Schauman Builders CC v MEC: Department of Roads and Public Works, Northern Cape and Another (734/2016) [2016] ZANCHC 60 (11 November 2016)

Schauman Builders CC v MEC: Department of Roads and Public Works, Northern Cape and Another (734/2016) [2016] ZANCHC 60 (11 November 2016)

The court found that the Department followed a two-stage tender process, with the closing date for submission of bills of quantities extended to 3 or 4 December 2015. This extension resulted in a new validity period of 90 days from the extended closing date, as provided for in the CIDB Standard Conditions of Tender....

Source-derived case information.

Citation
[2016] ZANCHC 60
Parties
Applicant: Schauman Builders CC; Respondent: MEC: Department of Roads and Public Works, Northern Cape; Respondent: Kobus Duvenhage Builders (Pty) Ltd
Court
Northern Cape High Court, Kimberley
Jurisdiction
South Africa
Case Number
734/2016
Procedural Posture
Review Application / Final Judgment on Review Application After Interim Interdict
Outcome
Application for review dismissed with costs.
Judges
Olivier, Erasmus
Legal Topics
Public Procurement, Tender Validity Period, Judicial Review of Administrative Action, Preferential Procurement Policy Framework Act, Construction Industry Development Board Act, Interim Interdict
Administrative Law Civil Procedure Commercial and Corporate Public Procurement Tender Validity Period Judicial Review of Administrative Action Preferential Procurement Policy Framework Act Construction Industry Development Board Act +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 13 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Schauman Builders CC

Applicant

MEC: Department of Roads and Public Works, Northern Cape

Respondent

Kobus Duvenhage Builders (Pty) Ltd

Respondent

Procedural Posture

Review Application / Final Judgment on Review Application After Interim Interdict

  1. 1 Whether the closing date for submission of bills of quantities constituted a new closing date or an extension of the initial closing date.
  2. 2 What effect an extended closing date would have on the validity period of the tender.
  3. 3 Whether the award of the tender contract to Duvenhage Builders should be set aside and the tender re-advertised.

Ratio Decidendi

The court found that the Department followed a two-stage tender process, with the closing date for submission of bills of quantities extended to 3 or 4 December 2015. This extension resulted in a new validity period of 90 days from the extended closing date, as provided for in the CIDB Standard Conditions of Tender. The evidence, including departmental reports and meeting minutes, supported the respondent's version that the validity period was properly extended and the award was made within the valid period. The applicant failed to provide a complete record or rebut the respondent's version. The application for review was dismissed as the applicant did not establish that the validity...

Court Disposition

Application for review dismissed with costs.

Orders

  • The application for review is dismissed with costs.
  • In respect of the urgent application for the interim interdict issued on 29 April 2016, the applicant and the first respondent will each pay its own costs.