The court found that the plaintiff's claim is based on an undisputed written contract, and clause 45 of the agreement expressly obliges the defendant to pay amounts claimed, even if disputed, with the right to seek repayment only after payment. The defendant did not challenge the enforceability or applicability of...

Source-derived case information.

Citation
[2024] ZAGPJHC 531
Parties
Plaintiff: Rangel Logistics (Pty) Ltd; Defendant: Unhu Aluminum (Pty) Ltd
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
2022/22946
Procedural Posture
Summary Judgment Application / Judgment After Hearing of Summary Judgment Application
Outcome
Summary judgment granted in favour of the plaintiff. In the alternative, security may be provided by the defendant. Costs awarded to the plaintiff.
Judges
Lucas J van Tonder
Legal Topics
Summary Judgment, Contractual Enforcement, Pay Now Fight Later Clause, Delay in Proceedings
Civil Procedure Commercial and Corporate Summary Judgment Contractual Enforcement Pay Now Fight Later Clause Delay in Proceedings

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Rangel Logistics (Pty) Ltd

Plaintiff

Unhu Aluminum (Pty) Ltd

Defendant

Procedural Posture

Summary Judgment Application / Judgment After Hearing of Summary Judgment Application

  1. 1 Whether the plaintiff is entitled to summary judgment for payment under an undisputed written contract.
  2. 2 Whether clause 45 of the agreement, a 'pay now fight later' provision, is enforceable.
  3. 3 Whether the defendant's procedural conduct and defences justify refusal of summary judgment.

Ratio Decidendi

The court found that the plaintiff's claim is based on an undisputed written contract, and clause 45 of the agreement expressly obliges the defendant to pay amounts claimed, even if disputed, with the right to seek repayment only after payment. The defendant did not challenge the enforceability or applicability of clause 45, nor did it raise any bona fide defence to the claim. The procedural delays caused by the defendant were unjustified and did not constitute grounds to refuse summary judgment. The court held that the 'pay now fight later' clause is enforceable and that summary judgment is warranted. In the alternative, the defendant may provide security for the claimed amount pending...

Court Disposition

Summary judgment granted in favour of the plaintiff. In the alternative, security may be provided by the defendant. Costs awarded to the plaintiff.

Orders

  • The defendant is ordered to pay the plaintiff the sum of R655,016.29.
  • Interest on the aforesaid amount at the rate of 9% per annum from date of summons until date of payment.