Sbahle Fire Services CC v Passenger Rail Agency of South Africa (42209/2012) [2018] ZAGPPHC 657 (29 August 2018)

Sbahle Fire Services CC v Passenger Rail Agency of South Africa (42209/2012) [2018] ZAGPPHC 657 (29 August 2018)

The court found that, after considering all the circumstances and evidence presented at trial, there are no reasonable prospects that another court would reach a different conclusion. Accordingly, the application for leave to appeal was dismissed with costs.

Citation
[2018] ZAGPPHC 657
Parties
Applicant: Sbahle Fire Services CC; Respondent: Passenger Rail Agency of South Africa
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Judgment Date
29 August 2018
Case Number
42209/2012
Procedural Posture
Leave to Appeal / Application for Leave to Appeal After Trial Judgment
Outcome
Application for leave to appeal dismissed with costs.
Judges
Raulinga
Legal Topics
Leave to Appeal, Prospects of Success, Costs Order

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Sbahle Fire Services CC

Applicant

Passenger Rail Agency of South Africa

Respondent

Procedural Posture

Leave to Appeal / Application for Leave to Appeal After Trial Judgment

  1. 1 Whether there are reasonable prospects that another court would reach a different conclusion.
  2. 2 Whether leave to appeal should be granted.

Ratio Decidendi

The court found that, after considering all the circumstances and evidence presented at trial, there are no reasonable prospects that another court would reach a different conclusion. Accordingly, the application for leave to appeal was dismissed with costs.

Court Disposition

Application for leave to appeal dismissed with costs.

Orders

  • The application for leave to appeal is dismissed.
  • The applicant is ordered to pay the costs of the application.