Public Investment Corporation SOC Ltd and Another v Trencon Construction (Pty) Ltd and Another (49930/20) [2022] ZAGPPHC 226 (4 April 2022)

Public Investment Corporation SOC Ltd and Another v Trencon Construction (Pty) Ltd and Another (49930/20) [2022] ZAGPPHC 226 (4 April 2022)

The court found that Trencon Construction (Pty) Ltd failed to provide a full and proper explanation for the delay in filing its application for leave to cross-appeal. The excuses provided did not account for the entire period of delay and were insufficient to justify condonation. The principle of finality required...

Source-derived case information.

Citation
[2022] ZAGPPHC 226
Parties
Applicant: Public Investment Corporation SOC Ltd; Applicant: Government Employees Pension Fund; Respondent: Trencon Construction (Pty) Ltd; Respondent: GVK-Siya Building Contractors (Pty) Ltd
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
49930/20
Procedural Posture
Leave to Appeal / Application for Leave to Appeal and Cross Appeal Following Main Judgment and Amendment of Order.
Outcome
Leave to appeal to the Supreme Court of Appeal is granted to the GEPF and PIC. Trencon's application for condonation for the late filing of its application for leave to cross-appeal is refused with costs.
Judges
Neukircher
Legal Topics
Leave to Appeal, Condonation, Rule 49, Rule 42, Prospects of Success
Civil Procedure Leave to Appeal Condonation Rule 49 Rule 42 Prospects of Success

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Public Investment Corporation SOC Ltd

Applicant

Government Employees Pension Fund

Applicant

Trencon Construction (Pty) Ltd

Respondent

GVK-Siya Building Contractors (Pty) Ltd

Respondent

Procedural Posture

Leave to Appeal / Application for Leave to Appeal and Cross Appeal Following Main Judgment and Amendment of Order.

  1. 1 Whether Trencon Construction (Pty) Ltd provided a reasonable and full explanation for the late filing of its application for leave to cross-appeal.
  2. 2 Whether condonation for the late filing of the cross-appeal should be granted.
  3. 3 Whether the GEPF and PIC have reasonable prospects of success in their application for leave to appeal.

Ratio Decidendi

The court found that Trencon Construction (Pty) Ltd failed to provide a full and proper explanation for the delay in filing its application for leave to cross-appeal. The excuses provided did not account for the entire period of delay and were insufficient to justify condonation. The principle of finality required that condonation not be granted in the absence of a reasonable explanation. In contrast, the GEPF and PIC's application for leave to appeal was filed timeously and demonstrated reasonable prospects of success, particularly regarding the finding that the GEPF is an organ of state, which has broader implications. Accordingly, leave to appeal was granted to the GEPF and PIC, while...

Court Disposition

Leave to appeal to the Supreme Court of Appeal is granted to the GEPF and PIC. Trencon's application for condonation for the late filing of its application for leave to cross-appeal is refused with costs.

Orders

  • Leave to appeal to the Supreme Court of Appeal is granted in the application for leave to appeal filed by the GEPF and PIC dated 13 December 2021. Costs are costs in the appeal.
  • The application for condonation for the late filing of the application for leave to cross-appeal, filed by Trencon on 2 February 2022, is refused with costs.