court found that the defendant was contractually obliged, including by tacit term, to provide a fully serviced site with municipal and electrical infrastructure. The defendant failed to ensure the timely supply of electricity, which delayed the plaintiff's occupation and completion of her home. The defendant's attempt to shift responsibility to Eskom was rejected, as it did not take reasonable steps to facilitate the connection. Damages flowing from the breach were limited to those proven, namely rental, project manager costs, gardener, and legal costs, while other claimed damages were not sufficiently substantiated. The counterclaim was dismissed due to lack of locus standi, as the...
- Citation
- [2023] ZAGPJHC 356
- Parties
- Plaintiff: Nadine Orkin; Defendant: Goldleaf Investments (Pty) Ltd
- Court
- South Gauteng High Court, Johannesburg
- Jurisdiction
- South Africa
- Judgment Date
- 21 April 2023
- Case Number
- 22321/2018
- Procedural Posture
- Civil Trial / Final Judgment
- Outcome
- Plaintiff's claim for damages partially succeeds; defendant's counterclaim is dismissed.
- Judges
- MIA
- Legal Topics
- Implied Terms, Breach of Contract, Damages Assessment, Locus Standi, Cession of Rights, Municipal Services Supply
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Nadine Orkin
Plaintiff
Goldleaf Investments (Pty) Ltd
Defendant
Procedural Posture
Civil Trial / Final Judgment
Legal Issues
- 1 Whether the defendant was required to supply the necessary infrastructure for a fully serviced site regarding municipal and electrical services.
- 2 Whether the defendant breached the sale agreement by failing to provide or ensure the supply of electricity, causing delay in completion of building works.
- 3 Whether the plaintiff proved causation and quantum of damages flowing from the breach.
Ratio Decidendi
The court found that the defendant was contractually obliged, including by tacit term, to provide a fully serviced site with municipal and electrical infrastructure. The defendant failed to ensure the timely supply of electricity, which delayed the plaintiff's occupation and completion of her home. The defendant's attempt to shift responsibility to Eskom was rejected, as it did not take reasonable steps to facilitate the connection. Damages flowing from the breach were limited to those proven, namely rental, project manager costs, gardener, and legal costs, while other claimed damages were not sufficiently substantiated. The counterclaim was dismissed due to lack of locus standi, as the...
Court Disposition
Plaintiff's claim for damages partially succeeds; defendant's counterclaim is dismissed.
Orders
- The defendant is to pay the plaintiff the sum of R486,550.36.
- Interest on the aforesaid sum at the prescribed rate from 1 March 2018 to date of final payment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment