Sebenza Construction BK v Nkosi (184/2004) [2007] ZAGPHC 217 (21 September 2007)
- Citation
- [2007] ZAGPHC 217
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- High Courts - Gauteng
- Panel
- T.J. Raulinga, C. Pretorius
- Case number
- 184/2004
More details
- Court
- High Courts - Gauteng
- Panel
- T.J. Raulinga, C. Pretorius
- Case number
- 184/2004
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The appeal succeeded because the magistrate erred in accepting an unsubstantiated amount based on the respondent's evidence, which was not supported by documentation or proper computation. The respondent failed to prove the extent or quantum of defective work and did not institute a counter-claim. The appellant established its entitlement to the contract balance, less the admitted amount for unfinished work. The court held that the appellant was prevented from completing the work and that the quantification for additional work and incomplete performance was reasonable. The respondent's evidence was contradictory and unsupported, and issues not pleaded could not be relied upon. The appellant's claim was upheld, and the respondent was ordered to pay the contract balance with interest and costs.
Court disposition
Appeal upheld with costs; respondent ordered to pay contract balance and interest.
Orders
- The respondent must pay the appellant R96,000.00 with interest.
- Interest tempore morae applies.
- The respondent must pay the costs of the appeal on a party and party scale.
02
Material facts
Parties
Sebenza Construction BK
AppellantSam Nkosi
RespondentAmounts and remedies
- Contract Balance Awarded: ZAR 96,000
03
Procedural history
Posture
Civil Appeal / Appeal From Magistrate's Court
04
Questions and positions
Legal issues
- 01
Whether the appellant proved its entitlement to the claimed contract balance.
- 02
Whether the respondent established defective workmanship and the quantum thereof.
- 03
Whether the magistrate erred in awarding a thumb-sucked amount based on respondent's evidence.
- 04
Whether the absence of a counter-claim precluded the respondent from recovering for alleged defects.
Party arguments
- Applicant
- The appellant argued that a verbal contract was concluded for the erection of a chicken run at an agreed price of R320,000, with additional work valued at R16,441.44. The respondent paid R224,000 in two instalments, leaving a balance of R102,441.44, which was reduced for jurisdictional purposes. The appellant admitted R10,000 for unfinished work and claimed the respondent prevented completion. The appellant maintained that the additional work was properly quantified and reasonable, and that the respondent failed to prove any defects or their quantum.
- Respondent
- The respondent contended that the workmanship was defective and that he had to employ another contractor to rectify and complete the work. He disputed the contract price in pleadings but admitted it during trial. The respondent did not produce evidence of the quantum of defects nor did he institute a counter-claim. During cross-examination, he conceded owing R21,488.84, but this amount was not substantiated by documentation or computation.
05
Court’s reasoning
Legal principles
- 01
F & I Advisors (Edms) Bpk en ander v Eerste Nationale Bank van Suidelike Afrika Bpk [1998] ZASCA 65; 1999 (1) SA 515 (SCA) at 524H-525B/C
Issues must be formulated in pleadings; evidence not pleaded cannot be relied upon.
- 02
Bk Tooling v Scope Precision Engineering 1979 (1) SA 391 (A) at F-G
Where a creditor is prevented from completing reciprocal performance, he may claim performance subject to reduction, depending on contractual provisions.
- 03
Dalinga Beleggings (Pty) Ltd v Antina (Pty) Ltd 1979 (2) SA 56 (A)
A reasonable quantification for incomplete work may be accepted if properly computed.
- 04
Qwa-Qwa Regeringsdiens v Martin Harris & Seuns 2000 (3) SA 339 (A) at G-H
A claim for defective work requires a counter-claim and proof of quantum.
06
Ratio, limits and disposition
Ratio decidendi
The appeal succeeded because the magistrate erred in accepting an unsubstantiated amount based on the respondent's evidence, which was not supported by documentation or proper computation. The respondent failed to prove the extent or quantum of defective work and did not institute a counter-claim. The appellant established its entitlement to the contract balance, less the admitted amount for unfinished work. The court held that the appellant was prevented from completing the work and that the quantification for additional work and incomplete performance was reasonable. The respondent's evidence was contradictory and unsupported, and issues not pleaded could not be relied upon. The appellant's claim was upheld, and the respondent was ordered to pay the contract balance with interest and costs.
Obiter and limits
- Issues raised in evidence but not pleaded cannot be relied upon for judgment.
- A party alleging defective work must substantiate the quantum and institute a counter-claim.
- Thumb-sucked figures without computation or documentation are insufficient for judicial determination.
Court disposition
Appeal upheld with costs; respondent ordered to pay contract balance and interest.
- The respondent must pay the appellant R96,000.00 with interest.
- Interest tempore morae applies.
- The respondent must pay the costs of the appeal on a party and party scale.
Source and reliance status
High Courts - Gauteng
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
High Courts - Gauteng
Judgment
IN THE HIGH COURT OF SOUTH AFRICA (TRANSVAAL PROVINCIAL DIVISION)
CASE NO: 184/2004 APPEAL CASE NO.: A 1248/2005
In the matter between:
SEBENZA
CONSTRUCTION BK
Appellant
And
SAM
NKOSI
Respondent
JUDGEMENT
RAULINGA. AJ
[1] This is an appeal lodged by the appellant/plaintiff against a judgement of a
magistrate at Ermelo.
[2] Appellant, (a Construction Close Corporation) had issued summons
against Sam Nkosi, an adult male residing at De Goedehoop- Ermelo for
an amount of R 96 000, 00 which is an unpaid balance of the erection of a
not reportable
21 SEPTEMBER 2007
2
chicken run emanating from a verbal contract (location conduction operis) entered into between the two parties in 2003.
[3] The original price for the erection of the chicken run was R 320 000, 00.
The parties entered into another contract for the amount of R 16 441, 44 for additional work. Defendant paid plaintiff R 224 000, 00 in two equal instalments of R 112 000, 00 which means that there would remain a balance of R 102 441, 44 which was reduced to R 1000 00, 00 after an amount of R 2441, 44 was abandoned to found jurisdiction at the magistrate court, less R 10 000, 00 which was an amount due to the defendant for unfinished work.
[4] The contract price was in dispute, but the respondent further avers that
the workmanship was defective.
[5] In his pleadings the respondent contends that because the workmanship
of the appellant was defective he had to employ another contractor to rectify and finish the work. The respondent didn't institute a counter-claim.
[6] During cross-examination the respondent conceded that he owed the
Plaintiff an amount of R 21 488, 84. The magistrate relied on this piece of evidence and rejected the Appellant's case holding that the Appellant didn't prove its case on a balance of probabilities.
3
[7] The Respondent was a single witness. He didn't produce any proof as
evidence to show how the amount was computed. Appellant also called a single witness, who is a qualified builder with seventeen (17) years experience in building construction work. The Respondent could also not produce proof as to the extent of the defect.
[8] Although the Respondent in his pleadings denies that the contract price is
R 320 000, 00 he however admits this in his evidence during the trial. The Appellant avers that the amount of R 16 441 , 44 for additional construction work is reasonable, as well as the amount of R 10 000, 00 for unfinished
work.
[9] The Respondent has the onus to prove the extent of defective work and its
amounts. Respondent didn't call any witnesses to corroborate his contention that the work is defective, the court is not placed in a position to make such a finding.
[10] The Appellant has the onus to establish that it had done all that it was required to do in terms of the contract. However, Appellant alleges that it could not complete its work because it was prevented by the Respondent from doing so. Appellant admits that there was outstanding work quantified at R 10 000, 00. In his pleadings Respondent contends that
4
another contractor had to be hired to rectify and complete the defective work but during the trial he says that the other contractor had to complete outstanding work. This is a contradiction in terms.
[11] It is clear that a number of issues raised by the Respondent in his evidence were not raised in his pleadings. The general rule is that issues had to be formulated in pleadings. F & I Advisors (Edms) Bpk en ander v Eerste Nationale Bank van Suidelike Afrika Bpk [1998] ZASCA 65; 1999 (1) SA 515 (SCA) at 524H-525B/C.
[12] The appellant admits that the chicken-run was not completed and that
R 10 000, 00 was a reasonable amount under the circumstances.
Dalinga Beleggings (Pty) Ltd v Antina (Pty) Ltd 1979 (2) SA 56 (A). He further avers that he was prevented by the respondent from completing the work.
Bk Tooling v Scope Precision Engineering 1979 (1) SA 391 (A) at F-G. There can only be talk of breach of contract by more creditoris where such a demand has in fact been made. The Appellant made several demands _ Qwa-Qwa Regeringsdiens v Martin Harris & Seuns 2000 (3) 339 (A) at G-H.
[13] In location conduction operis, such as in casu, which is a reciprocal contract when a creditor is prevented from fully performing his own counter-performance by the failure of the other party's necessary co-
5
operation, he, despite his own incomplete performance, can claim performance by the other party, but, basically subject to reduction of the performance claimed. This will also depend upon the contractual provisions.
Bk Tooling v Scope Precision Engineering (EDMS) BPK, supra.
[14] In casu, the appellant made a computation of R 10 000, 00 for the incomplete part of the work as reasonable. He has also made a proper quantification of the amount for additional contract work. There is therefore no need for reduction.
[15] It can be mentioned that the magistrate couldn't have awarded an amount of R 21 488, 84 as the amount to which the appellant was entitled, since this amount was not properly computed, but was as a result of thumbsucking by the respondent during the trial. Furthermore, for the respondent to succeed in his claim, that the work was defective, he had to institute a counter-claim. The respondent didn't institute a counter-claim.
[16] It is my view, that the appellant's appeal against the judgement of the court a quo should be upheld with costs.
[17] It is therefore ordered that:
I agree,
6
(i) The respondent pays the appellant an amount of R 96 000, 00
with interest.
(ii) Interest tempore morae.
(ii) The respondent pays the costs of the appeal on a party and party scale.
T. J. RAULINGA ACTING JUDGE OF THE HIGH COURT
C.
PRETORIUS JUDGE OF THE HIGH COURT
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.