Sasol South Africa Limited v Association of Mineworkers and Construction Union and Another (2025/029924) [2025] ZALCJHB 113 (18 March 2025)

Sasol South Africa Limited v Association of Mineworkers and Construction Union and Another (2025/029924) [2025] ZALCJHB 113 (18 March 2025)

The court found that the certificate of outcome was not stale, as the delay was not unreasonable and the parties had engaged in ongoing negotiations. However, the dispute between AMCU and Sasol was intrinsically linked to the implementation of the 4-shift work system. Once Sasol suspended the 4-shift system, the...

Source-derived case information.

Citation
[2025] ZALCJHB 113
Parties
Applicant: Sasol South Africa Limited; Respondent: Association of Mineworkers and Construction Union (AMCU); Respondent: The individuals listed in Annexure 'A'
Court
Labour Court Johannesburg
Jurisdiction
South Africa
Case Number
2025/029924
Procedural Posture
Urgent Application / Return Date of Rule Nisi; Confirmation of Interim Interdict
Outcome
Rule nisi confirmed; strike interdicted; no order as to costs.
Judges
Tlhotlhalemaje
Legal Topics
Protected Strike, Mutual Interest Dispute, Shift Allowance, Strike Interdict, Certificate of Outcome, Rights Vs Interests
Labour Law Civil Procedure Protected Strike Mutual Interest Dispute Shift Allowance Strike Interdict Certificate of Outcome Rights Vs Interests

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2
Sign in to unlock

Parties

Sasol South Africa Limited

Applicant

Association of Mineworkers and Construction Union (AMCU)

Respondent

The individuals listed in Annexure 'A'

Respondent

Procedural Posture

Urgent Application / Return Date of Rule Nisi; Confirmation of Interim Interdict

  1. 1 Whether the certificate of outcome issued by the NBCCI was stale and could be relied upon for protected strike action.
  2. 2 Whether the dispute between AMCU and Sasol was a dispute of right or mutual interest for purposes of strike action.
  3. 3 Whether the dispute had been resolved by the suspension of the 4-shift work system and if any live dispute remained to justify strike action.

Ratio Decidendi

The court found that the certificate of outcome was not stale, as the delay was not unreasonable and the parties had engaged in ongoing negotiations. However, the dispute between AMCU and Sasol was intrinsically linked to the implementation of the 4-shift work system. Once Sasol suspended the 4-shift system, the underlying cause for AMCU's demands fell away, and no live dispute remained to justify strike action. The court held that AMCU could not demand the implementation of the 4-shift system as a right, and any demands related to it were matters of mutual interest only when the system was in operation. As the 4-shift system was suspended at the time of the strike notice, there was no...

Court Disposition

Rule nisi confirmed; strike interdicted; no order as to costs.

Orders

  • The Rule Nisi granted by this Court on 7 May 2025 is confirmed.
  • There is no order as to costs.