Scaw Wire and Strand, a division of Scaw Metals SA (Pty) Ltd v National Union of Metal Workers Union of South Africa and Others (J32/2011) [2011] ZALCJHB 47 (25 May 2011)

Scaw Wire and Strand, a division of Scaw Metals SA (Pty) Ltd v National Union of Metal Workers Union of South Africa and Others (J32/2011) [2011] ZALCJHB 47 (25 May 2011)

The court found that the union's demand was vague and unlawful, as it failed to provide sufficient particulars regarding the alleged inconsistent application of the disciplinary code and grievance procedure. The applicant had made repeated requests for clarification, which were ignored by the union. Disciplinary...

Source-derived case information.

Citation
[2011] ZALCJHB 47
Parties
Applicant: Scaw Wire and Strand, a division of Scaw Metals SA (Pty) Ltd; Respondent: National Union of Metal Workers of South Africa and Others
Court
Labour Court Johannesburg
Jurisdiction
South Africa
Case Number
J32/2011
Procedural Posture
Urgent Application / Final Order After Urgent Unopposed Application
Outcome
Final interdict granted; strike declared unlawful and unprotected; costs awarded against respondents.
Judges
Molahlehi
Legal Topics
Unprotected Strike, Lawful Demand, Disciplinary Procedure, Urgent Interdict
Labour Law Civil Procedure Unprotected Strike Lawful Demand Disciplinary Procedure Urgent Interdict

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 5 Party arguments 2
Sign in to unlock

Parties

Scaw Wire and Strand, a division of Scaw Metals SA (Pty) Ltd

Applicant

National Union of Metal Workers of South Africa and Others

Respondent

Procedural Posture

Urgent Application / Final Order After Urgent Unopposed Application

  1. 1 Whether the intended strike action by the union was lawful and protected under the Labour Relations Act.
  2. 2 Whether the demand forming the basis of the strike was sufficiently clear and lawful.
  3. 3 Whether the applicant was entitled to urgent relief and a final interdict against the strike.

Ratio Decidendi

The court found that the union's demand was vague and unlawful, as it failed to provide sufficient particulars regarding the alleged inconsistent application of the disciplinary code and grievance procedure. The applicant had made repeated requests for clarification, which were ignored by the union. Disciplinary action had already been taken against the relevant employees, and the union's demand for further action was not lawful. The procedures for protected strike action under the Labour Relations Act were not properly followed, and the intended strike was therefore unlawful and unprotected. The applicant satisfied the requirements for urgent relief, including urgency, irreparable harm,...

Court Disposition

Final interdict granted; strike declared unlawful and unprotected; costs awarded against respondents.

Orders

  • The applicant's non-compliance with rules relating to service and time periods is condoned and the matter is dealt with as one of urgency.
  • The industrial action intended by the respondents on 17 January 2011 or thereafter is declared unlawful and unprotected.