Sentinel Mining Industry Retirement Fund and Another v Waz Props (Pty) Ltd and Another (779/11) [2012] ZASCA 124; 2013 (3) SA 132 (SCA) (21 September 2012)
The Supreme Court of Appeal held that clause 5 of the contract, read with options 1 and 3, imposed a resolutive condition that terminated the obligation to pay if the project was not completed by 1 April 2009. The court found that clause 4 was exhaustive of the methods of payment and that the obligation to pay did not survive the lapsing of the security. The court further held that commercial sense and the scheme of the contract required that a tacit term be incorporated into clause 5, such that the guarantee under option 2 would also lapse if the project was not completed by the specified date. The court rejected the respondents' argument that the obligation to pay survived and found...
- Citation
- [2012] ZASCA 124
- Parties
- Appellant: Sentinel Mining Industry Retirement Fund; Appellant: Fluxmans Attorneys Inc; Respondent: Waz Props (Pty) Ltd; Respondent: Werlex Properties (Pty) Ltd
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 21 September 2012
- Case Number
- 779/11
- Procedural Posture
- Civil Appeal / Appeal From South Gauteng High Court, Johannesburg
- Outcome
- Appeal dismissed with costs.
- Judges
- Cloete, Malan, Shongwe, Tshiqi, Southwood
- Legal Topics
- Contract Interpretation, Tacit Terms, Guarantee Liability, Resolutive Condition
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sentinel Mining Industry Retirement Fund
Appellant
Fluxmans Attorneys Inc
Appellant
Waz Props (Pty) Ltd
Respondent
Werlex Properties (Pty) Ltd
Respondent
Procedural Posture
Civil Appeal / Appeal From South Gauteng High Court, Johannesburg
Legal Issues
- 1 Whether clause 5 of the contract imposed a resolutive condition terminating the obligation to pay if the project was not completed by 1 April 2009.
- 2 Whether a tacit term should be incorporated into clause 5 to the effect that the guarantee under option 2 would lapse if the project was not completed by the specified date.
- 3 Whether the presentation of the guarantee for payment was valid after the project completion date had passed.
Ratio Decidendi
The Supreme Court of Appeal held that clause 5 of the contract, read with options 1 and 3, imposed a resolutive condition that terminated the obligation to pay if the project was not completed by 1 April 2009. The court found that clause 4 was exhaustive of the methods of payment and that the obligation to pay did not survive the lapsing of the security. The court further held that commercial sense and the scheme of the contract required that a tacit term be incorporated into clause 5, such that the guarantee under option 2 would also lapse if the project was not completed by the specified date. The court rejected the respondents' argument that the obligation to pay survived and found...
Court Disposition
Appeal dismissed with costs.
Orders
- The appeal is dismissed with costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment