Regenesys Management (Pty) Ltd v Mantshule N.O and Others (JR316/21) [2022] ZALCJHB 358 (22 November 2022)

Regenesys Management (Pty) Ltd v Mantshule N.O and Others (JR316/21) [2022] ZALCJHB 358 (22 November 2022)

The applicant failed to provide a satisfactory or detailed explanation for the extreme delay in launching the review applications, which were 381 and 318 days late respectively. The court found that the prejudice caused by the delay favoured the fourth respondent, whose employment had terminated years prior. The...

Source-derived case information.

Citation
[2022] ZALCJHB 358
Parties
Applicant: Regenesys Management (Pty) Ltd; Respondent: Nthabiseng Loretta Mantshule N.O.; Respondent: Namasile Kheswa N.O.; Respondent: Commission for Conciliation, Mediation and Arbitration; Respondent: Jean Dovey
Court
Labour Court Johannesburg
Jurisdiction
South Africa
Case Number
JR316/21
Procedural Posture
Review Application / Condonation Application for Late Review of Jurisdictional Ruling and Arbitration Award
Outcome
Condonation refused; review applications dismissed; no order as to costs.
Judges
S Swartz
Legal Topics
Condonation, Review Application Delay, Jurisdictional Ruling, Arbitration Award, Reasonable Time Requirement
Labour Law Civil Procedure Condonation Review Application Delay Jurisdictional Ruling Arbitration Award Reasonable Time Requirement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Regenesys Management (Pty) Ltd

Applicant

Nthabiseng Loretta Mantshule N.O.

Respondent

Namasile Kheswa N.O.

Respondent

Commission for Conciliation, Mediation and Arbitration

Respondent

Jean Dovey

Respondent

Procedural Posture

Review Application / Condonation Application for Late Review of Jurisdictional Ruling and Arbitration Award

  1. 1 Whether condonation should be granted for the late filing of review applications against the jurisdictional ruling and arbitration award.
  2. 2 Whether the delay in launching the review applications was adequately explained and justified.
  3. 3 Whether the prospects of success are material where the delay is egregious and unexplained.

Ratio Decidendi

The applicant failed to provide a satisfactory or detailed explanation for the extreme delay in launching the review applications, which were 381 and 318 days late respectively. The court found that the prejudice caused by the delay favoured the fourth respondent, whose employment had terminated years prior. The principles governing condonation in labour law require strict scrutiny, and without a compelling explanation for the delay, prospects of success are immaterial. The delay was found to be excessive and unreasonable, even under section 158(1)(g) which does not prescribe a specific time limit. The court exercised its discretion to refuse condonation and dismissed the review...

Court Disposition

Condonation refused; review applications dismissed; no order as to costs.

Orders

  • The application for condonation is dismissed.
  • The review applications are accordingly dismissed.