RSC Avelo (Pty) Ltd v Trencon Construction (Pty) Ltd and Another (2022/057553) [2025] ZAGPJHC 7 (12 January 2025)

RSC Avelo (Pty) Ltd v Trencon Construction (Pty) Ltd and Another (2022/057553) [2025] ZAGPJHC 7 (12 January 2025)

The court found that the arbitrator had determined the issue of interest and intended to award interest on the late certification of escalation amounts. The award must be interpreted as requiring interest to be calculated in terms of the subcontract, specifically at a rate of 160% of the repo rate, compounded...

Source-derived case information.

Citation
[2025] ZAGPJHC 7
Parties
Applicant: RSC Avelo (Pty) Ltd; Respondent: Trencon Construction (Pty) Ltd; Respondent: Dirk van Zyl N.O.
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Judgment Date
12 January 2025
Case Number
2022/057553
Procedural Posture
Urgent Application / Application to Make Arbitration Award an Order of Court; Declaratory Relief Sought Regarding Interpretation of Interest Award
Outcome
Application granted. The arbitration award is made an order of court. Declaratory relief regarding the interpretation of interest is granted. Costs awarded to the applicant, including costs of senior counsel on scale C.
Judges
Lamprecht
Legal Topics
Arbitration Act Section 31, Arbitration Award Enforcement, Contractual Interest, Interpretation of Awards, Compound Interest, Default Interest
Civil Procedure Commercial and Corporate Arbitration Act Section 31 Arbitration Award Enforcement Contractual Interest Interpretation of Awards Compound Interest Default Interest

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 9 Authorities cited 13 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

RSC Avelo (Pty) Ltd

Applicant

Trencon Construction (Pty) Ltd

Respondent

Dirk van Zyl N.O.

Respondent

Procedural Posture

Urgent Application / Application to Make Arbitration Award an Order of Court; Declaratory Relief Sought Regarding Interpretation of Interest Award

  1. 1 Whether the arbitration award regarding interest on late certification should be made an order of court.
  2. 2 What is the correct interpretation of the interest provision in paragraph 2 of the arbitration award.
  3. 3 Whether the subcontract provides for interest on late certification and the applicable rate and mechanism.

Ratio Decidendi

The court found that the arbitrator had determined the issue of interest and intended to award interest on the late certification of escalation amounts. The award must be interpreted as requiring interest to be calculated in terms of the subcontract, specifically at a rate of 160% of the repo rate, compounded monthly from the date payment was due until actual payment. The court rejected Trencon's argument that the subcontract did not provide for interest on late certification, holding that the arbitrator's intention was clear and enforceable. The jurisdictional challenge also failed, as interest was claimed and formed part of the issues submitted to arbitration. Remittal was unnecessary...

Court Disposition

Application granted. The arbitration award is made an order of court. Declaratory relief regarding the interpretation of interest is granted. Costs awarded to the applicant, including costs of senior counsel on scale C.

Orders

  • The amended final award dated 26 October 2021 (amended 8 November 2021) of the arbitrator is made an order of court in terms of section 31(1) of the Arbitration Act 42 of 1965.
  • It is declared that paragraph 2 of the award means interest at the rate of 160% of the repo rate is payable on the escalation amounts of R2,647,829.17, compounded monthly from the date for payment until actual payment, as calculated in the spreadsheet annexed to the founding affidavit.