Rutherford Enza Civils (Pty) Ltd and Others v Bokpoort EPC Consortium (Pty) Ltd (2015/30655) [2016] ZAGPJHC 264 (6 September 2016)

Rutherford Enza Civils (Pty) Ltd and Others v Bokpoort EPC Consortium (Pty) Ltd (2015/30655) [2016] ZAGPJHC 264 (6 September 2016)

The court found that the probabilities favour the inclusion of the appendices as part of the contract, given the references within the contract and the nature of the construction project. However, there remains doubt, and the matter could be clarified at trial. As a result, the plaintiffs have not proven that the...

Source-derived case information.

Citation
[2016] ZAGPJHC 264
Parties
Plaintiff: Rutherford Enza Civils (Pty) Ltd (in liquidation); Plaintiff: Chavonnes Badenhorst St Clair Cooper N.O.; Plaintiff: Lebogang Michael Moloto N.O.; Plaintiff: Ezekiel Phetola Maenetja N.O.; Defendant: Bokpoort EPC Consortium (Pty) Ltd
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
2015/30655
Procedural Posture
Provisional Sentence Application / Judgment on Provisional Sentence Application
Outcome
Provisional sentence refused; costs reserved for action to be instituted.
Judges
Roland Sutherland
Legal Topics
Provisional Sentence, Rule 8 Compliance, Arbitration Clause, Construction Contracts
Civil Procedure Commercial and Corporate Provisional Sentence Rule 8 Compliance Arbitration Clause Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Rutherford Enza Civils (Pty) Ltd (in liquidation)

Plaintiff

Chavonnes Badenhorst St Clair Cooper N.O.

Plaintiff

Lebogang Michael Moloto N.O.

Plaintiff

Ezekiel Phetola Maenetja N.O.

Plaintiff

Bokpoort EPC Consortium (Pty) Ltd

Defendant

Procedural Posture

Provisional Sentence Application / Judgment on Provisional Sentence Application

  1. 1 Whether the plaintiffs have complied with Rule 8(3) by attaching all documents upon which the claim is founded.
  2. 2 Whether the appendices, including the arbitration clause, form part of the contract between the parties.
  3. 3 Whether the arbitration clause ousts the jurisdiction of the court in favour of arbitration.

Ratio Decidendi

The court found that the probabilities favour the inclusion of the appendices as part of the contract, given the references within the contract and the nature of the construction project. However, there remains doubt, and the matter could be clarified at trial. As a result, the plaintiffs have not proven that the full contract was attached to the summons, and Rule 8(3) has not been fulfilled. Furthermore, the arbitration clause in the appendices privileges arbitration as the process for resolving disputes between the parties. Consequently, the application for provisional sentence fails, and costs are reserved for the action to be instituted.

Court Disposition

Provisional sentence refused; costs reserved for action to be instituted.

Orders

  • Provisional sentence is refused.
  • The costs occasioned by the provisional sentence proceedings shall be costs in the action to be instituted by the plaintiffs against the defendant, such action to be commenced within 90 days of date of this judgment.