Sasol South Africa (Pty) Ltd v Murray and Roberts Power and Energy and Another (42863/18; 41910/18) [2020] ZAGPJHC 415 (14 January 2020)

Sasol South Africa (Pty) Ltd v Murray and Roberts Power and Energy and Another (42863/18; 41910/18) [2020] ZAGPJHC 415 (14 January 2020)

The court found that the validity of PMC200 was raised and considered in both adjudication and arbitration proceedings. The arbitrator did not exceed his powers in determining the validity of PMC200, as the pleadings and evidence required consideration of whether PMC200 was a valid instruction in accordance with the...

Source-derived case information.

Citation
[2020] ZAGPJHC 415
Parties
Applicant: Sasol South Africa (Pty) Ltd; Respondent: Murray and Roberts Power and Energy; Respondent: LTC Harms N.O.
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
42863/18; 41910/18
Procedural Posture
Review Application / Judgment on Review and Enforcement Applications
Outcome
Application for partial review of the arbitrator's award dismissed with costs; enforcement application granted with costs; arbitral award made an order of court.
Judges
Windell
Legal Topics
Arbitration Act 42 of 1965, Contractual Dispute Resolution, Jurisdiction of Arbitrator, Enforcement of Arbitral Award, Construction Contracts
Commercial and Corporate Alternative Dispute Resolution Arbitration Act 42 of 1965 Contractual Dispute Resolution Jurisdiction of Arbitrator Enforcement of Arbitral Award Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Sasol South Africa (Pty) Ltd

Applicant

Murray and Roberts Power and Energy

Respondent

LTC Harms N.O.

Respondent

Procedural Posture

Review Application / Judgment on Review and Enforcement Applications

  1. 1 Whether the arbitrator had jurisdiction to determine the validity of Project Manager's Communication 200 (PMC200).
  2. 2 Whether PMC200 constituted a valid instruction under the contract.
  3. 3 Whether the failure to refer a dispute regarding PMC200 to adjudication timeously barred the Contractor from disputing its validity.

Ratio Decidendi

The court found that the validity of PMC200 was raised and considered in both adjudication and arbitration proceedings. The arbitrator did not exceed his powers in determining the validity of PMC200, as the pleadings and evidence required consideration of whether PMC200 was a valid instruction in accordance with the contract. The jurisdictional point was not raised at the first available opportunity and was conceded to have no merit during argument. The arbitrator's finding that PMC200 was not a valid instruction and that the signed timesheets were binding between the parties was supported by the evidence. The court held that the application for partial review of the arbitrator's award...

Court Disposition

Application for partial review of the arbitrator's award dismissed with costs; enforcement application granted with costs; arbitral award made an order of court.

Orders

  • The application for the partial review of the arbitrator's award is dismissed with costs.
  • The enforcement application is granted with costs.