Radon Projects (Pty) Ltd v N V Properties (Pty) Ltd and Another (528/12) [2013] ZASCA 83; [2013] 3 All SA 615 (SCA); 2013 (6) SA 345 (SCA) (31 May 2013)
The Supreme Court of Appeal held that the contractor's revised claims, submitted after practical completion and based on new information, constituted disputes arising out of the agreement and were properly referable to arbitration. The court rejected the employer's argument that the arbitrator lacked jurisdiction because the initial claims had been finally disposed of during construction, finding that the current claims were distinct and not precluded by earlier decisions. The court further clarified that whether a dispute is resolved by adjudication or arbitration depends on when it is submitted for resolution, not when it arises. The arbitrator is empowered to consider the claims, and...
- Citation
- [2013] ZASCA 83
- Parties
- Appellant: Radon Projects (Pty) Ltd; Respondent: N V Properties (Pty) Ltd; Respondent: Gary Stephen Myburgh
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 31 May 2013
- Case Number
- 528/12
- Procedural Posture
- Civil Appeal / Appeal From Eastern Cape High Court, Grahamstown
- Outcome
- Appeal upheld; application dismissed with costs, including costs of two counsel where employed.
- Judges
- Nugent, Leach, Pillay, Erasmus, Saldulker
- Legal Topics
- Arbitration Agreement, Jurisdiction of Arbitrator, Construction Contracts, Principal Building Agreement, Dispute Resolution Procedure
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Radon Projects (Pty) Ltd
Appellant
N V Properties (Pty) Ltd
Respondent
Gary Stephen Myburgh
Respondent
Procedural Posture
Civil Appeal / Appeal From Eastern Cape High Court, Grahamstown
Legal Issues
- 1 Whether the arbitrator had jurisdiction to consider the contractor's revised claims submitted after practical completion.
- 2 Whether disputes arising before practical completion must be resolved by adjudication rather than arbitration.
- 3 Whether the principal agent's decisions on initial claims were final and binding, precluding arbitration.
Ratio Decidendi
The Supreme Court of Appeal held that the contractor's revised claims, submitted after practical completion and based on new information, constituted disputes arising out of the agreement and were properly referable to arbitration. The court rejected the employer's argument that the arbitrator lacked jurisdiction because the initial claims had been finally disposed of during construction, finding that the current claims were distinct and not precluded by earlier decisions. The court further clarified that whether a dispute is resolved by adjudication or arbitration depends on when it is submitted for resolution, not when it arises. The arbitrator is empowered to consider the claims, and...
Court Disposition
Appeal upheld; application dismissed with costs, including costs of two counsel where employed.
Orders
- The appeal is upheld with costs.
- The order of the court below is set aside and substituted with an order dismissing the application with costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment