Raubex Construction (Pty) Limited v Passenger Rail Agency Of South Africa (SOC) and Another (2023/117558) [2023] ZAGPJHC 703 (14 December 2023)

Raubex Construction (Pty) Limited v Passenger Rail Agency Of South Africa (SOC) and Another (2023/117558) [2023] ZAGPJHC 703 (14 December 2023)

The court found that the applicant failed to explain the delay in launching the urgent application, despite being aware of the tender award as early as 6 October 2023. By the time the application was heard, the works under the tender had already commenced, and a significant portion of the contract period had...

Source-derived case information.

Citation
[2023] ZAGPJHC 703
Parties
Applicant: Raubex Construction (Pty) Limited; Respondent: Passenger Rail Agency Of South Africa (SOC); Respondent: Re A Letamisa Trading & Projects CC
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
2023/117558
Procedural Posture
Urgent Application / Interim Interdict Application on Urgent Roll
Outcome
Application struck from the urgent roll with costs.
Judges
N Redman
Legal Topics
Public Procurement, Interim Interdict, Urgency, Delay in Instituting Proceedings
Administrative Law Civil Procedure Public Procurement Interim Interdict Urgency Delay in Instituting Proceedings

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Raubex Construction (Pty) Limited

Applicant

Passenger Rail Agency Of South Africa (SOC)

Respondent

Re A Letamisa Trading & Projects CC

Respondent

Procedural Posture

Urgent Application / Interim Interdict Application on Urgent Roll

  1. 1 Whether the applicant established sufficient urgency to justify hearing the matter on the urgent roll.
  2. 2 Whether the applicant is entitled to interim interdictory relief preventing implementation of the tender.
  3. 3 Whether the delay in bringing the application renders the relief sought nugatory.

Ratio Decidendi

The court found that the applicant failed to explain the delay in launching the urgent application, despite being aware of the tender award as early as 6 October 2023. By the time the application was heard, the works under the tender had already commenced, and a significant portion of the contract period had elapsed. The delay rendered the relief sought nugatory, and the applicant did not establish sufficient urgency to justify hearing the matter on the urgent roll. Consequently, the application was struck from the roll with costs.

Court Disposition

Application struck from the urgent roll with costs.

Orders

  • The application is struck from the urgent roll.
  • The applicant is ordered to pay the costs.