The court found that the applicant failed to comply with the 15-day period stipulated in Rule 25(1) for filing a replication after service of the plea, and its explanations for the delay were inadequate and contradictory. The applicant's reliance on previous indulgences granted to the respondents and on section 173...

Source-derived case information.

Citation
[2025] ZANWHC 84
Parties
Applicant: Selogilwe Building Contractors CC; Respondent: MEC: Department of Co-Operative Governance, Human Settlements and Traditional Affairs: North West; Respondent: HOD: Department of Co-Operative Governance, Human Settlements and Traditional Affairs: North West Province
Court
North West High Court, Mafikeng
Jurisdiction
South Africa
Case Number
1296/2018
Procedural Posture
Urgent Application / Application for Upliftment of Bar and Condonation for Late Filing of Replication
Outcome
Application dismissed with costs, including costs of two counsel where so employed.
Judges
Mfenyana
Legal Topics
Condonation, Late Filing, Upliftment of Bar, Replication, Rule 25, Rule 32
Civil Procedure Condonation Late Filing Upliftment of Bar Replication Rule 25 Rule 32

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Selogilwe Building Contractors CC

Applicant

MEC: Department of Co-Operative Governance, Human Settlements and Traditional Affairs: North West

Respondent

HOD: Department of Co-Operative Governance, Human Settlements and Traditional Affairs: North West Province

Respondent

Procedural Posture

Urgent Application / Application for Upliftment of Bar and Condonation for Late Filing of Replication

  1. 1 Whether the applicant should be granted condonation for the late filing of its replication.
  2. 2 Whether the Bar preventing the applicant from filing a replication should be uplifted.
  3. 3 Whether the applicant has shown good cause for the delay and prospects of success.

Ratio Decidendi

The court found that the applicant failed to comply with the 15-day period stipulated in Rule 25(1) for filing a replication after service of the plea, and its explanations for the delay were inadequate and contradictory. The applicant's reliance on previous indulgences granted to the respondents and on section 173 of the Constitution was misplaced, as the Rules are clear and admit of no ambiguity. The applicant's conduct demonstrated a lack of diligence and bona fides, and the delay was not properly explained. The court held that condonation is not automatic and must be justified by good cause, which the applicant failed to establish. The respondents suffered prejudice due to prolonged...

Court Disposition

Application dismissed with costs, including costs of two counsel where so employed.

Orders

  • The application is dismissed with costs, including costs of two counsel where so employed.