Pavebuild CC v F.J. Joubert & Sons CC (1605/2017) [2019] ZAMPMBHC 16 (9 April 2019)
The court found that the plaintiff constructed the wall at Makro Nelspruit in accordance with the design and specifications provided by the defendant's engineer, Mr Farraris. The construction was subject to regular inspection by the defendant's personnel and engineers, with no complaints or instructions to rectify any work during the process. The wall was signed off by the designer, and all required compaction and material tests met the necessary standards. The defendant's counterclaim for damages was unsupported by credible evidence, as no photographs or expert reports substantiated the alleged collapse or defective workmanship. The court held that subsequent damage to the wall was...
- Citation
- [2019] ZAMPMBHC 16
- Parties
- Plaintiff: Pavebuild CC; Defendant: F.J. Joubert & Sons CC
- Court
- Mbombela High Court, Mpumalanga
- Jurisdiction
- South Africa
- Judgment Date
- 9 April 2019
- Case Number
- 1605/2017
- Procedural Posture
- Civil Trial / Final Judgment
- Outcome
- Judgment in favour of the plaintiff. Defendant's counterclaim dismissed.
- Judges
- Jansen van Rensburg
- Legal Topics
- Construction Contracts, Breach of Contract, Quantification of Damages, Expert Evidence, Counterclaim, Service Rendered and Payment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Pavebuild CC
Plaintiff
F.J. Joubert & Sons CC
Defendant
Procedural Posture
Civil Trial / Final Judgment
Legal Issues
- 1 Whether the defendant is liable to pay the plaintiff for construction work performed, including the Makro wall.
- 2 Whether the defendant's counterclaim for damages due to alleged poor workmanship and collapse of the wall is valid.
- 3 Whether the plaintiff performed the work in accordance with the contract specifications and professional standards.
Ratio Decidendi
The court found that the plaintiff constructed the wall at Makro Nelspruit in accordance with the design and specifications provided by the defendant's engineer, Mr Farraris. The construction was subject to regular inspection by the defendant's personnel and engineers, with no complaints or instructions to rectify any work during the process. The wall was signed off by the designer, and all required compaction and material tests met the necessary standards. The defendant's counterclaim for damages was unsupported by credible evidence, as no photographs or expert reports substantiated the alleged collapse or defective workmanship. The court held that subsequent damage to the wall was...
Court Disposition
Judgment in favour of the plaintiff. Defendant's counterclaim dismissed.
Orders
- The defendant is ordered to pay the plaintiff the following amounts, including VAT: Claim 1: R160,528.00; Claim 2: Rings around trees: R67,200.00; Civil works: R24,460.00; Curving: R22,400.00; Side stones: R9,028.00; Civil works: R95,040.00; Construction of the Makro wall: R969,606.17; Claim 3: R35,470.27; Claim 4:...
- Interest at 15.5% per annum on the total amount due from date of service of summons.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment