Sedtrade (Pty) Limited v Scarliweb (Pty) Ltd t/a Cooling Solutions Projects and Others (1953/2020) [2023] ZANCHC 38 (10 March 2023)
The court held that the adjudicator's decision, which found no penalty was due for the delay, was binding and immediately enforceable under the terms of the subcontracting agreement. The appellant was not entitled to deduct penalties from the respondents' claims, and the procedural argument regarding amendment or supplementary affidavit was rejected. The court found that the dispute had been fully ventilated through adjudication and that the respondents were entitled to payment. The quantum of payment could be determined by the parties based on the certificates and adjudication outcome. The appeal was dismissed and the judgment of the court a quo upheld.
- Citation
- [2023] ZANCHC 38
- Parties
- Appellant: Sedtrade (Pty) Limited; Respondent: Scarliweb (Pty) Ltd t/a Cooling Solutions Projects; Respondent: Roburn Construction CC; Respondent: Sol Plaatjie University; Respondent: AECOM South Africa; Respondent: Standard Bank of South Africa Ltd
- Court
- Northern Cape High Court, Kimberley
- Jurisdiction
- South Africa
- Judgment Date
- 10 March 2023
- Case Number
- 1953/2020
- Procedural Posture
- Civil Appeal / Appeal Against Judgment and Order of Court a Quo; Confirmation of Anti Dissipation Order and Payment Dispute
- Outcome
- Appeal dismissed; judgment of the court a quo upheld.
- Judges
- Lever, Nxumalo, Chwaro
- Legal Topics
- Construction Contracts, Adjudication Enforcement, Anti Dissipation Orders, Penalty Deductions, Urgent Application
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sedtrade (Pty) Limited
Appellant
Scarliweb (Pty) Ltd t/a Cooling Solutions Projects
Respondent
Roburn Construction CC
Respondent
Sol Plaatjie University
Respondent
AECOM South Africa
Respondent
Standard Bank of South Africa Ltd
Respondent
Procedural Posture
Civil Appeal / Appeal Against Judgment and Order of Court a Quo; Confirmation of Anti Dissipation Order and Payment Dispute
Legal Issues
- 1 Whether the court a quo was correct in ordering the appellant to pay amounts due to the first and second respondents despite no amended notice of motion or supplementary affidavit being filed after adjudication.
- 2 Whether the adjudicator's decision regarding penalty deductions was binding and immediately enforceable.
- 3 Whether the appellant was contractually entitled to deduct penalties for delay from the respondents' claims.
Ratio Decidendi
The court held that the adjudicator's decision, which found no penalty was due for the delay, was binding and immediately enforceable under the terms of the subcontracting agreement. The appellant was not entitled to deduct penalties from the respondents' claims, and the procedural argument regarding amendment or supplementary affidavit was rejected. The court found that the dispute had been fully ventilated through adjudication and that the respondents were entitled to payment. The quantum of payment could be determined by the parties based on the certificates and adjudication outcome. The appeal was dismissed and the judgment of the court a quo upheld.
Court Disposition
Appeal dismissed; judgment of the court a quo upheld.
Orders
- The appeal is dismissed.
- The appellant is ordered to pay the costs of the appeal.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment