Sasol South Africa (Pty) Ltd v Murray & Roberts Limited (425/2020) [2021] ZASCA 94 (28 June 2021)

Sasol South Africa (Pty) Ltd v Murray & Roberts Limited (425/2020) [2021] ZASCA 94 (28 June 2021)

The Supreme Court of Appeal held that the adjudicator's decision on Dispute 16 was contractually binding and enforceable against Sasol. The adjudicator acted within his powers by reviewing the project manager's refusal to implement the arbitration award and applying the principles established by the arbitrator. The...

Source-derived case information.

Citation
[2021] ZASCA 94
Parties
Appellant: Sasol South Africa (Pty) Ltd; Respondent: Murray & Roberts Limited
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Judgment Date
28 June 2021
Case Number
425/2020
Procedural Posture
Civil Appeal / Appeal From Gauteng Division of the High Court, Johannesburg
Outcome
Appeal dismissed with costs; order of the high court varied to reflect amounts still due.
Judges
Saldulker, Zondi, Ledwaba, Gorven, Potterill
Legal Topics
Construction Contracts, Arbitration Award Enforcement, Adjudication Procedure, Contractual Obligation, Interest on Judgments
Commercial and Corporate Civil Procedure Construction Contracts Arbitration Award Enforcement Adjudication Procedure Contractual Obligation Interest on Judgments

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 10
Sign in to unlock

Parties

Sasol South Africa (Pty) Ltd

Appellant

Murray & Roberts Limited

Respondent

Procedural Posture

Civil Appeal / Appeal From Gauteng Division of the High Court, Johannesburg

  1. 1 Whether the adjudicator's decision on Dispute 16 is contractually binding and enforceable against Sasol.
  2. 2 Whether the adjudicator acted within his jurisdiction and powers in revising prior decisions based on the arbitration award.
  3. 3 Whether the adjudicator's decision was invalid due to alleged procedural defects, including timing and receipt of information.

Ratio Decidendi

The Supreme Court of Appeal held that the adjudicator's decision on Dispute 16 was contractually binding and enforceable against Sasol. The adjudicator acted within his powers by reviewing the project manager's refusal to implement the arbitration award and applying the principles established by the arbitrator. The timing and receipt of additional information were permitted under the adjudicator's contract, which prevailed in case of conflict with the construction contract. Sasol's procedural objections regarding jurisdiction and timing were rejected, as the adjudicator delivered his decision within the required period after the end of the information-gathering process. Sasol's refusal to...

Court Disposition

Appeal dismissed with costs; order of the high court varied to reflect amounts still due.

Orders

  • The respondent (Sasol) is ordered to make immediate payment to the applicant (Murray & Roberts) of the specified amounts plus VAT.
  • The respondent is ordered to pay interest on the amounts set out above plus VAT from 10 June 2019 to date of payment, calculated daily at the prime lending rate of ABSA Bank and compounded annually.