Sekhukhune District Municipality v Bo-Mamohlala Projects CC and Others (60186/15, 60185/15, 60180/15) [2016] ZAGPPHC 206 (10 February 2016)
The court found that the tender process conducted by the Sekhukhune District Municipality was procedurally flawed and did not comply with the requirements of section 217 of the Constitution or the Supply Chain Management Policy. The Bid Evaluation Committee failed to evaluate each bid for responsiveness and functionality, and decisions were made without proper quorum. The Bid Adjudication Committee was not properly constituted, lacking the required senior supply chain management practitioner. The failure to properly consider the requirement for audited financial statements resulted in arbitrary disqualification of bidders. These irregularities rendered the process unfair, unreasonable,...
- Citation
- [2016] ZAGPPHC 206
- Parties
- Applicant: Sekhukhune District Municipality; Respondent: Bo-Mamohlala Projects CC; Respondent: Casnan Civils CC; Respondent: Kingki Electrical & DGCV JV; Respondent: Eternity Star Investments 231 CC; Respondent: HTE Construction CC; Respondent: Kgalemo Construction CC; Respondent: Khulani Trading Enterprises CC; Respondent: KSB Pumps and Values (Pty) Ltd; Respondent: Lebaka Construction (Pty) Ltd; Respondent: Madipadi Construction CC; Respondent: Mashaipane General Construction JA; Respondent: Kingki Electrical Contractors DGDC JV; Respondent: Mothakge Phadima Construction and Sanitary Work & White Hazy Building Construction JV
- Court
- North Gauteng High Court, Pretoria
- Jurisdiction
- South Africa
- Judgment Date
- 10 February 2016
- Case Number
- 60186/15, 60185/15, 60180/15
- Procedural Posture
- Review Application / Judgment
- Outcome
- Application granted; the tender process and awards are set aside and the procurement process must recommence.
- Judges
- Hughes
- Legal Topics
- Municipal Procurement, Tender Irregularity, Review of Administrative Action, Section 217 Constitution, Procedural Fairness
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sekhukhune District Municipality
Applicant
Bo-Mamohlala Projects CC
Respondent
Casnan Civils CC
Respondent
Kingki Electrical & DGCV JV
Respondent
Eternity Star Investments 231 CC
Respondent
HTE Construction CC
Respondent
Kgalemo Construction CC
Respondent
Khulani Trading Enterprises CC
Respondent
KSB Pumps and Values (Pty) Ltd
Respondent
Lebaka Construction (Pty) Ltd
Respondent
Madipadi Construction CC
Respondent
Mashaipane General Construction JA
Respondent
Kingki Electrical Contractors DGDC JV
Respondent
Mothakge Phadima Construction and Sanitary Work & White Hazy Building Construction JV
Respondent
Procedural Posture
Review Application / Judgment
Legal Issues
- 1 Whether the tender process for water supply infrastructure in Sekhukhune District Municipality complied with section 217 of the Constitution.
- 2 Whether the Bid Evaluation Committee and Bid Adjudication Committee followed the prescribed procedures under the Supply Chain Management Policy.
- 3 Whether the composition of the Bid Adjudication Committee was lawful.
Ratio Decidendi
The court found that the tender process conducted by the Sekhukhune District Municipality was procedurally flawed and did not comply with the requirements of section 217 of the Constitution or the Supply Chain Management Policy. The Bid Evaluation Committee failed to evaluate each bid for responsiveness and functionality, and decisions were made without proper quorum. The Bid Adjudication Committee was not properly constituted, lacking the required senior supply chain management practitioner. The failure to properly consider the requirement for audited financial statements resulted in arbitrary disqualification of bidders. These irregularities rendered the process unfair, unreasonable,...
Court Disposition
Application granted; the tender process and awards are set aside and the procurement process must recommence.
Orders
- The tender process pertaining to tender number SK8/3/1/16/2014/15 is declared unlawful and set aside.
- The fifteen awards in respect of such tender to all respondents are set aside.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment