Reder Construction (Pty) Ltd v Minister of Public Works and Infrastructure of the Republic of South Africa and Another (4215/2022) [2024] ZAFSHC 300 (17 September 2024)

Reder Construction (Pty) Ltd v Minister of Public Works and Infrastructure of the Republic of South Africa and Another (4215/2022) [2024] ZAFSHC 300 (17 September 2024)

The court found that the declaration of the National State of Disaster and the implementation of the lockdown did not create a supervening impossibility for the First Defendant to effect payment as claimed by the Plaintiff. The lockdown regulations caused hindrance and delay but did not render performance...

Source-derived case information.

Citation
[2024] ZAFSHC 300
Parties
Plaintiff: Reder Construction (Pty) Ltd; Defendant: Minister of Public Works and Infrastructure of the Republic of South Africa; Defendant: Trustees of the Time Being of the Independent Development Trust
Court
Free State High Court, Bloemfontein
Jurisdiction
South Africa
Case Number
4215/2022
Procedural Posture
Civil Trial / Final Judgment After Heads of Argument; No Oral Evidence Led
Outcome
Judgment granted in favour of the Plaintiff. The First Defendant is liable for payment of the amounts claimed in claim 1 and claims 2 to 9, with interest and costs as specified.
Judges
Manye, AJ
Legal Topics
Supervening Impossibility, Construction Contracts, Covid19 Regulations, Extension of Time, Payment of Additional Costs
Commercial and Corporate Civil Procedure Supervening Impossibility Construction Contracts Covid19 Regulations Extension of Time Payment of Additional Costs

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 11
Sign in to unlock

Parties

Reder Construction (Pty) Ltd

Plaintiff

Minister of Public Works and Infrastructure of the Republic of South Africa

Defendant

Trustees of the Time Being of the Independent Development Trust

Defendant

Procedural Posture

Civil Trial / Final Judgment After Heads of Argument; No Oral Evidence Led

  1. 1 Whether the declaration of the National State of Disaster and the implementation of the nationwide lockdown created a supervening impossibility for the First Defendant to make payment of additional costs and time-related general items claimed by the Plaintiff.
  2. 2 Whether the First Defendant is liable for payment of the amounts claimed in terms of claim 1 pursuant to the extension of the date of practical completion granted to the Plaintiff.

Ratio Decidendi

The court found that the declaration of the National State of Disaster and the implementation of the lockdown did not create a supervening impossibility for the First Defendant to effect payment as claimed by the Plaintiff. The lockdown regulations caused hindrance and delay but did not render performance permanently impossible. Since neither party invoked the termination provisions of the contract, and the contract continued, the First Defendant remained liable for payment of the additional costs and time-related general items resulting from the extension of the date for practical completion. The Plaintiff's entitlement to payment was confirmed, and the Defendant's reliance on...

Court Disposition

Judgment granted in favour of the Plaintiff. The First Defendant is liable for payment of the amounts claimed in claim 1 and claims 2 to 9, with interest and costs as specified.

Orders

  • The First Defendant is liable to pay the Plaintiff an amount of R975,714.42 including VAT in respect of claim 1.
  • Payment of interest on R975,714.42 at specified rates for defined periods until date of payment.