Pro-Care Contracting (Pty) Ltd v ISA & Partners (Pty) Ltd (285/2019) [2021] ZAFSHC 17 (28 January 2021)
- Citation
- [2021] ZAFSHC 17
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Free State High Court, Bloemfontein
- Panel
- C Reinders
- Case number
- 285/2019
More details
- Court
- Free State High Court, Bloemfontein
- Panel
- C Reinders
- Case number
- 285/2019
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the respondent's version regarding the validity and process of issuing payment certificates was supported by the formal contract between the parties. The disputed certificates did not bear the respondent's letterhead or signature and were not issued in accordance with the agreed process. The applicant's argument that previous certificates were paid without signature did not establish the validity of the disputed certificates. Applying the Plascon-Evans rule, the court could not reject the respondent's version as far-fetched or palpably false. Consequently, the applicant failed to prove entitlement to judgment on the papers, and the application was refused.
Court disposition
Application refused with costs.
Orders
- The application is refused with costs.
02
Material facts
Parties
Pro-Care Contracting (Pty) Ltd
Applicant Counsel: Adv. R. van der MerweISA & Partners (Pty) Ltd
Respondent Counsel: Adv. W.A. van AswegenAmounts and remedies
- Certificate No. 10 Amount: ZAR 1,363,843.09
- Certificate No. 11 Amount: ZAR 791,755.97
- Certificate No. 12 Amount: ZAR 816,909.76
- Interest Rate Per Annum: ZAR 10.25
03
Procedural history
Posture
Civil Application / Final Judgment
04
Questions and positions
Legal issues
- 01
Whether the payment certificates relied upon by the applicant are valid and enforceable under the contract.
- 02
Whether the respondent's version regarding the process and validity of payment certificates can be rejected on the papers.
- 03
Whether the applicant is entitled to judgment in money based on the disputed certificates.
Party arguments
- Applicant
- The applicant contends that the parties entered into a contract for construction works, governed by the General Conditions of Contract for Construction Works (GCC) and related documents. The applicant performed the work and submitted payment certificates for additional work, which the respondent refuses to pay. The applicant argues that previous certificates were paid without the respondent's signature or letterhead, and that the format used for the disputed certificates was agreed upon by the parties.
- Respondent
- The respondent asserts that valid payment certificates must bear the respondent's letterhead and the managing director's original signature, following a prescribed process of evaluation and deduction. The respondent denies that the disputed certificates were approved or valid, noting that they do not comply with the agreed process and that their dates of issue and valuation are inconsistent with prior valid certificates. The respondent maintains that no contractual liability arises from these certificates.
05
Court’s reasoning
Legal principles
- 01
Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd [1984] ZASCA 51; 1984 (3) SA 623 (A) at 634E–635C
In motion proceedings seeking final relief, factual disputes must be resolved by accepting the respondent's version unless it is far-fetched or palpably false.
- 02
Wightman t/a JW Construction v Headfour (Pty) Ltd and Another [2008] ZASCA 6; 2008 (3) SA 371 (SCA) para [12]
An applicant who seeks final relief on motion must accept the version set up by the respondent unless the respondent's allegations are not such as to raise a real, genuine or bona fide dispute of fact.
- 03
General Conditions of Contract for Construction Works (2nd Edition, 2010), Clause 6.10.1
The contract prescribes that payment certificates must be signed and issued by the respondent to be valid and enforceable.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the respondent's version regarding the validity and process of issuing payment certificates was supported by the formal contract between the parties. The disputed certificates did not bear the respondent's letterhead or signature and were not issued in accordance with the agreed process. The applicant's argument that previous certificates were paid without signature did not establish the validity of the disputed certificates. Applying the Plascon-Evans rule, the court could not reject the respondent's version as far-fetched or palpably false. Consequently, the applicant failed to prove entitlement to judgment on the papers, and the application was refused.
Obiter and limits
- The court emphasized that the refusal of the application does not amount to a dismissal of the applicant's claims with res judicata effect.
- The court noted that the dispute of fact could not be resolved on the papers and that the applicant may pursue its claims in other proceedings if appropriate.
Court disposition
Application refused with costs.
- The application is refused with costs.
Source and reliance status
Free State High Court, Bloemfontein
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Free State High Court, Bloemfontein
Judgment
IN THE HIGH COURT OF SOUTH AFRICA,
FREE
STATE DIVISION BLOEMFONTEIN
Case number: 285/2019
In the matter between:
PRO-CARE CONTRACTING (PTY) LTD
[Registration No. 2010/006882/07]
Applicant
And
ISA & PARTNERS (PTY) LTD
[Registration No. 2004/034689/07]
Respondent
JUDGMENT BY:
RENDERS,
J
DELIVERED ON:
28 JANUARY 2021
[1] The applicant in its notice of motion prays for relief in the following terms:
"1. The Respondent is ordered to pay the Applicant the amount set out in prayers 1.1 — 1.3 infra plus interest on the amounts set out in prayers 1.1 -1.3 infra at the rate of 10.25% per annum, calculated from the following dates until date of final payment:
1.1 On Certificate No. 10 in the amount of R 1,363,843.09 from 22 October 2018 until date of final payment;
1.2 On Certificate No.11 in the amount of R 791,755.97 from 27 October 2018 until date of final payment;
1.3 On Certificate No.12 in the amount of R 816,909.76 from 22 October 2018 until date of final payment;
2. The Respondent is ordered to pay the costs of the application."
[2] On 18 June 2020 leave was granted to the applicant to file the duly signed and commissioned confirmatory affidavits of two witnesses as annexures to the applicant's replying affidavit.
[3] Mr Jacobus Greeff, a director of the applicant, avers that the parties entered into an agreement to see to the execution of works after the Setsoto Municipality ("the municipality") awarded a public tender to the respondent company Isa and Partners (Pty)Ltd for the rendering of services in respect of the design and construction for the upgrading and re-alignment of its Van Solen Sewage Pipeline in the Ficksburg/Meqheleng area. The physical construction work on the pipeline was subcontracted by the respondent to the applicant, Pro-Care Contracting (Pty) Ltd. The deponent avers that the agreement between the parties is embodied by the General Conditions of Contract for Construction Works (2nd Edition,2010) ("the GCC") and the contract data which consisted of a letter of the appointment (dated 4 August 2017) and a bill of quantities (including the pricing data). The applicant performed in terms of the said agreement. Nine payment certificates were submitted up to August 2018 which were all paid. The parties agreed that applicant would perform further works which did not form part of the initial bill of quantities. Applicant annexed three electronic mails which consisted of further instructions and a further bill of quantities. In terms thereof the applicant submitted three further payment certificates being the certificates the applicant now seeks to enforce and which respondent refuses to pay.
[4] The respondent through its managing director Mr Christopher Nganga Kimaru avers that an official or "valid" payment certificate issued by the respondent contains the respondent's letterhead and bears his original signature. Such a certificate is only issued after the respondent evaluated the applicant's statement and verified that all amounts claimed and all previous payments and penalties are deducted. A valid certificate is then issued to the municipality and the applicant is supplied with an e-mailed copy thereof. This document is then used by the applicant to generate what is described as a concept payment certificate. The applicant in turn submits this concept certificate to the respondent together with its monthly statement as contemplated by the contract. Respondent would then evaluate the statement, the calculation sheet as signed by both parties and the concept certificate and confirm that the amounts claimed are correct, then make the necessary deductions and give validity to the concept certificate by putting it on the respondent's official letterhead whereafter the deponent signs it. He then denies
that any of the certificates relied upon were approved by the respondent nor clothed with any validity as none of the certificates
were issued having followed the prescribed process. The deponent denies that any of the certificates bears the respondent's letterhead
or his signature. In amplification of his denial he avers that all three certificates bear the same date of issue, namely 17 May 2018. In fact, their purported date of issue predates the last valid certificate being Certificate No 8 (annexed to his affidavit) which was issued in June 2018, and the date of valuation on each of the certificates predates the date of valuation of the said Certificate No 8 which was likewise in June 2018. He concludes that the disputed certificates therefore do not give rise to any contractual liability on the part of the respondent.
[5] In its replying affidavit the applicant insisted that the payment certificates were approved payment certificates and conceded that the payment certificates did not bear respondent's letterhead nor was signed by the managing director of respondent. It is averred that the format constituted the agreed format for payment certificates and that respondent made payments on previous certificates which did not bear the signature of the managing director nor the letterhead of the respondent.
[6] To adjudicate the application settled law prescribes the process I am to follow. The applicant approached court by way of motion proceedings and seeks final relief in the form of judgment in money against respondent. The factual disputes are therefore to be adjudicated on the principles laid down in Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd [1984] ZASCA 51; 1984 (3) SA 623 (A) at 634E — 635C). In Wightman t/a JW Construction v Headfour (Pty) Ltd and Another [2008] ZASCA 6; 2008 (3) SA 371 (SCA) at paragraphs [12] it was stated:
"Recognising that the truth almost always lies beyond mere linguistic determination the courts have said that an applicant who seeks final relief on motion, must in the event of conflict, accept the version set up by his opponent unless the latter's allegations are, in the opinion of the court, not such as to raise a real, genuine or bona fide dispute of fact or are so far-fetched or clearly untenable that the court is justified in rejecting them merely on the papers...”
[7] In applying the test that I have to, it seems to me that the respondent disputes the very basis of the applicant's cause of action, namely the validity of the certificates. Respondent denies having confirmed or signed the certificates. If I cannot reject the respondent's version as being far-fetched or palpably false, the application cannot succeed. The written memorandum entered into between the parties prescribes that applicant shall deliver to the engineer a monthly statement for all amounts he considers to be due to him and prescribes that the engineer shall, by signed payment certificates issued to the employer and the contractor, certify the amounts he considers to be due to the contractor. Clause 6.10.1 of the GCC prescribes that the amount due to the applicant are to be certified by way of a signed payment certificate issued by the respondent. It would appear therefore that the version of the respondent is supported by the formal agreement between the parties. I can see no reason how I can reject the respondent's version on the papers to be far-fetched or palpably false. The allegation by the applicant that the respondent paid other payment certificates without having signed them in my view cannot assist the applicant to obtain judgment where the certificates in casu are in dispute. Even if it should have carried some weight, it carries insufficient thrust to reject the respondent's version as far as the contested certificates are concerned. Differently said, even assuming that respondent might
have paid other unsigned certificates, it does not proof the validity of the present disputed certificates which on face value do not comply with the agreed terms between the parties nor can respondent's version be rejected simply on that basis.
[8] Having reached the conclusion as aforementioned it is not necessary to deal with any of the other defences raised by the respondent, for example that it was agreed that applicant would only be entitled to payment once respondent has received payment from the municipality, which had not occurred yet at the time of the filing of the papers. I wish to emphasize that the conclusion which I have come to must not be considered as a dismissal of the applicant's claims, having the
effect of res judicata. It must be stressed that I am simply of the view that the relief cannot be granted as there is a dispute of fact which I cannot resolve on the papers applying the mentioned legal principles.
[9] I therefore make the following order:
The application is refused with costs.
C. REINDERS J
For the applicant:
Adv. R. van der Merwe
Instructed by: Badenhorst Attorneys
BLOEMFONTEIN
For the defendant: Adv. W.A. van Aswegen
Instructed by:
Phatshoane Henney Inc
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.