SA Metal & Machinery Co (Pty) Ltd v Spanjaard Ltd and Another (26092/07) [2009] ZAGPJHC 96 (16 April 2009)

SA Metal & Machinery Co (Pty) Ltd v Spanjaard Ltd and Another (26092/07) [2009] ZAGPJHC 96 (16 April 2009)

The court found that the plaintiff's version was more plausible and credible than that of the second defendant. There was no agreement permitting cancellation on 30 days notice, and the second defendant failed to prove that such notice was given. The evidence showed that the second defendant repudiated the contract...

Source-derived case information.

Citation
[2009] ZAGPJHC 96
Parties
Applicant: SA Metal & Machinery Co (Pty) Ltd; Respondent: Spanjaard Ltd; Respondent: Coppermet SA (Pty) Ltd
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
26092/07
Procedural Posture
Civil Trial / Judgment After Trial
Outcome
Judgment for the plaintiff against the second defendant for damages arising from breach of contract.
Judges
Willis
Legal Topics
Breach of Contract, Repudiation, Damages Quantification, Contractual Terms, Notice of Termination
Commercial and Corporate Breach of Contract Repudiation Damages Quantification Contractual Terms Notice of Termination

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 14 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

SA Metal & Machinery Co (Pty) Ltd

Applicant

Spanjaard Ltd

Respondent

Coppermet SA (Pty) Ltd

Respondent

Procedural Posture

Civil Trial / Judgment After Trial

  1. 1 Whether the contract between the plaintiff and the second defendant included a term permitting cancellation on 30 days notice.
  2. 2 Whether the second defendant lawfully repudiated the contract by refusing to take delivery of copper as agreed.
  3. 3 Whether the plaintiff is entitled to damages for breach of contract.

Ratio Decidendi

The court found that the plaintiff's version was more plausible and credible than that of the second defendant. There was no agreement permitting cancellation on 30 days notice, and the second defendant failed to prove that such notice was given. The evidence showed that the second defendant repudiated the contract by refusing to take delivery of copper as agreed. The plaintiff was entitled to damages calculated as the difference between the contract price and the price obtained after repudiation. The court also held that joining the first defendant was not reckless, given the close relationship between the defendants, and no adverse cost order was warranted against the plaintiff for this...

Court Disposition

Judgment for the plaintiff against the second defendant for damages arising from breach of contract.

Orders

  • The second defendant is to pay the plaintiff the sum of R593,537.15 as damages for breach of contract entered into on or about 13 April 2007.
  • Interest on the aforesaid sum at 15.5% per annum from 29 October 2007 to date of payment.